IN FORCE Norms Committee — Engineering (Gr B / NC-I) Advance Authorisation 2009-04-16

DGFT Committee Minutes

Document text

RATIFIED   Minutes of M.No.02/10 held on 16.04.2009 of Norms Committee (NC­I) (DES.I Section)     The meeting No. 02/10 of the Norms Committee (NC­I) for the licensing year 2009­2010 could not held on the scheduled date of 14.04.2008 due gazetted holyday and actually convened on 16.04.2009 under the Chairmanship of Shri A.  Komu,  Joint  Director  General  of  Foreign  Trade  to  consider  the  applications  under  Duty  Exemption  /  Remission Schemes (Chapter­4) of Foreign Trade Policy 2004–2009 / Handbook of Procedure Volume­I.  The following Members of the Committee were present in the meeting: ­   Sl.No Name  of  the  representatives  &  their Designation Room No. Telephone No. Deptt. 1. Sh B. C. Nayak. D.O. 475 23062635 DHI, U.B. 2. Sh  S.K. Jain,  D.O. 429A 23063321 Extn.3318 DIPP, U.B. 3. Sh. B.D. Ghosh. Jt. IA 399 23063355 M/o Steel, U.B. 4. Sh. A.K. Mishra, AIA     M/o Steel, U.B. 5. Sh. K.K. Funda, Asstt. Director 736A   DC(MSME) N.B. 6. Sh. Krishan Kumar, DDG & Convener NC­I 302 23061562 Ext.380 DGFT, U.B. 7. Sh. Ramavatar Meena, FTDO 404 23061562 Ext.265 DGFT, U.B.   The Committee considered the individual cases of the agenda of this meeting generated through the online system of NIC and some manual cases and the decision taken thereon were as under: ­    1

Case No.:15/8/80­ALC2/2008

Party Name:ARJUN TECHNOLOGIES (INDIA) LTD, Meet No/Date:2/80­ALC2/2009 14.04.2009 Status:Case deferred HQ File :01/80/050/00296/AM09/ RLA File :04/24/040/00410/AM07/ Lic.No/Date:0410087487 09.02.2007 Defer Date: 09.06.2009 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee observed that no reply of the firm had been received by this office in response to this office letter calling for certain information. The Committee, therefore, decided to remind the firm for expediting the said information otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009.     2

Case No.:56/6/80­ALC2/2008

Party Name:DOSHION LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00246/AM09/ RLA File :08/24/040/00232/AM07/ Lic.No/Date:0810063592 13.03.2007 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that neither comments  on  queries  raised  by  the  NC  in  its  meeting  No.  39/09  dt.  06.01.2009  has  been  received  so  far  from concerned Regional Authority in spite of reminder nor reply of the firm has been received in response to this office letter calling for certain information. The Committee, therefore, decided to remind the RA as well as the firm for expediting the said comments / information.   The case may be re­listed on 09.06.2009.   3

Case No.:131/48/80­ALC2/2007

Party Name:SOLOGUARD MEDICAL DEVICES PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/00777/AM08/ RLA File :04/24/040/00083/AM08/ Lic.No/Date:0410089887 08.06.2007   Decision  :  The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The C&PC  furnished  written  comments  in  this  case  vide  their  O.M.  No.  46011/08/2009­PC­II  dated 09.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject  advance  authorization  in  accordance  with  their  written  comments  after  some  modification  as under:­   1.      Net content of HDPE Granules and Polypropylene granules may be allowed with 1% wastage. 2.      Relevant Needles (import item No. 3) may be allowed on net to net basis. 3.      Printing ink may be allowed as 0.007 grams per 100 Nos. of Syringes to be exported. 4.      Packing Material may be allowed as per General Packing Policy.   The Regional Authority may take necessary action accordingly.

4

Case No.:138/48/80­ALC2/2007

Party Name:SOLOGUARD MEDICAL DEVICES PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/00784/AM08/ RLA File :04/24/040/00098/AM08/ Lic.No/Date:0410089962 14.06.2007   considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The C&PC  furnished  written  comments  in  this  case  vide  their  O.M.  No.  46011/08/2009­PC­II  dated 09.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject  advance  authorization  in  accordance  with  their  written  comments  after  some  modification  as under:­   1.      Net content of HDPE Granules and Polypropylene granules may be allowed with 1% wastage. 2.      Relevant Needles (import item No. 3) may be allowed on net to net basis. 3.      Printing ink may be allowed as 0.007 grams per 100 Nos. of Syringes to be exported. 4.      Packing Material may be allowed as per General Packing Policy.     5

Case No.:292/48/80­ALC2/2007

Party Name:SOLOCARE MEDICALS PRIVATE LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/00938/AM08/ RLA File :04/24/040/00172/AM08/ Lic.No/Date:0410091076 17.09.2007   C&PC  furnished  written  comments  in  this  case  vide  their  O.M.  No.  46011/08/2009­PC­II  dated 09.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject  advance  authorization  in  accordance  with  their  written  comments  after  some  modification  as under:­   1.      Net content of HDPE Granules and Polypropylene granules may be allowed with 1% wastage. 2.      Relevant Needles (import item No. 3) may be allowed on net to net basis. 3.      Printing ink may be allowed as 0.007 grams per 100 Nos. of Syringes to be exported. 4.      Packing Material may be allowed as per General Packing Policy.     6

