RATIFIED MINUTES   DIRECTORATE GENERAL OF FOREIGN TRADE (DES­II SECTION)   MINUTES OF THE NORMS COMMITTEE­II MEETING NO. 16/81 SCHEDULED TO BE HELD ON 20.07.2010 BUT ACTUALLY HELD ON 27.07.2010.   The Meeting No. 16/81 of Norms Committee­II was held on 27.07.2010   for the licensing year 2010­2011 under the Chairmanship of Sh. V.K. Srivastava, Addl. Director General of Foreign Trade to consider the following applications for ratification of norms in respect of advance authorisations  under  Duty  Exemption  Scheme  (Chapter­4)  of  Foreign  Trade  Policy  2009­2014.  The  following  members  were  present  in  the meeting:­ S.No Name of the representatives & their Designation   Deptt.   1. 2. 3. 4. 5. 6.   Sh. B.D. Ghosh, Jt. IA Sh. Gajraj Singh, Sr. D.O. Sh. S.K. Jain, DO Sh. K.K.Funda, Asst. Dir. Sh. Shyam Sunder, DDG Sh. Narendra Vashista, FTDO   MOS DHI DIPP M/o Steel DGFT DGFT     1

Case No.:30/29/81­ALC2/2008

Party Name:STERLITE INDUSTRIES (INDIA) LTD. Meet No/Date:16/81­ALC2/2010 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00447/AM09/ RLA File :35/24/040/00018/AM09/ Lic.No/Date:3510024830 10.10.2008 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.     2

Case No.:2/32/81­ALC2/2008

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00468/AM09/ RLA File :35/24/040/00049/AM08/ Lic.No/Date:3510024905 Defer

17.10.2008 Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.   3

Case No.:20/27/81­ALC2/2010

Party Name:ABB LIMITED 20.07.2010 Status:Approved HQ File :01/81/050/00202/AM10/ RLA File :07/21/040/00757/AM09/ Lic.No/Date:0710061858 22.12.2008   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Norms Committee decided to ratify the norms in respect of the subject advance authorization, as per written comments of DHI vide their U.O No. 3(97)/2009/TSW(B)/352 dated 19.07.2010 (copy enclosed).   R/A may take suitable consequential action accordingly.   4

Case No.:3/44/81­ALC2/2008

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00663/AM09/ RLA File :35/24/040/00023/AM09/ Lic.No/Date:3510025556 05.01.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.     5

Case No.:5/44/81­ALC2/2008

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00665/AM09/ RLA File :35/24/040/00024/AM09/ Lic.No/Date:3510025570 07.01.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.

6

Case No.:17/41/81­ALC2/2009

Party Name:RATNAVEER STAINLESS PRODUCTS (PVT) LTD, 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00402/AM10/ RLA File :34/24/040/00171/AM09/ Lic.No/Date:3410024452 12.06.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC observed that the value addition is 1%, whereas it has to be as per policy. Accordingly, it has been decided to seek clarification from the firm and RA. The case stands deferred and to be relisted on 24.08.2010.   7

Case No.:7/23/80­ALC2/2009

Party Name:BHARAT HEAVY ELECTRICALS LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/80/050/00329/AM10/ RLA File :05/24/040/00207/AM10/ Lic.No/Date:0510248210 24.08.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in  its  M.No.  16/81  scheduled  be  held  on  20.07.2010  but  actually  held  on  27.07.2010.  The  committee  observed  that  the  case  is  under examination of DHI. The case stands deferred and to be re­listed on 24.08.2010.     8

Case No.:1/26/81­ALC2/2009

Party Name:VIJAI ELECTRICALS LTD 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00177/AM10/ RLA File :09/24/040/00223/AM10/ Lic.No/Date:0910039304 16.09.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in  its  M.No.  16/81  scheduled  be  held  on  20.07.2010  but  actually  held  on  27.07.2010.  The  committee  observed  that  the  case  is  under examination of DHI. The case stands deferred and to be re­listed on 24.08.2010.   9

