Agenda for Approval Committee meeting for SEZ Pune Cluster to be held on 28 March 2024. — 08-midc-pune-sez
SEEPZ SPECIAL ECONOMIC ZONE ANDHERI (EAST), MUMBAI.
AGENDA FOR
MEETING OF THE APPROVAL COMMITTEE FOR SECTOR SPECIFIC SPECIAL ECONOMIC ZONE FOR IT/ITES AT PUNE OF MIDC-SEZ
DATE : 28.03.2024
TIME : 11:00 A.M.
MEETING OF THE APPROVAL COMMITTEE FOR SECTOR SPECIFIC SPECIAL ECONOMIC ZONE FOR IT/ITES AT PUNE, UNDER THE CHAIRMANSHIP OF DEVELOPMENT COMMISSIONER, SEEPZ-SEZ ON 28.03.2024 INDEX
Agenda Item No.
Subject
Agenda Item No. 01: - Confirmation of the Minutes of the meeting held on 29.02.2024 Agenda Item No. 02: - Application for Approval of List of Material submitted by M/s. Nxtra Data Ltd. (Co-Developer) Agenda Item No. 03 :- Application for approval of setting up of cafeteria and appointment of vendors submitted by M/s. Infosys Ltd. Agenda Item No. 04:- Application for setting up of Rooftop Non-Conventional Solar Power Plant within SEZ unit and availing Duty benefits submitted by M/s. Tudip Technologies Pvt. Ltd. Agenda Item No. 05 :- Application for setting up of Rooftop Non-Conventional Solar Power Plant within SEZ unit and availing Duty benefits submitted by M/s. TCS Ltd. Agenda Item No. 06 :- Application for approval of Change in shareholding pattern M/s. Bion Clinicals Pvt Ltd.
GOVT.OF INDIA, OFFICE OF THE ZONAL DEVELOPMENT COMMISSIONER, SEEPZ-SEZ (PUNE CLUSTER)
AGENDA NOTE FOR CONSIDERATION OF THE APPROVAL COMMITTEE
a. Proposal: -
Application of M/s. Nxtra Data Limited, Co- Developer, located at Plot No.
13/10A, 28, MIDC, Rajiv Gandhi Infotech Park, Phase-III, Hinjewadi, Pune
411057 for approval of List of Material for operations and maintenance of
Data Center Building for authorized Operation.
b. Specific Issue on which decision of Approval Committee is required: -
Approval for List of material required for operations and maintenance of Data
Center Building for authorized operation totally valued at Rs. 1,89,79,002/-
c. Relevant Provisions: -
As per Rule 12 (2) of SEZ Rules, 2006 “The Developer shall make an
application, after obtaining approval for the authorized operation
under rule 9, to the Development Commissioner, along with the list of
goods and services, including machinery, equipments and construction
material required for the authorized operations, duly certified by a
Chartered Engineer for approval by the Approval Committee”.
d. List of Materials for Authorized Operations :
Sr. No. List of materials required for the below mentioned Authorized operations Estimated value for Goods
purchased from DTA (Amount in Rs.) Estimated value for
Goods purchased from Import (Amount in Rs.) Estimated Total Value of Goods (Amount in Rs.)