Case No.:1/10/80­ALC2/2008

Party Name:LARSEN & TOUBRO LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00301/AM09/ RLA File :04/24/040/00223/AM08/ Lic.No/Date:0410091098 18.09.2007 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The representative of the DHI informed  the  Committee  that  the  case  was  under  their  study.  The  Committee,  therefore,  decided  to  defer  the consideration and to re­list the case on 09.06.2009.   7

Case No.:28/30/81­ALC2/2007

Party Name:THE SARASWATI INDUSTRIAL SYNDICATE LTD. 14.04.2009 Status:Case deferred HQ File :01/81/050/00362/AM08/ RLA File :05/24/040/00559/AM08/ Lic.No/Date:0510210503 15.10.2007 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee observed that the firm has furnished incomplete reply in response to this office letter calling for certain information. The Committee, therefore, decided to advise the firm to appear before the NC to explain their case in person along with full facts. The case may be re­listed on 09.06.2009.   8

Case No.:63/12/80­ALC2/2008

Party Name:BHARAT HEAVY ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00429/AM09/ RLA File :09/24/040/00353/AM08/ Lic.No/Date:0910032441 20.12.2007 Defer Date: 09.06.2009 informed the Committee that they desired additional information vide their U.O. No. 3(48)2008/TSW(B)/175 dt. 23.07.2008  to  examine  the  case.  The  Committee  decided  to  ask  the  firm  to  furnish  the  following information/clarification desired by the technical authority otherwise their case would be rejected.   The case may be li d 09 06 2009

relisted on 09.06.2009:­   1.      Specific quantity in numbers against export item No. 1. 2.      Bifurcation of import items for each export product. 3.      Justification for quantity of components to be imported. 4.      Information in respect of Sl.No.11 of the Standard Deficiency Format for import of CS Plates.     9

Case No.:13/10/80­ALC2/2008

Party Name:DEE DEVELOPMENT ENGINEERS PVT. LTD. 14.04.2009 Status:Case approved HQ File :01/80/050/00313/AM09/ RLA File :05/24/040/00777/AM08/ Lic.No/Date:0510214510 04.01.2008   representative  of  the  DIPP  present  in  the  meeting  recommended  the  case.  The  Committee,  after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization with following modifications:­   1. Words “Total Pipe Length 1770 mtrs. (Carbon Steel Pipes: 184 Mtrs. & Stainless Steel Seamless/ERW Pipes: 1586 Mtrs” may be specified with the total quantity of export product. 2. Word “relevant” may be prefixed with the description of import items at S.No.1, 2 & 5. 3. Quantity of import item at S.No.1 may be allowed as 7.752 MT (188 Mtrs.) inclusive of 2% wastage. 4. Quantity of import item at S.No.2 may be allowed as 21.632 MT (1618.5Mtrs.) inclusive of 2% wastage. 5. Quantity of import item at S.No.3 may be allowed as 1.9 MT (374 Nos.) on net to net basis. 6. Quantity of import item at S.No.4 may be allowed as 10.304 MT (2850 Nos.) on net to net basis. 7. Quantity of import item at S.No.5 may be allowed as 6.72 MT inclusive of 2% wastage. 8. Quantities of import items at S.No.6 & 7 may be allowed as 0.836 MT each. 9. Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type, technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.     10

Case No.:3/2/85­ALC3/2008

Party Name:MAHATI ELECTRICS 14.04.2009 Status:Case deferred HQ File :01/85/050/00003/AM09/ RLA File :31/24/040/00304/AM08/ Lic.No/Date:3110032429 23.01.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  DHI  has  desired  some information vide their U.O. No. 3(26)/09­TSW(B) dt. 05.03.2009. The Committee has decided to ask the firm to furnish  the  following  information/clarification  desired  by  the  technical  authority  otherwise  their  case  would  be rejected.   The case may be re­listed on 09.06.2009:­   1.       The items proposed for import has been given in set.  The break up of the sets in number may be given. 2.       Details of item no. 41 and 42 with catalogue / write up. 3.       Clarification regarding information given in Appendix 11 A that 1.1 number of quantity required per unit of resultant product.  Justification for 10% wastage. 4.       Information in respect of Sl.No.5 of the Standard Deficiency Format.   11

Case No.:5/2/85­ALC3/2008

Party Name:MAHATI ELECTRICS 14.04.2009 Status:Case deferred HQ File :01/85/050/00005/AM09/ RLA File :31/24/040/00308/AM08/ Lic.No/Date:3110032430 23.01.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  DHI  has  desired  some information vide their U.O. No. 3(26)/09­TSW(B) dt. 05.03.2009. The Committee has decided to ask the firm to furnish  the  following  information/clarification  desired  by  the  technical  authority  otherwise  their  case  would  be rejected.   The case may be re­listed on 09.06.2009:­   1.       The items proposed for import has been given in set.  The break up of the sets in number may be given. 2.       Details of item no. 41 and 42 with catalogue / write up. 3.       Clarification regarding information given in Appendix 11 A that 1.1 number of quantity required per unit of resultant product.  Justification for 10% wastage. 4.       Information in respect of Sl.No.5 of the Standard Deficiency Format.