Case No.:7/33/81­ALC2/2009

Party Name:ALSTOM PROJECTS INDIA LIMITED, 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00286/AM10/ RLA File :03/94/040/00630/AM10/ Lic.No/Date:0310544190 05.11.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in  its  M.No.  16/81  scheduled  be  held  on  20.07.2010  but  actually  held  on  27.07.2010.  The  committee  observed  that  the  case  is  under examination of DHI. The case stands deferred and to be re­listed on 24.08.2010.

10

Case No.:17/33/81­ALC2/2009

Party Name:ASIATIC ELECTRICAL AND SWITCHGEAR PVT.LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00296/AM10/ RLA File :05/23/040/00092/AM10/ Lic.No/Date:0510252108 09.11.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in  its  M.No.  16/81  scheduled  be  held  on  20.07.2010  but  actually  held  on  27.07.2010.  The  committee  observed  that  the  case  is  under examination of DHI. The case stands deferred and to be re­listed on 24.08.2010.   11

Case No.:13/37/83­ALC1/2009

20.07.2010 Status:Deffered and Re­indexed HQ File :01/83/050/00696/AM10/ RLA File :35/24/040/00014/AM10/ Lic.No/Date:3510028373 30.11.2009 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. As per written recommendations of M/o Mines vide O.M. No. 4(4)/2010­Met.III/L dated  20.07.2010(copy  enclosed),  NC  decided  to  call  for  the  certain  information/clarification  from  the  firm  and  to  re­list  the  case  on 24.08.2010.                               12

Case No.:1/43/81­ALC2/2009

Party Name:YAMUNA POWER & INFRASTRUCTURE LTD 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00416/AM10/ RLA File :05/24/040/00430/AM10/ Lic.No/Date:0510255635 05.01.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC decided that a copy of the reply received from the firm may be referred to DIPP. The case stands deferred and to be relisted on 17.08.2010.   13

Case No.:3/43/81­ALC2/2009

Party Name:BHARAT HEAVY ELECTRICALS LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00418/AM10/ RLA File :05/23/040/00135/AM10/ Lic.No/Date:0510255677 06.01.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010.   14

Case No.:7/43/81­ALC2/2009

Party Name:LARSEN & TOUBRO LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00422/AM10/ RLA File :03/95/040/00537/AM10/ Lic.No/Date:0310554919 12.01.2010 Defer

Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Defense are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.     15

Case No.:8/43/81­ALC2/2009

Party Name:ALSTOM PROJECTS INDIA LIMITED, 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00423/AM10/ RLA File :03/94/040/00869/AM10/ Lic.No/Date:0310555103 13.01.2010 Defer Date:24.07.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from DHI are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   16

Case No.:15/43/81­ALC2/2009

Party Name:INTERPLEX ELECTRONICS INDIA PVT.LTD., 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00430/AM10/ RLA File :07/24/040/00385/AM10/ Lic.No/Date:0710069448 18.01.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from MIT are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   17

Case No.:2/49/81­ALC2/2009

Party Name:VIJAI ELECTRICALS LTD 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00462/AM10/ RLA File :09/24/040/00248/AM10/ Lic.No/Date:0910041023 19.02.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee decided that a copy of the application of the firm may be referred to DHI for comments. The case stands deferred and to be relisted on 24.08.2010.     18

Case No.:6/49/81­ALC2/2009

Party Name:KOTAK URJA PVT. LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00466/AM10/ RLA File :07/24/040/00415/AM10/ Lic.No/Date:0710070184 Defer

23.02.2010 Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from MNRES are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   19

Case No.:7/49/81­ALC2/2009

Party Name:VIJAI ELECTRICALS LTD 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00467/AM10/ RLA File :09/24/040/00462/AM10/ Lic.No/Date:0910041054 24.02.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010.   20

