IN FORCE Norms Committee — Engineering (Gr A / NC-II) Advance Authorisation 2009-07-21

DGFT Committee Minutes

Document text

RATIFIED MINUTES DIRECTORATE GENERAL OF FOREIGN TRADE (DES­II SECTION)   Minutes of the Norms Committee­II Meeting No. 16/10 held on 21.07.2009. The Meeting No. 16/10 of Norms Committee­II was held on 21.07.2009 for the licensing year 2009­2010 under the Chairmanship of  Sh.  O.P.  Hisaria,  Joint  Director  General  of  Foreign  Trade  (OPH)  to  consider  the  applications  under  Duty  Exemption  Scheme (Chapter­4) of Foreign Trade Policy 2004­2009. The following members were present in the meeting:­ S.No Name of the representatives & their Designation   Deptt.   1. Shri B.D. Ghosh, AIA M/o Steel   2. 3. 4. 5. Sh. S.K. Jain, D.O. Sh. N. L. Goswami, Sr. D.O. Shri A. K. Mishra, Asst IA Shri K. K. Funda, Asst. Director DIPP DHI M/o Steel DC(SSI) 6.   Shri Narendra Vashista, FTDO DGFT               The Committee took up the individual cases of the agenda of this meeting for discussion and the decision taken in respect of each case as follows: 1

Case No.:1134/26/81­ALC2/2007

Party Name:BHARAT ELECTRONICS LTD. Meet No/Date:16/81­ALC2/2009 21.07.2009 Status:Deffered and Re­ indexed HQ File :01/81/050/00573/AM06/ RLA File :07/24/040/00521/AM06/ Lic.No/Date:0710040666 05.10.2005 Defer Date:21.07.2009 Decision  :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DHI. The case stands deferred and to be re­listed on 15.09.2009.       2

Case No.:10/40/81­ALC2/2007

Party Name:OMEGA PRODUCTS PVT.LTD. 21.07.2009 Status:Deffered and Re­indexed

HQ File :01/81/050/00448/AM08/ RLA File :03/95/040/00838/AM08/ Lic.No/Date:0310450840 20.11.2007 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee  ­  II  in  its  M.N0.  16/81  held  on  21.07.2009.  The  committee  observed  the  firm  has  failed  to  furnish  the  requisite information despite several reminders and decided to reject the request of the firm.   R/A may take suitable consequential action accordingly.   3

Case No.:12/40/81­ALC2/2007

Party Name:POWER GEAR LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00450/AM08/ RLA File :07/24/040/00600/AM08/ Lic.No/Date:0710054616 22.11.2007 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. On the recommendation of the representative of DHI present in the meeting, it  was  decided  by  the  Committee  to  call  for  the  following  information/clarification  from  the  firm  and  to  re­list  the  case  on 15.09.2009: ­   1.      Whether the list of components sought for import is for one no. of export product instead of three no. and if it proposes to export only one no. of 14 KV Isolated Phase Busduct. 2.      List of import items given at the time of licence was for 3 nos. of export product , but now same list is given for 1 no. of export product – firm may clarify.       4

Case No.:5/12/81­ALC2/2008

Party Name:ASIATIC ELECTRICAL AND SWITCHGEAR PVT.LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00151/AM09/ RLA File :05/24/040/00142/AM09/ Lic.No/Date:0510222178 16.06.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Norms Committee, after deliberating upon the case, decided to call for some  information  in  respect  of  the  subject  advance  authorisation,  as  per  DHI    vide  their  U.O.  No.  3(16)/09/TSW(B)  dated 01.07.2009. (copy enclosed). The case stands deferred and to be relisted on 15.09.2009.     5

Case No.:3/19/81­ALC2/2008

Party Name:POWER GEAR LTD. 21.07.2009 Status:Deffered and Re­indexed

HQ File :01/81/050/00288/AM09/ RLA File :07/24/040/00140/AM09/ Lic.No/Date:0710058261 01.07.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. On the recommendation of the representative of DHI present in the meeting, it  was  decided  by  the  Committee  to  call  for  the  following  information/clarification  from  the  firm  and  to  re­list  the  case  on 15.09.2009: ­   1.      Weight of Aluminium items required to be welded.     6