Operations
and Maintenance 1,89,79,002 0.00 1,89,79,002
TOTAL 1,89,79,002 0.00
Detail List of Material is as follows: Estimated material cost (in Rs.) Sr No Description of Item Unit QTY Rate Total 1 COD sensor Nos 1
5,85,000.00
5,85,000.00 2 BOD sensor Nos 1
2,25,000.00
2,25,000.00 3 Free chlorine sensor Nos 1
1,65,500.00
1,65,500.00 4 Hardness sensor Nos 1
1,40,800.00
1,40,800.00 File No.S-SEZ-PRO0MIDC/19/2022-JDCP I/4082/2024 347
5 Flow sensor Nos 2
1,78,000.00
3,56,000.00 6 TSS sensor Nos 1
1,83,450.00
1,83,450.00 7 TDS Sensor Nos 1
1,35,750.00
1,35,750.00 8 HMI sensor hardware integration Nos 1
9,870.00
9,870.00 9 IOT sensor hardware integration Nos 1
22,000.00
22,000.00 10 Automatic chemical dosing system Nos 1
1,73,200.00
1,73,200.00 11 Supply of 2" UPVC Pipe Line from water source to sensor location Inlet & Outlet Line Rmt 30
318.00
9,540.00 12 Supply of 1" CPVC Pipe Line from from water source to sensor location Inlet & Outlet Line Rmt 30
204.00
6,120.00 13 Pipe Line Road Crossing and Outer Area Civil Work Rmt 30
532.00
15,960.00 14 Supply of 2" CPVC Valve Nos 25
1,000.00
25,000.00 15 Supply of 1" CPVC Valve Nos 20
319.00
6,380.00 16 Supply of aluminum armored cable 350x50 mm from HT Room to Sensor location Rmt 35
233.00
8,155.00 17 Supply of G.I cable tray 30x50x50 mm Nos 20
248.00
4,960.00 18 Supply of Colour Coated Sheet Shed with Structure, Including Painting & Finishing Work Complete SQFT 50
245.00
12,250.00 19 Supply of Cable Tray M.S. Angle Structure Kg 25
363.00
9,075.00 20 Supply of sensor Foundation Meter3 5
8,850.00
44,250.00 21 Supply of Synthetic enamel paint for structure painting Kg 10
322.00
3,220.00 22 Water transfer pump HP 2
24,750.00
49,500.00 23 water/chemical tank L 300
7.70
2,310.00 24 Set of Miscellaneous Fittings (FTA, MTA, socket, solvent, , clamp, T, union, etc.) Set 2
3,370.00
6,740.00 25 Sensor consumables Nos/mo nth 8
1,490.00
1,43,040.00 26 Sensor calibration (COD, BOD, Nos/mo 8
File No.S-SEZ-PRO0MIDC/19/2022-JDCP I/4082/2024 348
TSS, Chlorine, Hardness) nth 1,988.00 1,90,848.00 27 Flow sensor calibration Nos/mo nth 8
495.00
47,520.00 28 IOT dashboard Nos/mo nth 8
2,000.00
1,92,000.00 29 SITC of Battery termination junction box with SMPS and relay board Nos 8
65,200.00
5,21,600.00 30 Phillips LED Lights 36W Nos 500
875.00
4,37,500.00 31 Phillips LED Lights 34W Nos 100
2,615.00
2,61,500.00 32 BACnet Controller [5000 Points]- with SMA, inclusive of MQTT and JSON toolkit Nos 2
6,46,048.00
12,92,096.00 33 OPC DA converter: MQTT - OPC DA gateway [5000 Points], Nos 10
2,66,500.00
26,65,000.00 34 Client PC- Windows Desktop to connect to BMS Network for remote access to our Controller Nos 1
78,000.00
78,000.00 35 Vibration Sensor Nos 8
15,600.00
1,24,800.00 36 Panel Enclosure Nos 12
19,500.00
2,34,000.00 37 Extensions bow/8 Module with 5A Switch (1) and (3) Nos 12
2,600.00
31,200.00 38 Lan Patch Cable 3M Nos 36
390.00
14,040.00 39 Lan Patch Cable 1M Nos 24
195.00
4,680.00 40 Insulation Tape Nos 57
20.00
1,140.00 41 Cable Ties (small) Nos 22
130.00
2,860.00 42 Cable Ties (Medium) Nos 12
195.00
2,340.00 43 Cable Ties (Large) Nos 12
260.00
3,120.00 44 Network Switch 4 Port Nos 12
7,800.00
93,600.00 45 2 core Communication cable Meters 200
45.00
9,000.00 46 Panel Support channel (Other Misc) Set 1
70,200.00
70,200.00 47 Supply of Siemens Siepan ACB Vertical
- 415V, 4000A, 50kA/1Sec from 3B Type2 Seismic Zone-3, IP42 -Siemens 3WL ACB with UV Coil. Nos 4
14,42,000.00
57,68,000.00 File No.S-SEZ-PRO0MIDC/19/2022-JDCP I/4082/2024 349
48 Supply of Siemens LOGO PLC for Auto Changeover Logic Nos 4
1,50,000.00
6,00,000.00 49 Supply of 3.5cx300 Sq.mm AL. Armd. FRLS Cable Mtr 1975
1,677.85
33,13,753.75 50 Supply of End Termination of 3.5Cx300sq.mm Al.Armd Cable Nos 126
2,745.05
3,45,876.30 51 Supply of 1000x75mm Ladder type cable tray Mtr 50
1,427.15