Case No.:7/5/81­ALC2/2010

Party Name:BILCARE LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00016/AM11/ RLA File :31/24/040/00191/AM10/ Lic.No/Date:3110042243 05.03.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010.     21

Case No.:1/5/81­ALC2/2010

Party Name:MINEX METALLURGICAL COMPANY LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00010/AM11/ RLA File :03/95/040/00876/AM10/ Lic.No/Date:0310569411 13.04.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Steel  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.   22

Case No.:3/5/81­ALC2/2010

Party Name:INTERPLEX ELECTRONICS INDIA PVT.LTD., 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00012/AM11/ RLA File :07/24/040/00489/AM10/ Lic.No/Date:0710070942 Defer

15.04.2010 Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands deferred and to be relisted on 24.08.2010.   23

Case No.:4/5/81­ALC2/2010

Party Name:ALCOMEX SPRINGS PRIVATE LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00013/AM11/ RLA File :31/24/040/00004/AM11/ Lic.No/Date:3110042932 20.04.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands     24

Case No.:5/5/81­ALC2/2010

Party Name:RUBY MICA COMPANY PRIVATE LIMITED, 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00014/AM11/ RLA File :02/24/040/00002/AM11/ Lic.No/Date:0210141063 21.04.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010.   25

Case No.:6/5/81­ALC2/2010

Party Name:OHSUNG ELECTRONICS INDIA PRIVATE LIMTIED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00015/AM11/ RLA File :31/24/040/00005/AM11/ Lic.No/Date:3110042956 21.04.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010.   26

Case No.:8/5/81­ALC2/2010

Party Name:MAN INDUSTRIES (INDIA) LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00017/AM11/ RLA File :03/95/040/00019/AM11/ Lic.No/Date:0310571444 Defer

27.04.2010 Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. As per written recommendations of DIPP, NC decided to call for the following information/clarification from the firm and to re­list the case on 24.08.2010: ­   1.      Outer Diameter (OD), Wall Thickness (WT) and  length of Export product. 2.      Information in respect of S.No. 5 & 11of Standard Deficiency Format. 3.      Quantity of import item at Sl. No. 6 has been indicated as 1478226 MT and the same may be justified.       27

Case No.:9/5/81­ALC2/2010

Party Name:MAN INDUSTRIES (INDIA) LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00018/AM11/ RLA File :03/95/040/00020/AM11/ Lic.No/Date:0310571458 27.04.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. As per written recommendations of DIPP, NC decided to call for the following information/clarification from the firm and to re­list the case on 17.08.2010: ­   1.      Outer Diameter (OD), Wall Thickness (WT) and  length of Export product. 2.      Information in respect of S.No. 5 & 11of Standard Deficiency Format. 3.      Quantity of import item at Sl. No. 6 has been indicated as 1478226 MT and the same may be justified.     28

Case No.:11/5/81­ALC2/2010

Party Name:MAN INDUSTRIES (INDIA) LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00020/AM11/ RLA File :03/95/040/00053/AM11/ Lic.No/Date:0310571777 28.04.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. As per written recommendations of DIPP, NC decided to call for the following information/clarification from the firm and to re­list the case on 17.08.2010: ­   1.      Outer Diameter (OD), Wall Thickness (WT) and  length of Export product. 2.      Information in respect of S.No. 5 & 11of Standard Deficiency Format. 3.      Quantity of import item at Sl. No. 6 has been indicated as 997717 MT and the same may be justified.