Case No.:12/17/81­ALC2/2008

Party Name:POWER GEAR LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00259/AM09/ RLA File :07/24/040/00151/AM09/ Lic.No/Date:0710058414 09.07.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DHI. The case stands deferred and to be re­listed on 15.09.2009.       7

Case No.:37/17/81­ALC2/2008

Party Name:VIJAI ELECTRICALS LTD 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00284/AM09/ RLA File :09/24/040/00156/AM09/ Lic.No/Date:0910034716 21.07.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DHI. The case stands deferred and to be re­listed on 15.09.2009.     8

Case No.:12/23/81­ALC2/2008

Party Name:ALSTOM PROJECTS INDIA LIMITED, 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00346/AM09/ RLA File :03/94/040/00407/AM09/ Lic.No/Date:0310483438 22.08.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.

9

Case No.:13/23/81­ALC2/2008

Party Name:FLUIDTHERM TECHNOLOGY P LTD 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00347/AM09/ RLA File :04/24/040/00131/AM09/ Lic.No/Date:0410098141 22.08.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Norms Committee, after deliberating upon the case, decided to ratify the  norms  in  respect  of  the  subject  advance  authorisation,  as  per  written  comments  of  DHI    vide  their  U.O.  No. 3(69)/2009/TSW(B) dated 26.05.2009. (copy enclosed).       10

Case No.:12/25/81­ALC2/2008

Party Name:ASIATIC ELECTRICAL AND SWITCHGEAR PVT.LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00380/AM09/ RLA File :05/24/040/00387/AM09/ Lic.No/Date:0510227339 11.09.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.   11

Case No.:5/29/81­ALC2/2008

Party Name:BHUSHAN STEEL LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00422/AM09/ RLA File :05/24/040/00350/AM09/ Lic.No/Date:0510228478 29.09.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited by M/o Steel and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.   12

Case No.:41/29/81­ALC2/2008

Party Name:JSW STEEL LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00458/AM09/ RLA File :03/94/040/00476/AM09/ Lic.No/Date:0310490039 13.10.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited by M/o Steel and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.

13

Case No.:7/34/81­ALC2/2008

Party Name:UTV SOFTWARE COMMUNICATIONS LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00504/AM09/ RLA File :05/24/040/00488/AM09/ Lic.No/Date:0510230376 05.11.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the comments from I&B are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 15.09.2009.   14

Case No.:8/36/81­ALC2/2008

Party Name:AJMERA REALTY & INFRA INDIA LTD 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00523/AM09/ RLA File :31/24/040/00193/AM09/ Lic.No/Date:3110036110 17.11.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited by M/o Steel and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.   15

Case No.:9/36/81­ALC2/2008

Party Name:AJMERA REALTY & INFRA INDIA LTD 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00524/AM09/ RLA File :31/24/040/00206/AM09/ Lic.No/Date:3110036111 17.11.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited by M/o Steel and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.     16

Case No.:6/40/81­ALC2/2008

Party Name:VIDEOCON INDUSTRIES LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00604/AM09/ RLA File :03/95/040/00528/AM09/ Lic.No/Date:0310497526 12.12.2008 Defer Date:21.07.2009

Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Norms Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorisation, as per written comments of MIT  vide their U.O. No. 17(19)/2009­IPHW dated 05.06.2009. (copy enclosed).     17

Case No.:8/40/81­ALC2/2008

Party Name:MINEX METALLURGICAL COMPANY LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00606/AM09/ RLA File :03/95/040/00711/AM09/ Lic.No/Date:0310497822 15.12.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Norms Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorisation, as per written comments of M/o Steel  vide their U.O. No. 2(8)/2006­ TW dated 10.06.2009. (copy enclosed).     18

Case No.:24/40/81­ALC2/2008

Party Name:CHANDAN STEEL LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00622/AM09/ RLA File :03/94/040/00747/AM09/ Lic.No/Date:0310498393 17.12.2008 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Norms Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorisation, as per written comments of M/o Steel  vide their U.O. No. 2(13)/2006­ TW Vo. II dated 09.06.2009. (copy enclosed).     19

Case No.:6/48/81­ALC2/2008

Party Name:SUZLON ENERGY LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00711/AM09/ RLA File :31/24/040/00296/AM09/ Lic.No/Date:3110037214 03.02.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the comments from C&PC are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 15.09.2009.