12

Case No.:4/2/85­ALC3/2008

Party Name:MAHATI ELECTRICS 14.04.2009 Status:Case deferred HQ File :01/85/050/00004/AM09/ RLA File :31/24/040/00340/AM08/ Lic.No/Date:3110032470 24.01.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  DHI  has  desired  some information vide their U.O. No. 3(26)/09­TSW(B) dt. 05.03.2009. The Committee has decided to ask the firm to furnish  the  following  information/clarification  desired  by  the  technical  authority  otherwise  their  case  would  be rejected.   The case may be re­listed on 09.06.2009:­   1.       The items proposed for import has been given in set.  The break up of the sets in number may be given. 2.       Details of item no. 22and 31 with catalogue / write up. 3.       Clarification regarding information given in Appendix 11 A that 1.1 number of quantity required per unit of resultant product.  Justification for 10% wastage. 4.       Information in respect of Sl.No.5 of the Standard Deficiency Format. 5.       Reason of importing one set each of item no. 52, 53 and 54 when they are supplying two sets of generators.   13

Case No.:101/24/80­ALC2/2008

Party Name:NICOMET INDUSTRIES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00977/AM09/ RLA File :03/95/040/01062/AM08/ Lic.No/Date:0310459253 25.01.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information despite reminder. The Committee, therefore, decided to issue final reminder to the firm for expediting the required information otherwise their case will be rejected and no further representation will be entertained.   The case may be re­listed on 09.06.2009.     14

Case No.:27/10/80­ALC2/2008

Party Name:TEXMACO LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/00327/AM09/ RLA File :02/24/040/00297/AM08/ Lic.No/Date:0210109384 21.02.2008   Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization with following modifications:­   1.      Export product description may be revised as per firm’s reply dt. 07.09.2008. A copy of the firm’s reply is to be sent to RA. 2.      Components may be allowed as per GN­4 for the engineering products. 3.      Spares may be allowed as per Spares Policy. 4.      Quantity of item no. 5 is to be allowed as one number.          15

Case No.:87/18/80­ALC2/2008

Party Name:CHANDAN STEEL LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00756/AM09/ RLA File :03/94/040/01305/AM07/ Lic.No/Date:0310462020 21.02.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  On the recommendation of the representative of M/o Steel present in the meeting, it was decided by the Committee to call for the clarification from RA as to why the export items at Sl.No. 3 to 7 were allowed in the authorization when their quantity is NIL.  It was also decided to call for the following information/clarification from the firm and to re­list the case on 09.06.2009:­   1.      Grade of stainless steel quantity wise for export. 2.      Grade of stainless steel for imported stainless steel scrap.    

Case No.:24/2/80­ALC2/2008

Party Name:SUR HENNING PVT. LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/01232/AM08/ RLA File :07/24/040/00794/AM08/ Lic No/Date:0710056059

16 HQ File :01/80/050/01232/AM08/ RLA File :07/24/040/00794/AM08/ Lic.No/Date:0710056059 26.02.2008   DHI furnished written comments in this case vide their U.O. No.3(49)/08­TSW(B)/171 dated 06.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization in accordance with their written comments as under:­   1.      Quantity of brass items (Import item Nos. 29,31,33 and 40) may be allowed with 1% wastage.  2.      Quantity of other raw materials may be allowed with 2% wastage. 3.      Components may be allowed on net to net basis without any wastage with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     17

Case No.:120/24/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00996/AM09/ RLA File :09/24/040/00530/AM08/ Lic.No/Date:0910033210 04.03.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The representative of the DHI informed the Committee that they had received the firm’s reply and case was under their study. The Committee, therefore, decided to defer the consideration and to re­list the case on 09.06.2009.     18

Case No.:2/2/81­ALC2/2008

Party Name:CIM TOOLS PVT.LTD., 14.04.2009 Status:Case approved HQ File :01/81/050/00696/AM08/ RLA File :07/24/040/00825/AM08/ Lic.No/Date:0710056335 11.03.2008   committee  noted  that  a  subcommittee  visited  the  factory  of  the  firm  to  see  the  actual  manufacturing process to find­out the wastage involved and has submitted its report.  The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject authorization as under as per sub Committee report:­   SL.NO. PART NO. CRN PART NAME Export qty as per license Total export weight (Kgs) Total RM wt. after 15 % recovery (in Kgs) wastage in % age after 15 % recovery 1 2 3 4 5 6 7 8 1 A800182­ 812 23­084 BASE 77 63.60 314.0 394   19