29

Case No.:1/12/81­ALC2/2010

Party Name:VINEY AUTO PVT. LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00063/AM11/ RLA File :05/24/040/00060/AM11/ Lic.No/Date:0510265843 10.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands   30

Case No.:2/12/81­ALC2/2010

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00064/AM11/ RLA File :35/24/040/00050/AM10/ Lic.No/Date:3510030537 11.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.   31

Case No.:3/12/81­ALC2/2010

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00065/AM11/ RLA File :35/24/040/00004/AM11/ Lic.No/Date:3510030567 14.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.     32

Case No.:4/12/81­ALC2/2010

Party Name:CHHAPERIA INTERNATIONAL COMPANY 20.07.2010 Status:Approved HQ File :01/81/050/00066/AM11/ RLA File :07/24/040/00062/AM11/ Lic.No/Date:0710072221 14.06.2010   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Norms Committee decided to ratify the norms in

respect of the subject advance authorization, as per written comments of DIPP vide their U.O No. DIPP/TSW/DES­II/16/81 /32  dated    27.07.2010 with following modification:­   1.      Words “Width 6 mm  to 80 mm” may be suffixed with the description of Export product. 2.      Words “Width 1000 mm or  above ” may be suffixed with the description of import item. 3.      Quantity of import item may be allowed as applied for i.e 20 MT inclusive of a wastage of 2 %.   R/A may take suitable consequential action accordingly.   33

Case No.:1/13/81­ALC2/2010

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00067/AM11/ RLA File :35/24/040/00007/AM11/ Lic.No/Date:3510030580 14.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.     34

Case No.:2/13/81­ALC2/2010

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00068/AM11/ RLA File :35/24/040/00008/AM11/ Lic.No/Date:3510030581 14.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.   35

Case No.:3/13/81­ALC2/2010

Party Name:S.P.FABRICATORS PVT.LTD. 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00069/AM11/ RLA File :03/95/040/00199/AM11/ Lic.No/Date:0310578749 14.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010.

36

Case No.:4/13/81­ALC2/2010

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00070/AM11/ RLA File :35/24/040/00009/AM11/ Lic.No/Date:3510030593 15.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.     37

Case No.:5/13/81­ALC2/2010

20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00071/AM11/ RLA File :35/24/040/00010/AM11/ Lic.No/Date:3510030594 15.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines  are  still  awaited  and  therefore  decided  to  remind  them  to  expedite  the  same.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.   38

Case No.:6/13/81­ALC2/2010

Party Name:ROTOMAG MOTORS AND CONTROLS P LTD 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00072/AM11/ RLA File :34/24/040/00041/AM11/ Lic.No/Date:3410027237 16.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. As per written recommendations of DIPP, NC decided to call for the following information/clarification from the firm and to re­list the case on 24.08.2010: ­   1.      Export product wise information in respect of S.No. 4, 5 & 11 of the Standard Deficiency Format.     39

Case No.:7/13/81­ALC2/2010

Party Name:JLC ELECTROMET PVT. LTD., 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00073/AM11/ RLA File :13/24/040/00014/AM11/ Lic.No/Date:1310032468 17.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II

in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC decided that M/o Steel may review the case and the comments received from DIPP will be taken up in consideration read with comments of M/o Steel. The case stands deferred and to be relisted on 24.08.2010.     40

Case No.:8/13/81­ALC2/2010

Party Name:JLC ELECTROMET PVT. LTD., 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00074/AM11/ RLA File :13/24/040/00013/AM11/ Lic.No/Date:1310032469 17.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC decided that M/o Steel may review the case and the comments received from DIPP will be taken up in consideration read with comments of M/o Steel. The case stands deferred and to be relisted on 24.08.2010.   41

Case No.:9/13/81­ALC2/2010

Party Name:ABB LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00075/AM11/ RLA File :07/24/040/00087/AM11/ Lic.No/Date:0710072311 17.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands   42

Case No.:10/13/81­ALC2/2010

Party Name:SOURIAU INDIA PRIVATE LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00076/AM11/ RLA File :10/24/040/00024/AM11/ Lic.No/Date:1010039133 21.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from MIT are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.     43