71,357.50 52 Supply of Steel support KG 200
97.75
19,550.00 53 Supply of GI Earth Strip LS 1
5,750.00
5,750.00 54 Supply of 12cx1.5Sq.mm Cu.Armd. FRLS insulated cable along with End Termination Mtr 480
488.75
2,34,600.00
TOTAL
1,89,79,001.55
e. Other Information: - • M/s. Nxtra Data Limited, Co- Developer has been granted Letter of Approval No. F.2/129/2005-SEZ dated 14.12.2017 • The Co-Developer has submitted List of Materials duly certified by the Chartered Engineer Makarand Kulkarni, (Registration No. 093577-0 dated 17.02.2006) dated 19.03.2024 for Operation and Maintenance which is authorized operation for development of their SEZ located at M/s. Nxtra Data Limited, Co- Developer, Plot No. 13/10A, 28, MIDC, Rajiv Gandhi Infotech Park, Phase-III, Hinjewadi, Pune 411 057. • The Co-Developer has informed that the list of material required for providing Infrastructural facilities in the aforesaid sector Specific SEZ for Information Technology/Information Technology Enabled Services (IT/ITES) which is authorized operation for development of their SEZ in the aforesaid sector specific SEZ for IT /ITES. • The total value of said materials is Rs. 1,89,79,002/- • SO has been requested vide letter dated 20.03.2024 to submit verification report and SO’s vide his verification report dated 26.03.2024 has submitted that, the Co-Developer has Bond Balance of Rs. 64,37,59,905 which is sufficient for the procurement of Indigenous material of estimated value of Rs.1,89,79,002/-. Accordingly, the list of material is in order, the CE vide his letter dated 19.03.2024 have also certified that, these materials are required for Authorized Operations of M/s. Nxtra Data Ltd. (Co-Developer) and hence the request of Co-Developer may be considered.
f. ADC’s Observation : -
• Approval Committee may kindly consider the request of the Co-Developer for approval of list of material as per Rule 12(2) of SEZ Rules, 2006.
******************
File No.S-SEZ-PRO0MIDC/19/2022-JDCP I/4082/2024 350
GOVT. OF INDIA, OFFICE OF THE DEVELOPMENT COMMISSIONER, SEEPZ-SEZ (PUNE CLUSTER)
AGENDA NOTE FOR CONSIDERATION OF THE APPROVAL COMMITTEE
a. Proposal:
Proposal submitted by M/s. Infosys Limited (Unit III), Ascendas – SEZ, Building Cypress, Floor 6 to 8, International Tech Park, Plot No. 18, MIDC- IT/ITES-SEZ, Rajiv Gandhi Infotech Park, Phase III, Hinjewadi, Pune-411 057, for approval of setting up of cafeteria and appointment of service provider in the Cafeteria in the SEZ Unit Premises.
b. Specific issue on which decision of Approval Committee is required:
Approval of the Committee for setting up of cafeteria and appointment of service provider in the cafeteria, as detailed below:
Sr. No. Name of the Vendor Activity Location Area. 1 M/s. MDP Food & Beverage Pvt Ltd having office address at No. 295, 11th Cross Happy Valley
Layout Uttarahalli. Bengaluru Urban 560061. To operate and will be serving tea, Coffee Refreshment
and supply of pre-cooked food to Infosys SEZ Unit Employees. Lower Ground Floor of Angsana Building at Ascendas IT Park, Plot No. 18, Rajiv Gandhi Infotech
Park, Hinjewadi, Phase III, MIDC Pune 411057. 11,497 Sq. ft
c. Relevant Provision:
As per para 3 of Instruction No.95 dated 11.06.2019 ‘3. The issue was examined in this department and with the approval of competent authority, it is conveyed that the same could be allowed subject to the following conditions. The facilities as envisaged under the proviso to Rule 11(5) of the SEZ Rules could also be created by a Unit for its exclusive use subject to obtaining a NOC from the Developer as well as necessary NOCs/ clearances/approvals from the relevant statutory authorities. The units shall not be eligible for any exemptions, drawback, concessions or any other benefits available under Section 7 or Section 26 of SEZ Act, for creating of operating such facilities.