Case No.:2/48/80­ALC2/2008

Party Name:SHIV INDUSTRIES 14.04.2009 Status:Case deferred HQ File :01/80/050/01763/AM09/ RLA File :30/24/040/00057/AM08/ Lic.No/Date:3010055453 11.03.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  Committee  noted  that hardcopy of firm’s application has not been received so far from concerned Regional Authority in spite of reminder.  The Committee, therefore, decided to remind RA with a copy to firm to forward 4 set of application at the earliest and on receipt forward the same to DC(MSME) for examination and submission of comments. The case may be re­ listed on 09.06.2009.     20

Case No.:42/24/80­ALC2/2008

Party Name:BOTIL OIL TOOLS INDIA PVT LTD(FORMERLY BAKER OIL 14.04.2009 Status:Case deferred HQ File :01/80/050/00918/AM09/ RLA File :05/24/040/00940/AM08/ Lic.No/Date:0510217768 12.03.2008 Defer Date: 09.06.2009

informed  the  Committee  that  the  case  was  under  their  study.  The  Committee,  therefore,  decided  to  defer  the consideration and to re­list the case on 09.06.2009.   21

Case No.:119/24/80­ALC2/2008

Party Name:MINDA SILCA ENGINEERING LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00995/AM09/ RLA File :05/24/040/00941/AM08/ Lic.No/Date:0510217932 14.03.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The DC(MSME) has desired some information vide their U.O. No. 30(357)2008­ME dt. 25.03.2009. The Committee has decided to ask the firm to furnish the following information/clarification desired by the technical authority otherwise their case would be rejected.   The case may be re­listed on 09.06.2009:­   1.      Weight of each export product (all the three) separately for each pice and total number of pieces. 2.      Sheet layout diagram of the material indicating the wastage during the operation of blanking. 3.      Details of calculation, as how the quantity of raw material has been arrived with complete wastage justification. 4.      Process of manufacturing and stepwise wastage therein.     22

Case No.:1/39/80­ALC2/2008

Party Name:NEPTUNE INDUSTRIES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01554/AM09/ RLA File :08/24/040/00263/AM08/ Lic.No/Date:0810070858 24.03.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   23

Case No.:73/12/80­ALC2/2008

Party Name:JKM DAE RIM AUTOMOTIVE LIMITED., 14.04.2009 Status:Case deferred HQ File :01/80/050/00439/AM09/ RLA File :07/24/040/00535/AM08/ Lic.No/Date:0710056578 25.03.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   24

Case No.:40/24/80­ALC2/2008

Party Name:MULTITEX FILTRATION ENGINEERS LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00916/AM09/ RLA File :05/24/040/00961/AM08/ Lic.No/Date:0510218436 25.03.2008 Defer Date: 09.06.2009 Committee observed that the firm has furnished incomplete reply in response to this office letter calling for certain  information.  The  Committee,  therefore,  decided  to  direct  the  firm  to  furnish  the  following information complete in all respects otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009:­   1. Information in respect of Sl.No.3,5 & 11 of the Standard    Deficiency Format.   25

Case No.:43/24/80­ALC2/2008

Party Name:MAHARASHTRA SEAMLESS LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00919/AM09/ RLA File :05/24/040/00878/AM08/ Lic.No/Date:0510218634 28.03.2008 Defer Date: 09.06.2009

26

Case No.:5/36/84­ALC3/2008

Party Name:JYOTI CNC AUTOMATION PVT LTD, 14.04.2009 Status:Case reverted back to RA HQ File :01/84/050/00397/AM09/ RLA File :24/21/040/00197/AM08/ Lic.No/Date:2410020941 01.04.2008   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that firm’s application has not been received so far.  However, according to online data, items of import appear to be covered in GN­4 for the Engineering Products. The Committee accordingly decided to revert back the case to concerned Regional Authority without any examination for taking appropriate decision in terms of Policy Circular No. 20 dt. 05.12.2007.   27

Case No.:127/16/80­ALC2/2008

Party Name:PSL LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00650/AM09/ RLA File :05/24/040/00987/AM08/ Lic.No/Date:0510218884 02.04.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.     28

Case No.:129/16/80­ALC2/2008

Party Name:AVLIGHT AUTOMOTIVES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00652/AM09/ RLA File :05/24/040/00991/AM08/ Lic.No/Date:0510219004 04.04.2008 Defer Date: 09.06.2009   29

Case No.:130/16/80­ALC2/2008

Party Name:AVLIGHT AUTOMOTIVES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00653/AM09/ RLA File :05/24/040/00994/AM08/ Lic.No/Date:0510219002 04.04.2008 Defer Date: 09.06.2009   30

Case No.:131/16/80­ALC2/2008

Party Name:AVLIGHT AUTOMOTIVES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00654/AM09/ RLA File :05/24/040/00993/AM08/ Lic.No/Date:0510219001 04.04.2008 Defer Date: 09.06.2009    