Case No.:11/13/81­ALC2/2010

Party Name:ADVANCE CABLE TECHNOLOGIES PVT.LTD, 20.07.2010 Status:Approved

HQ File :01/81/050/00077/AM11/ RLA File :07/24/040/00076/AM11/ Lic.No/Date:0710072363 21.06.2010   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Norms Committee decided to ratify the norms in respect of the subject advance authorization, as per written comments of DIPP vide their U.O No. DIPP/TSW/DES­II/16/81 /43  dated    27.07.2010 with following modification:­   1.      Words “1100 V” may be suffixed with the descriptions of Export products from Sl No. 1 to 6. 2.      Quantities of import items at Sl. No. 1 & 2  may be allowed as 32254 Kgs & 32591 Kgs respectively as  per Engineering Table 5.   R/A may take suitable consequential action accordingly.   44

Case No.:12/13/81­ALC2/2010

Party Name:ABB LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00078/AM11/ RLA File :07/24/040/00095/AM11/ Lic.No/Date:0710072376 22.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands     45

Case No.:13/13/81­ALC2/2010

Party Name:MOLEX (INDIA) PRIVATE LIMITED, 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00079/AM11/ RLA File :07/24/040/00079/AM11/ Lic.No/Date:0710072388 23.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from MIT are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   46

Case No.:14/13/81­ALC2/2010

Party Name:BHARAT HEAVY ELECTRICALS LIMITED 20.07.2010 Status:Deffered and Re­indexed HQ File :01/81/050/00080/AM11/ RLA File :06/24/040/00014/AM11/ Lic.No/Date:0610018297 23.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II

in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from DHI are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   47

Case No.:2/16/81­ALC2/2010

Party Name:ALCOMEX SPRINGS PRIVATE LIMITED 20.07.2010 Status: Deffered and Re­indexed HQ File :01/81/050/00087/AM11/ RLA File :31/24/040/00060/AM11/ Lic.No/Date:3110043776 29.06.2010 Defer Date:24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands     48

Case No.:1/16/81­ALC2/2010

Party Name:BHANDARI FOILS & TUBES LIMITED, Meet No/Date:16/81­ALC2/2010 20.07.2010 Re­indexed HQ File :01/81/050/00086/AM11/ RLA File :03/94/040/00268/AM11/ Lic.No/Date:0310581975 02.07.2010 Defer Date: 24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands   49

Case No.:3/16/81­ALC2/2010

Party Name:JLC ELECTROMET PVT. LTD., 20.07.2010 Re­indexed HQ File :01/81/050/00088/AM11/ RLA File :13/24/040/00015/AM11/ Lic.No/Date:1310032646 08.07.2010 Defer Date: 24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands   50

Case No.:4/16/81­ALC2/2010

Party Name:GEM ELECTRO MECHANICALS PVT. LTD., 20.07.2010 Re­indexed HQ File :01/81/050/00089/AM11/ RLA File :13/24/040/00016/AM11/ Lic.No/Date:1310032647 08.07.2010 Defer Date: 24.08.2010

Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands     51

Case No.:5/16/81­ALC2/2010

Party Name:SVAM PACKAGING INDUSTRIES PRIVATE LIMITED 20.07.2010 Re­indexed HQ File :01/81/050/00090/AM11/ RLA File :05/24/040/00131/AM11/ Lic.No/Date:0510267887 09.07.2010 Defer Date: 24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands   52

Case No.:6/16/81­ALC2/2010

Party Name:PHOENIX FOILS PVT. LTD. 20.07.2010 Re­indexed HQ File :01/81/050/00091/AM11/ RLA File :03/95/040/00229/AM11/ Lic.No/Date:0310582844 09.07.2010 Defer Date: 24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands   53

Case No.:7/16/81­ALC2/2010

Party Name:ABB LIMITED 20.07.2010 Re­indexed HQ File :01/81/050/00092/AM11/ RLA File :07/24/040/00122/AM11/ Lic.No/Date:0710072772 09.07.2010 Defer Date: 24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands    