d. Other Information: - • M/s. Infosys Limited has been granted LOA No. SEEPZ-SEZ/MIDC-SEZ/IL Unit III/63/2018-19/136 dated 07.08.2018. • Location of the Unit: M/s. Infosys Limited, Ascendas SEZ Unit III Building Cypress, Floor 6 to 8, International Tech Park, Plot No. 18, MIDC-IT/ITES- SEZ, Rajiv Gandhi Infotech Park, Phase III, Hinjewadi, Pune-411 057 • Date of commencement of authorized operation: 01.08.2019 • LOA valid up to: 31.07.2024 File No.S-SEZ-PRO0MIDC/26/2022-JDCP I/4068/2024 128
• The unit vide their letter dated 06.03.2024 had requested for approval of setting up of cafeteria and appointment of service provider. • The unit has submitted that:
- The Unit and the service provider will not be taking any duty benefits on the procurement related to Cafeteria.
- The unit shall provide space as mentioned above.
- The vendor will be serving Tea, Coffee, Refreshments and will bring the pre-cooked food to their employees of the Unit. • In support of the above unit has submitted the following documents: • Copy of Fire NOC of the building • Copy of NOC from Co-Developer • Copy of GST Certificate of Vendor • Copy of FSSAI Certificate
d. ADC’s Recommendations:
•
Approval Committee may kindly consider the proposal for setting up of
cafeteria and appointment of service provider in the cafeteria, in terms of
para 3 of Instruction No.95 dated 11.06.2019 issued by MOC&I.
File No.S-SEZ-PRO0MIDC/26/2022-JDCP I/4068/2024 129
GOVT. OF INDIA, OFFICE OF THE ZONAL DEVELOPMENT COMMISSIONER, SEEPZ – SEZ (PUNE CLUSTER)
AGENDA NOTE FOR CONSIDERATION OF THE APPROVAL COMMITTEE
a. Proposal :
Proposal submitted by M/s Tudip Technologies Pvt. Ltd., IT/ITES SEZ
Unit Located at Plot No. 11/2, MIDC-IT-ITES-SEZ, Hinjewadi, Pune for granting duty exemption for procurement of material w.r.t. installation of Rooftop Non- Conventional Solar Plant in SEZ Unit premises.
b. Previous Reference:
During the Approval Committee meeting held on 09.02.2024, the committee
approved the proposal of M/s Tudip Technologies Pvt. Ltd for setting up of
Roof Top Non-Conventional Solar Power plant for Captive consumption in
terms of Office Memorandum dated 07.06.2021 issued in addendum to
Power Guidelines dated 16.02.20216 issued by MOC&I amounting to Rs.
75,04,027/- (including 13.8 % taxes) having capacity of 138.24 KW.
Accordingly approval letter was issued to the Unit dated 20.02.2024.