20

Case No.:18/48/81­ALC2/2008

Party Name:CHANDAN STEEL LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00723/AM09/ RLA File :03/94/040/00980/AM09/ Lic.No/Date:0310505840 05.02.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Norms Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorisation, as per written comments of M/o Steel  vide their U.O. No. 2(13)/2006­ TW Vo. II dated 09.06.2009. (copy enclosed).     21

Case No.:21/48/81­ALC2/2008

Party Name:BHANSALI CABLES & CONDUCTORS (P) LTD., 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00726/AM09/ RLA File :05/24/040/00346/AM09/ Lic.No/Date:0510235990 06.02.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DIPP. The case stands deferred and to be re­listed on 15.09.2009.       22

Case No.:22/48/81­ALC2/2008

Party Name:ALCAN COMPOSITES INDIA PVT. LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00727/AM09/ RLA File :03/94/040/00913/AM09/ Lic.No/Date:0310505986 06.02.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.   23

Case No.:1/9/81­ALC2/2009

Party Name:LLOYD INSULATIONS (INDIA) LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00036/AM10/ RLA File :05/24/040/00065/AM10/ Lic.No/Date:0510241176 12.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.

24

Case No.:2/9/81­ALC2/2009

Party Name:BHARATH AUTO INDUSTRIES, 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00037/AM10/ RLA File :31/21/040/00022/AM10/ Lic.No/Date:3110038394 13.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands deferred and to be relisted on 15.09.2009.     25

Case No.:3/9/81­ALC2/2009

Party Name:ADVANCE CABLE TECHNOLOGIES PVT.LTD, 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00038/AM10/ RLA File :07/24/040/00012/AM10/ Lic.No/Date:0710064738 14.05.2009 Defer Date:21.07.2009 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. Based on the recommendations of the representative of DIPP present in the  meeting,  the  Norms  Committee,  after  deliberating  upon  the  case,  decided  to  ratify  the  norms  in  respect  of  the  subject Advance Authorisation as per following modification:­   1.      Quantity of import item at S.No.1 may be allowed as 65826 Kgs. inclusive of a  wastage of 1%. 2.      Quantity of import item at S.No.2 may be allowed as 27340 Kgs. on net to net basis as claimed by the firm. 3.      Quantity of import item at S.No.3 may be allowed as applied for i.e. 1181 Kgs. inclusive of a wastage of 5%. 4.      Quantity of import item at S.No.4 may be allowed as applied for i.e. 45646 Kgs. inclusive of a wastage of 2%.     26

Case No.:4/9/81­ALC2/2009

Party Name:SOURIAU INDIA PRIVATE LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00039/AM10/ RLA File :10/24/040/00015/AM10/ Lic.No/Date:1010033657 15.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited by MIT and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be relisted on 15.09.2009.

27

Case No.:5/9/81­ALC2/2009

Party Name:ABB LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00040/AM10/ RLA File :07/24/040/00062/AM10/ Lic.No/Date:0710064774 15.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm or the status if AA has been issued on net to net basis. The case stands deferred and to be relisted on 15.09.2009.   28

Case No.:6/9/81­ALC2/2009

Party Name:SHIVALIK BIMETAL CONTROLS LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00041/AM10/ RLA File :05/24/040/00081/AM10/ Lic.No/Date:0510241570 15.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands deferred and to be relisted on 15.09.2009.   29

Case No.:7/9/81­ALC2/2009

Party Name:HOSLEY INDIA PRIVATE LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00042/AM10/ RLA File :05/24/040/00087/AM10/ Lic.No/Date:0510241591 15.05.2009 Defer Date:21.07.2009 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. Based on the recommendations of the representative of DC(SSI) present in the meeting, the Norms Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject Advance Authorisation as per following modification:­   1.            The quantity of import item and its  quantity may allowed as  102995 Kgs inclusive of 2 % wastage.         30

Case No.:10/9/81­ALC2/2009

Party Name:PEARL INSULATIONS PVT. LIMITED 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00045/AM10/ RLA File :07/24/040/00669/AM09/ Lic.No/Date:0710064852 19.05.2009 Defer Date:21.07.2009

Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands deferred and to be relisted on 15.09.2009.   31