Case No.:132/16/80­ALC2/2008

Party Name:AVLIGHT AUTOMOTIVES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00655/AM09/ RLA File :05/24/040/00992/AM08/ Lic.No/Date:0510219003 04.04.2008 Defer Date: 09.06.2009

31 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the   32

Case No.:25/24/80­ALC2/2008

Party Name:TEXMACO LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00901/AM09/ RLA File :02/24/040/00337/AM08/ Lic.No/Date:0210111218 09.04.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study.  The  Committee,  therefore,  decided  to  defer  the consideration and to re­list the case on 09.06.2009.   33

Case No.:70/16/80­ALC2/2008

Party Name:KERN­LIEBERS SOMAPPA PRECISION PARTS PVT.LTD, 14.04.2009 Status:Case deferred HQ File :01/80/050/00593/AM09/ RLA File :07/24/040/00008/AM09/ Lic.No/Date:0710057064 23.04.2008 Defer Date: 09.06.2009     34

Case No.:27/24/80­ALC2/2008

Party Name:TIL LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00903/AM09/ RLA File :02/24/040/00019/AM09/ Lic.No/Date:0210111785 25.04.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that firm has sought time for submission of required information.  The Committee, therefore, decided to remind the firm for expediting  the  said  information  otherwise  their  case  will  be  rejected  without  any  further  chance  and  no  further representation will be entertained.   The case may be re­listed on 09.06.2009.   35

Case No.:28/24/80­ALC2/2008

Party Name:TIL LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00904/AM09/ RLA File :02/24/040/00014/AM09/ Lic.No/Date:0210111784 25.04.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   36

Case No.:113/24/80­ALC2/2008

Party Name:VULCAN INDUSTRIAL ENGINEERING CO.LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00989/AM09/ RLA File :34/24/040/00009/AM09/ Lic.No/Date:3410021276 29.04.2008 Defer Date: 09.06.2009    

Case No.:71/16/80­ALC2/2008

Party Name:DYNAMATIC TECHNOLOGIES LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/00594/AM09/ RLA File :07/24/040/00800/AM08/ Lic.No/Date:0710057193 29.04.2008 Defer Date: 09.06.2009 D i i Th di tifi ti f i t f b d th i ti id d b th

37 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee observed that no reply of the firm had been received by this office in response to this office letter calling for certain information despite reminder whereas the firm vide their letter dt. 19.02.2009 itself assured to submit their reply immediately.  The Committee, therefore, decided to issue final reminder to the firm for expediting the required information otherwise their case will be rejected and no further representation will be entertained.   The case may be re­listed on 09.06.2009.   38

Case No.:29/24/80­ALC2/2008

Party Name:GKB RX LENS PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/00905/AM09/ RLA File :02/24/040/00003/AM09/ Lic.No/Date:0210111924 30.04.2008   C&PC  furnished  written  comments  in  a  similar  case  of  the  applicant  firm  vide  their  O.M.  No.46011/42/2007­PC.II dated 23.03.2009. The Committee, after deliberating upon the case, decided to ratify  the  norms  in  respect  of  the  subject  advance  authorization  on  the  basis  of  earlier  decision  in  the similar case as under:­   1.      Quantity of import item No. 15 viz. Spectacle Lenses Semi Finished Raw Material may be allowed with 2% wastage. 2.      Quantity of other import items may be allowed as recommended by C&PC in their O.M. referred to above.       39

Case No.:8/39/80­ALC2/2008

Party Name:KENNAMETAL INDIA LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01561/AM09/ RLA File :07/24/040/00797/AM08/ Lic.No/Date:0710057214 30.04.2008 Defer Date: 09.06.2009 informed  the  Committee  that  they  had  received  the  firm’s  application  and  case  was  under  their  study.  The Committee, therefore, decided to defer the consideration and to re­list the case on 09.06.2009.   40

Case No.:46/24/80­ALC2/2008

Party Name:BELMAKS PRIVATE LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/00922/AM09/ RLA File :05/24/040/00060/AM09/ Lic.No/Date:0510220066 05.05.2008   DHI  furnished  written  comments  in  this  case  vide  their  U.O.  No.U.O.No.  3(44)/09­TSW(B)  dated 16.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization in accordance with their written comments as under:­   1.      Import of steel pipes may be allowed as applied for on net to net basis without any wastage.     41

Case No.:18/8/80­ALC2/2008

Party Name:ERBATECH MACHINERY P LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00299/AM09/ RLA File :32/24/040/00006/AM09/ Lic.No/Date:3210037776 06.05.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study.  The  Committee,  therefore,  decided  to  defer  the consideration and to re­list the case on 09.06.2009.     42

Case No.:72/16/80­ALC2/2008

Party Name:RAPSRI ENGG INDUSTRIES LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00595/AM09/ RLA File :07/24/040/00024/AM09/ Lic.No/Date:0710057316 08.05.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M No 02/10 held on 16 04 2009 as per the agenda The representative of the

Norms  Committee  (NC I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The  representative  of  the DC(MSME) informed the Committee that they had received the firm’s reply and case was under their study. The   43