Now, MOC&I has issued Officer Memorandum dated 07.03.2024 stating that, “Duty benefits under Section 26 of SEZ Act, 2005 is allowed to the units for installation as well as O&M of renewable energy equipment exclusively for captive consumption of the unit with a specific condition that the power shall not be wheeled out to DTA.” c. Current Application: -
In view of the O.M. dated 07.03.2024, issued by MOC&I, the unit vide their letter dated 11.03.2024 has requested for permission to avail duty benefits for installation of Rooftop Non-conventional Solar power Plant at their SEZ unit against the approval letter dated 20.02.2024 issued to them. The unit also informed that, they have not procured any material required for the installation of Non-conventional Solar Power Plant. d. Report of The Specified Officer:
In respect of the application of the Unit dated 11.03.2024, the specified officer was requested to submit the verification report. The Specified Officer vide his letter dated 20.03.2024 has submitted the verification report and informed that the unit has not procured any material w.r.t. Solar Power Plant. e. Specific Issue on which decision of Approval Committee is required:
Approval of the Committee for installation of Rooftop Non-conventional Solar power Plant, for captive consumption with availing of duty benefits, for captive consumption in terms of Office Memorandum dated 07.03.2024 issued by MOC&I as detailed below: File No.S-SEZ-PRO0MIDC/1/2024-JDCP I/4077/2024 23
1 Name of the Vendor of Solar Power Plant Shree Solar Tech 2 Vendor-Service Design, Supply, Installation & Commissioning of Rooftop Solar power 3 Capacity 138.24 KW 4 Annual Generation in capacity 166000 KWH 5 Total Expenditure for Installation of 138.24KW Solar Power Plant. (Rs. 47,700 * 138.24 = Rs.65,94,048/- Rs. 65,94,048/-
f. Relevant provisions:
As per MO&I’s O.M. dated 07-03-2024 issued under F. No. K-43014(16)/8/2020-
SEZ:
“The undersigned is directed to refer to the subject mentioned above and to
state that in Partial modification of Power Guidelines issued vide this
Department’s O.M. of even No. dated 07.06.2021, it is conveyed that the Duty
benefits under Section 26 of SEZ Act, 2005 is allowed to the Units for
Installation as well as O & M of renewable energy equipment exclusively for
captive consumption of the Unit with specific condition that the power shall
not be wheeled out to DTA.”
g. Other Information:
•
LOA No. SEEPZ-SEZ/MIDC-SEZ/TTPL/67/2019-20/ dated 08.03.2019 &
29.03.2020 (Original LOA & Addition of Location)
•
Location: Plot No. 11/2, Lower Ground Floor, Ground & First Floor, MIDC-IT-
ITES-SEZ, RGIP, Hinjewadi, Phase III, Pune 411057.
•
Date of Commencement of Production: 16.01.2020
•
Validity of LOA: 15.01.2025
•
The Unit has submitted that:
a. Copy of Approval for Installation of Solar Plant.
b. Copy of Power Guidelines amendment vide No. K-43014(16)/8/2020-SEZ
dated 07.03.2024.
c. The said Solar Power Plant shall be set up exclusively for captive
consumption purpose only.
h. ADC Observations :
• The Approval committee may kindly consider the proposal of the unit for installation of rooftop Non-conventional Solar power Plant, for captive consumption with availing of duty benefits, in terms of MOC&I O.M. issued under F.No.K-43014(16)/8/2020-SEZ dated 07.03.2024.
File No.S-SEZ-PRO0MIDC/1/2024-JDCP I/4077/2024 24
GOVT. OF INDIA, OFFICE OF THE ZONAL DEVELOPMENT COMMISSIONER, SEEPZ – SEZ (PUNE CLUSTER)
AGENDA NOTE FOR CONSIDERATION OF THE APPROVAL COMMITTEE
a. Proposal :
Request of M/s Tata Consultancy Services Ltd., IT/ITES SEZ Unit
Located at Plot No. 5, Rajiv Gandhi Infotech Park, Hinjewadi, Phase III, Pune
411057 for granting duty exemption for procurement of material w.r.t. installation
of Rooftop Non-Conventional Solar Plant in SEZ Unit premises.