Case No.:8/9/81­ALC2/2009

Party Name:CORDS CABLE INDUSTRIES LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00043/AM10/ RLA File :05/24/040/00069/AM10/ Lic.No/Date:0510241686 19.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee  ­  II  in  its  M.N0.  16/81  held  on  21.07.2009.  On  the  recommendation  of  the  representative  of  DIPP  present  in  the meeting, it was decided by the Committee to call for the following information/clarification from the firm and to re­list the case on 15.09.2009: ­   1. Information in respect of item at S.No.  12  of Standard Deficiency Format.     32

Case No.:9/9/81­ALC2/2009

Party Name:ADITYA VIDYUT APPLIANCES LTD., 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00044/AM10/ RLA File :03/94/040/00066/AM10/ Lic.No/Date:0310520414 19.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DHI. The case stands deferred and to be re­listed on 15.09.2009.       33

Case No.:11/9/81­ALC2/2009

Party Name:PRAKASH STEELAGE LTD. 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00046/AM10/ RLA File :03/95/040/00846/AM09/ Lic.No/Date:0310520480 20.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands deferred and to be relisted on 15.09.2009.

34

Case No.:12/9/81­ALC2/2009

Party Name:ITP INFOTECH PRIVATE LTD 21.07.2009 Status:Deffered and Re­indexed HQ File :01/81/050/00047/AM10/ RLA File :05/24/040/00102/AM10/ Lic.No/Date:0510241847 20.05.2009 Defer Date:21.07.2009 Decision :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee decided to refer a copy of the application of the  firm to MIT for examination and comments. The case stands deferred and to be re­listed on 15.09.2009.       PART –A ­DEFFER   S.No 9

Case No.A  ­ 285

M/s P.P.Rolling Mills Mfging Co.Pvt.Ltd.New Delhi Meeting No.16/81 F.No.01/81/162/1072 /AM08/DES­II Dated: 21­07­2009 Advance Licence No 0510212239    dt  19­11­2007              RLA F.No.05/24/40/649/am08               Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the reply from the firm is still awaited by MIT despite many reminders and therefore decided to issue a final reminder the firm to expedite the reply. If no reply is received within 15 days from the issue of the letter the case will be rejected and no representations in the matter will be entertained. The case stands deferred and to be relisted on 15.09.2009.         PART –AR –DEFFER   S.No.25

Case No. AR­36

 M/S Walchandnagar Industries Ltd., Pune           Meeting No.16/81 F.No.01/81/162/851/AM06/DES­II Dated 21­07­2009 Advance Licence No.3110023394  dt. 23.12.2005           RLA F.No.31/95/42/0042/AM06 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II  in  its  M.N0.  16/81  held  on  21.07.2009.  The  committee  decided  to  get  the  quantities  inputs  to  be  verified  by  The  Nuclear  Power Corporation. The case stands deferred and to be relisted on 15.09.2009.

PART –C­ DEFFER   S.No.23

Case No.C­36

M/s  Sahney Commutators Pvt.Ltd.Bangalaore Meeting No.16/81 F.No.01/81/162/968/AM08/DES­II Dated: 21­07­2009               Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DHI. The case stands deferred and to be re­listed on 15.09.2009.   S.No.24

Case No.C­37

M/s  Sahney Commutators Pvt.Ltd.Bangalaore Meeting No.16/81 F.No.01/81/162/967/AM08/DES­II Dated: 21­07­2009               Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee observed that the case is under examination of DHI. The case stands deferred and to be re­listed on 15.09.2009.   S.No.25

Case No. C­32

 M/S Technova Imaging Systems P.Ltd.Mumbai            Meeting No.16/81 F.No.01/81/162/311/AM09/DES­II Dated 21­07­2009        Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee decided to transfer the case to NC­I as the matter pertains to them.       PART ­D – DEFFER S.No.5

Case No D­1

 M/S Nagreeka Foils Ltd.,Mumbai Through EEPC,Kolkata            Meeting No.16/81 F.No.01/81/162/648/AM09/DES­II Dated 21­07­2009   Decision  :  The  case  regarding  fixation  of  DEPB  rates  for  item  covered  under  SION  S.No.  C­1711  was  considered  by  the  Norms Committee ­ II in its M.N0. 16/81 held on 21.07.2009. The committee decided to call for the current data from EEPC. The case stands deferred and to be re­listed on 15.09.2009.