Case No.:96/24/80­ALC2/2008

Party Name:IDMC LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00972/AM09/ RLA File :34/24/040/00030/AM09/ Lic.No/Date:3410021368 09.05.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   44

Case No.:98/24/80­ALC2/2008

Party Name:IDMC LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00974/AM09/ RLA File :34/24/040/00252/AM08/ Lic.No/Date:3410021362 09.05.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.     45

Case No.:92/16/80­ALC2/2008

Party Name:ACCURATE PRODUCTS CORPORATION PVT LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00615/AM09/ RLA File :04/24/040/00014/AM09/ Lic.No/Date:0410095855 14.05.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   46

Case No.:91/16/80­ALC2/2008

Party Name:GODREJ & BOYCE MFG. CO. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00614/AM09/ RLA File :03/94/040/00140/AM09/ Lic.No/Date:0310471579 19.05.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study.  The  Committee,  therefore,  decided  to  defer  the consideration and to re­list the case on 09.06.2009.   47

Case No.:93/16/80­ALC2/2008

Party Name:PET MOULDS PVT LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00616/AM09/ RLA File :04/24/040/00029/AM09/ Lic.No/Date:0410096019 23.05.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  DHI informed the Committee that they have not received reply of the firm. The Committee therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.     48

Case No.:25/39/80­ALC2/2008

Party Name:SHIV INDUSTRIES 14.04.2009 Status:Case deferred HQ File :01/80/050/01578/AM09/ RLA File :30/24/040/00011/AM09/ Lic.No/Date:3010056342 26.05.2008 Defer Date: 09.06.2009 Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the

Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  the DC(MSME) informed the Committee that they had received the firm’s reply and case was under their study. The   49

Case No.:56/24/80­ALC2/2008

Party Name:PSL LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00932/AM09/ RLA File :03/95/040/00178/AM09/ Lic.No/Date:0310472141 27.05.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  DIPP informed the Committee that they have not received reply of the firm. The Committee therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.   50

Case No.:105/24/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00981/AM09/ RLA File :03/94/040/00154/AM09/ Lic.No/Date:0310472328 28.05.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study.  The  Committee,  therefore,  decided  to  defer  the consideration and to re­list the case on 09.06.2009.     51

Case No.:52/24/80­ALC2/2008

LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00928/AM09/ RLA File :03/95/040/00150/AM09/ Lic.No/Date:0310472298 28.05.2008 Defer Date: 09.06.2009 informed the Committee that the case was under their study and they will finalize comments shortly. The Committee, therefore, decided to defer the consideration and to re­list the case on 09.06.2009.   52

Case No.:58/24/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/00934/AM09/ RLA File :03/95/040/00125/AM09/ Lic.No/Date:0310472290 28.05.2008     1.      Word “Relevant” may be prefixed with the description of import item at S.No.1 and quantity of this item may be allowed as applied for i.e. 116000 Kgs. inclusive of 5% wastage. 2.      Weights of 13220 Kgs., 800 Kgs., 600 Kgs. and  100 Kgs. may be specified with the quantities of import items at S.Nos. 2, 4, 5 & 6 respectively and their quantities may be allowed on net to net basis. 3.       Word “relevant” may be prefixed with the description of import item at S.No.3 and quantity of this item may be allowed as 61200  mtrs. (30400 Kgs.) inclusive of 2% wastage. 4.      Quantities of import items st S.Nos. 7, 8 & 9 may be allowed as applied for. 5.      Import item at S.No.5 to be supplied alongwith export product.      6.  Import of components may be allowed with accountability clause   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,   53

Case No.:104/24/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00980/AM09/ RLA File :03/94/040/00189/AM09/ Lic.No/Date:0310472348 29.05.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The i h f d id d i d h fi f di i h id i f i h i h i ill b

09.06.2009.   54

Case No.:47/24/80­ALC2/2008

Party Name:GUMMI METALL TECHNIK (INDIA)PVT.LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00923/AM09/ RLA File :07/24/040/00092/AM09/ Lic.No/Date:0710057665 02.06.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   55

Case No.:97/16/80­ALC2/2008

Party Name:ANSALDOCALDAIE BOILERS INDIA PRIVATE LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/00620/AM09/ RLA File :04/24/040/00050/AM09/ Lic.No/Date:0410096188 03.06.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.     56

Case No.:48/24/80­ALC2/2008

Party Name:WEBB INDIA PVT. LTD 14.04.2009 Status:Case approved HQ File :01/80/050/00924/AM09/ RLA File :07/24/040/00087/AM09/ Lic.No/Date:0710057752 06.06.2008   representative of the DC(MSME) present in the meeting recommended the case. The Committee, after   1.      Quantity of import item no. 1 & 2 may be allowed with 1% wastage. 2.      Quantity of rest of the import items may be allowed on net to net basis with accountability clause.   Note: The import of components shall be permitted on net­to­net basis with accountability clause and the type, technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.   57

Case No.:63/24/80­ALC2/2008

Party Name:EVERGREEN TECHNOLOGIES PVT LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00939/AM09/ RLA File :03/94/040/00171/AM09/ Lic.No/Date:0310473669 09.06.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  DIPP informed the Committee that they have not received reply of the firm. The Committee therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.    