b. Previous Reference:
During the Approval Committee held on 09.02.2024, approved the proposal
of
M/s Tata Consultancy Services Ltd., for setting up of Roof Top Non-Conventional
Solar Power plant for Captive consumption in terms of Office Memorandum dated
07.06.2021 issued in addendum to Power Guidelines dated 16.02.20216 issued by
MOC&I amounting to Rs. 1,35,00,000/- (including 13.8 % taxes) having capacity of
264 KWP. Accordingly approval letter was issued to the Unit dated 20.02.2024.
Now, MOC&I has issued Officer Memorandum dated 07.03.2024 stating that, “Duty benefits under Section 26 of SEZ Act, 2005 is allowed to the units for installation as well as O&M of renewable energy equipment exclusively for captive consumption of the unit with a specific condition that the power shall not be wheeled out to DTA.” c. Current Application: - In view of the O.M. dated 07.03.2024, issued by MOC&I, the unit vide their letter dated 19.03.2024 has requested for permission to avail duty benefits for installation of Rooftop Non-conventional Solar power Plant at their SEZ unit against the approval letter dated 20.02.2024 issued to them. The unit has informed that, they have received certain goods against the Delivery Challans (as supply being against a work order) for installation of Non-Conventional Solar Plant. d. Report of The Specified Officer: In respect of the application of the Unit dated 19.03.2024, the specified officer was requested to submit the verification report. The Specified Officer vide his letter dated 26.03.2024 has submitted the verification report and informed that the unit has procured 05 line items as given below by Delivery challan under non-benefit:
Sr.No DC No
Date of
entry
Description of Items
Qty.
Value
1
10
06/03/24
Equipment of Solar Power
plant
1 lot
12,86,100
2
11
13/03/24
SS Fastner
1 lot
68,140
3
15
13/03/24
Cement Bags
40 Nos
12,000
4
18
18/03/24
Khadi and Crush Sand
8 Brass
40,000
5
2340102353 20/03/24
Equipment of Solar Power
493 Nos
47,09,511
File No.S-SEZ-PRO0MIDC/15/2022-JDCP
I/4083/2024
243
Plant Total Rs.61,15,751
e. Specific Issue on which decision of Approval Committee is required: Approval of the Committee for installation of Rooftop Non-conventional Solar power Plant, for captive consumption with availing of duty benefits, for captive consumption in terms of Office Memorandum dated 07.03.2024 issued by MOC&I as detailed below: 1 Name of the Vendor of Solar Power Plant M/s Kirloskar Solar Technologies Pvt Ltd. 2 Vendor-Service Engineering, Procurement, Commissioning of Complete Solar Power Plant. 3 Capacity 264 KWP 4 Annual Generation in capacity 2,59,573 kWP/Year 5 Total Expenditure for Installation of 264 KWP Solar Power Plant. (Rs. 1,35,00,000/- (less Rs.. 61,15,751/-(material already delivered under non-benefit) = Rs. 73,84,249/- Rs. 73,84,249/-
f. Relevant provisions:
As per MO&I’s O.M. dated 07-03-2024 issued under F. No. K-43014(16)/8/2020- SEZ,:
“The undersigned is directed to refer to the subject mentioned above and to
state that in Partial modification of Power Guidelines issued vide this
Department’s O.M. of even No. dated 07.06.2021, it is conveyed that the Duty
benefits under Section 26 of SEZ Act, 2005 is allowed to the Units for
Installation as well as O & M of renewable energy equipment exclusively for
captive consumption of the Unit with specific condition that the power shall
not be wheeled out to DTA.”
g. Other Information:
•
LOA No. SEEPZ-SEZ/MIDC-SEZ/TCSL/50/2014-15/05554 dated
01.03.2018 (Original LOA)
•
Location: Plot No. 5, MIDC-IT-ITES-SEZ, Rajiv Gandhi Infotech Park, Phase
III, Hinjewadi, Pune 411057.
•
Date of Commencement of Production: 20.01.2020
•
Validity of LOA: 19.01.2025
•
The Unit has submitted that:
a. They are proposing to install 264 KWP solar power generation system.
b. The Solar modules will be installed on roof top of their building at (Tower 1 &
Tower 2) located at Plot No. Plot No. 5, MIDC-IT-ITES-SEZ, Rajiv Gandhi
Infotech Park, Phase III, Hinjewadi, Pune 411057.
c. The said Solar Power Plant shall be set up exclusively for captive
File No.S-SEZ-PRO0MIDC/15/2022-JDCP
I/4083/2024
244
consumption purpose only. d. The said solar power plant will be set up by their vendor i.e. M/s Kirloskar Solar Technologies Pvt. Ltd., in accordance to the revised power guidelines.
h. ADC Observations :
• The Approval committee may kindly consider the proposal of the unit for installation of rooftop Non-conventional Solar power Plant, for captive consumption with availing of duty benefits, in terms of MOC&I O.M. issued under F.No.K-43014(16)/8/2020-SEZ dated 07.03.2024.