Case No.:8/16/81­ALC2/2010

Party Name:ABB LIMITED

54 y 20.07.2010 Re­indexed HQ File :01/81/050/00093/AM11/ RLA File :07/24/040/00124/AM11/ Lic.No/Date:0710072774 09.07.2010 Defer Date: 24.08.2010 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the application of the firm is not received. Therefore, the Committee decided to remind RA for forwarding the copy of the application of the firm. The case stands                 PART – AR – DEFFER. S. No. 92

Case No. AR­11

 M/s Salvi Chemical Industries Ltd. Mumbai      Meeting No. 16/81 F.No.01/83/50/1397/AM08/DES­IV/DES­II Dated:   20.07.2010 Advance Licence No.0310446666  dt.17­10­2007   RLA  F.No.03/95/040/721/AM08 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC decided that a copy of the reply received from the firm may be referred to DC(MSME). The case stands deferred and to be relisted on 24.08.2010.   S. No. 93

CASE NO. AR­32

M/s  SIA Manufacturers, Aligarh. Meeting No. 13 /81  F.No.01/81/050/709/AM’06/DES­II      Dated:            29.06.2010  Advance Licence No. 0610010113 dated 30.11.2005   RLA’s F.No.06/81/040/0130/AM09 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC observed that there is representation with regards to nos. of

export  product.  Please  get  the  same  examined  by  DGFT/TA  and  take  up  in  NC  meeting.  The  case  stands  deferred  and  to  be  relisted  on 24.08.2010.     S. No. 94

CASE NO. AR­37

M/s  Schneider Electric India Pvt. Ltd., New Delhi Meeting No. 16/81 F. No. 01/81/050/329/AM’10/DES­II,  Dated:              20.07.2010  Advance Licence No. 0510162049 dated 14.07.2005   RLA’s F.No.05/24/040/297/AM06 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Norms Committee decided to ratify the norms in respect of the subject advance authorization, as per written comments of DIPP vide their U.O No. DIPP/TSW/DES­II/16/81 /94  dated    27.07.2010 as per GN­4.   R/A may take suitable consequential action accordingly. PART – B – FRESH Sl. No. 4

CASE NO.  B ­ 02

M/s Neo Wheel Ltd., Navi Mumbai ( formally known as Versatile Hi­tech C&E Ltd.,) Meeting No. 16/81 F. No. 01/81/162/241/AM’11/DES­II,  Dated: 20.07.2010   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the reply from the firm is still awaited and therefore decided to remind the firm to expedite the reply. The case stands deferred and to be re­listed on 24.08.2010. PART – C – DEFFER S. No. 29

Case No. C­51

 M/S  Hindustan Zinc Ltd., Noida  through DC(SEZ), Noida Meeting No.16/81 F.No.01/81/162/767/AM09/DES­II Dated:  20.07.2010   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Mines are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   S. No. 30

CASE NO. C­  10

M/s. Simmonds Marshall Ltd., Mumbai through EEPC

(India), Kolkata Meeting No. 16/81 F.No.01/81/162/319/AM’10/DES­II      Dated:  20.07.2009   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. The Committee observed that the comments from M/o Steel are still awaited and therefore decided to remind them to expedite the same. The case stands deferred and to be relisted on 24.08.2010.   S. No. 31

CASE NO. C ­ 07

M/s TTP Technologies Pvt. Ltd., Bangalore.   Meeting No. 14/81 F.No.01/81/162/0094/AM’11/DES­II      Dated: 06.07.2010   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee ­ II in its M.No. 16/81 scheduled be held on 20.07.2010 but actually held on 27.07.2010. NC discussed the comments of DHI and observed that the export product  is  different  than  what  is  given  under  SION  C­274.  Hence,  it  has  been  decided  to  refer  the  matter  to  M/o  Steel  for  examination  and comments. The case stands deferred and to be relisted on 24.08.2010.    