Case No.:27/16/80­ALC2/2008

Party Name:JINDAL SAW LTD 14.04.2009 Status:Case approved HQ File :01/80/050/00550/AM09/ RLA File :05/24/040/00202/AM09/ Lic.No/Date:0510222889 26.06.2008  

58   1.      Net weights of 7018.7 MT, 99.3 MT, 4421.9 MT & 2015 MT may be specified with the quantities of export products at S.Nos. 1, 2, 3 & 4 respectively (total net export weight 13554.9 MT). 2.      Word “Relevant” may be prefixed with the description of import item at Sl.No. 1. 3.      Taking clue from SION C­593, quantities of import items from S.Nos. 1 to 5 may be allowed as applied for. 4.      Quantities of import items at S.Nos. 6 & 7 may be allowed as applied for i.e.474 MT & 5205 ltrs. respectively. 5.      Quantities of import items at S.Nos. 8 & 9 may be allowed as 115302 sq. mtrs. & 62949 sq. mtrs. respectively inclusive of 5% wastage. 6.      Quantities of import items from S.Nos. 10 to 13 may be allowed as applied for on net to net basis.   59

Case No.:28/16/80­ALC2/2008

Party Name:HORIZON INDUSTRIAL PRODUCTS PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00551/AM09/ RLA File :05/24/040/00217/AM09/ Lic.No/Date:0510222895 26.06.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. On the recommendation of the representative  of  DHI  present  in  the  meeting,  it  was  decided  by  the  Committee  to  call  for  the  following information/clarification from the firm and to re­list the case on 09.06.2009: ­   Information in respect of Sl.No.3,4,11 & 11a of the Standard Deficiency Format.     60

Case No.:41/16/80­ALC2/2008

Party Name:L D FABRICATORS PVT.LTD, 14.04.2009 Status:Case deferred HQ File :01/80/050/00564/AM09/ RLA File :07/24/040/00128/AM09/ Lic.No/Date:0710058224 30.06.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   61

Case No.:46/16/80­ALC2/2008

Party Name:ZINSER TEXTILE SYSTEMS PVT. LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00569/AM09/ RLA File :03/95/040/00280/AM09/ Lic.No/Date:0310476885 30.06.2008 Defer Date: 09.06.2009 comments  called  for  from  Textile  Commissioner  are  yet  to  be  received.    The  Committee,  therefore,  decided  to remind them for expediting their comments. The case may be re­listed on 09.06.2009.   62

Case No.:47/16/80­ALC2/2008

Party Name:AQUASUB ENGINEERING Meet No/Date:2/80­ALC2/2009 14.04.2009 Status:Case deferred HQ File :01/80/050/00570/AM09/ RLA File :32/24/040/00014/AM09/ Lic.No/Date:3210038146 01.07.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.     63

Case No.:48/16/80­ALC2/2008

Party Name:THERMAL SYSTEMS (HYDERABAD) P.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00571/AM09/ RLA File :09/24/040/00127/AM09/ Lic.No/Date:0910034488 01.07.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The committee noted that the firm  has  reported  that  no  advance  authorization  pertaining  to  No.  0910034488  has  been  issued  to  them.      The committee  observed  from  the  RA  letter  09/24/040/00127/AM09 dt.  27.08.2008  forwarding  the  copy  of  advance authorization alongwith firm’s application that under the subject file RA has issued adv authorization

authorization  alongwith  firm’s  application  that  under  the  subject  file  RA  has  issued  adv.  authorization No.0910035143  and  on  the  online  data  system  authorization  no.  is  wrongly  appended  as  0910034488.    The committee accordingly decided to ask the firm to furnish the required information in connection with authorization No.0910035143 issued through RA file no. 09/24/040/00127/AM09.  The case may be re­listed on 09.06.2009.   64

Case No.:51/16/80­ALC2/2008

Party Name:MAGPLASTIC ASIA PVT. LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00574/AM09/ RLA File :31/24/040/00090/AM09/ Lic.No/Date:3110034299 02.07.2008 Defer Date: 09.06.2009 informed the Committee that firm’s reply has been received and case was under their study and they will finalize their  comments  shortly.  The  Committee,  therefore,  decided  to  defer  the  consideration  and  to  re­list  the  case  on 09.06.2009.     65