File No.S-SEZ-PRO0MIDC/15/2022-JDCP I/4083/2024 245
GOVT. OF INDIA, OFFICE OF THE ZONAL DEVELOPMENT COMMISSIONER, SEEPZ – SEZ (PUNE CLUSTER)
AGENDA NOTE FOR CONSIDERATION OF APPROVAL COMMITTEE
a. Proposal: - Application submitted by M/s. Bion Clinicals Pvt Ltd., IT/ITES unit located in Ground floor, Saicon Infratek Pvt Ltd – SEZ Co-Developer, Plot Mo. 25-6- A, Rajiv Gandhi Infotech Park, MIDC-SEZ, Phase III, Hinjewadi, Pune 411057 for Change in Shareholding Pattern.
b. Specific Issue on which decision of Approval Committee is required: -Approval of the Committee for Change in Shareholding Pattern in terms of Instruction No. 109 dated 18.10.2021, as detailed below:
Existing Shareholding Pattern before Transfer of Shares. Sr. No. Name of the Equity shareholders No. of Shares Value % 01 Sachin Shivajirao Mane 5000 50,000.00 50 02 Deepak Gangadhar Bagde 5000 50,000.00 50
Total 10,000 1,00,000.00 100
Proposed Shareholding Pattern after Transfer of Shares. Sr. No. Name of the Equity shareholders No. of Shares Value % 01 Sachin Shivajirao Mane 4500 45,000.00 45 02 Deepak Gangadhar Bagde 4500 45,000.00 45 03 Mrs Leena Harish Rathi 500 5000.00 5 04 Mrs Smita Sachin Mane 500 5000.00 5
Total 10,000 1,00,000.00 100
c. Relevant provisions: - As per para (i) of Instruction no. 109, dated 18.10.2021,
“Reorganization including change of name, Change of Shareholding pattern, business transfer arrangements, court approved mergers and demergers, change of constitution, Change of Directors, etc. may be undertaken by the Unit Approval Committee (UAC) concerned subject to the condition that the Developer/Co-developer/ Unit shall not opt out or exit out of the Special Economic Zone and continues to operate as a going concern. All liabilities of the Developer/Co-Developer/Unit shall File No.S-SEZ-PRO0MIDC/29/2022-JDCP I/4070/2024 258
remain unchanged on such reorganization.” …
d. Other Information: - • M/s. Bion Clinicals Pvt Ltd., IT/ITES units located in Ground floor, Developed by Saicon Infratek Pvt Ltd – Co-Developer, Plot Mo. 25-6-A, Rajiv Gandhi Infotech Park, MIDC-SEZ, Phase III, Hinjewadi, Pune 411057 • DCP: 01.06.2023 • LOA valid till: 31.05.2028 • The Unit has submitted following documents
- Copy of SEZ On line Application (OnLine Request Id : 422400095213)
- Copy of Board’s Resolution for transfer of Shares;
- Copy of all Letter of Approval;
- CA/CS certified Shareholding Pattern before and after transfer of share;
- Share transfer deed in Form SH 4 duly executed both by the transferor and transferee;
- Consent letter for transfer of shares;
- Undertaking as per Instruction 109.
• Reason for change in shareholding pattern:
The Unit has submitted that the change in Shareholding Pattern of the Company is due to transfer of Shares.
d. ADC’s Observation: • Approval Committee may consider the proposal of the unit for Change in shareholding pattern due to transfer of Shares, in terms of Instruction no. 109 issued by MOC&I.
File No.S-SEZ-PRO0MIDC/29/2022-JDCP I/4070/2024 259
Verbatim extracted text (OCR/PDF). Older scans and tables may show extraction artifacts — verify against the original for anything you act on.
No analysis has been generated for this document yet.