Case No.:59/16/80­ALC2/2008

Party Name:DEE DEVELOPMENT ENGINEERS PVT. LTD. 14.04.2009 Status:Case approved HQ File :01/80/050/00582/AM09/ RLA File :05/24/040/00216/AM09/ Lic.No/Date:0510223409 04.07.2008     1. Words  “Total  Pipe  Length  1221  Mtrs.  (Carbon  Steel  Seamless  Pipes/Tubes:  486  Mtrs.  &  Stainless  Steel Seamless/Welded Pipes/Tubes:  735 Mtrs” may be specified with the quantity of export product. 2. Word “relevant” may be prefixed with the description of import items at S.No.1, 3, 5  & 6. 3. Quantity of import item at S.No.1 may be allowed as 5.09 MT (496 Mtrs.) inclusive of 2% wastage. 4. Quantity of import item at S.No.2 may be allowed as 1.188 MT (1218 Nos.) on net to net basis. 5. Quantity of import item at S.No.3 may be allowed as 5.814 MT (626 Mtrs.) inclusive of 2% wastage. 6. Quantity of import item at S.No.4 may be allowed as 0.95 MT (2078 Nos.) on net to net basis. 7. Quantity of import item at S.No.5 may be allowed as 3.88 MT inclusive of 2% wastage. 8. Quantity of import item at S.No. 6 may be allowed as 124 mtrs. (194 Kgs.) inclusive of 2% wastage. 9. Weights of 300 Kgs., 100 Kgs., 500 Kgs., 200 Kgs., 500 Kgs. 400 Kgs. 200 Kgs. & 50 Kgs. may be specified with the quantities of import items from S.Nos. 7 to 14 respectively and quantities of these items may be allowed on net to net basis with accountability clause. 10. Quantity of import items at S.No. 15 may be allowed as 83 mtrs. inclusive of 2% wastage. 11. Weights of 800 Kgs., 500 Kgs., 50 Kgs. & 30 Kgs.. may  be specified with the quantities of import items from S.Nos. 16 to 19 respectively and quantities of these items may be allowed on net to net basis with accountability clause. 12. Quantity of import item at S.No.20 may be allowed as 173 Kgs. 13.  Quantity of import item at S.No.21 may be allowed equal to weight of Welding Wire at S.No. 20. 14. Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,  technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.   66

Case No.:1/48/80­ALC2/2008

Party Name:BMT CORPORATION 14.04.2009 Status:Case approved HQ File :01/80/050/01762/AM09/ RLA File :30/24/040/00018/AM09/ Lic.No/Date:3010057006 07.07.2008     1.      Quantity of import item at S.No.1 may be allowed as applied for on net to net basis. 2.      Quantity of import item at S.No.2 may be allowed as 21.4 mtrs. inclusive of 2% wastage. 3.      Quantity of import item at S.No.3 may be allowed as 378 Nos. on net to net basis.  

Case No.:2/17/81­ALC2/2008

Party Name:CIM TOOLS PVT.LTD., 14.04.2009 Status:Case already approved

67 HQ File :01/81/050/00249/AM09/ RLA File :07/24/040/00160/AM09/ Lic.No/Date:0710058366 08.07.2008   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The committee noted that the subject case was already approved in NC meeting No. 53/09 held on 31.03.2009.  Accordingly the case may be withdrawn from the agenda.   68

Case No.:32/18/80­ALC2/2008

Party Name:TRANSLLOY INDIA PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00701/AM09/ RLA File :03/95/040/00293/AM09/ Lic.No/Date:0310478002 09.07.2008 Defer Date: 09.06.2009   69

Case No.:8/18/84­ALC3/2008

Party Name:RADIANT INDUSTRIES (PP. VIJAY V. JADHAV) 14.04.2009 Status:Case deferred HQ File :01/84/050/00229/AM09/ RLA File :31/24/040/00108/AM09/ Lic.No/Date:3110034521 23.07.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   70

Case No.:40/20/80­ALC2/2008

Party Name:GKB RX LENS PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/00796/AM09/ RLA File :02/24/040/00113/AM09/ Lic.No/Date:0210115469 30.07.2008   C&PC  furnished  written  comments  in  a  similar  case  of  the  applicant  firm  vide  their  O.M.  No.46011/42/2007­PC.II dated 23.03.2009. The Committee, after deliberating upon the case, decided to ratify  the  norms  in  respect  of  the  subject  advance  authorization  on  the  basis  of  earlier  decision  in  the similar case as under:­   1.      Quantity of import item No. 1 viz. Spectacle Lenses Semi Finished Raw Material may be allowed with 2% wastage. 2.      Quantity of other import items may be allowed as recommended by C&PC in their O.M. referred to above.       71

Case No.:11/24/80­ALC2/2008

Party Name:CIM TOOLS PVT.LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/00887/AM09/ RLA File :07/24/040/00263/AM09/ Lic.No/Date:0710059201 19.08.2008   Norms Committee (NC­I) in its M.No.02/10 held  on  16.04.2009  as  per  the  agenda.  The  committee  noted  that  a subcommittee visited the factory of the firm to see the actual manufacturing process to find­out the wastage involved and has submitted its report.  The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization as under as per sub Committee report:­   SL.NO. PART NAME Export qty as per license  (Nos.) Total export weight (Kgs) Total RM Wt. after 15 % recovery (in Kgs) Wastage in %age after recovery 1 2 3 4 5 6 1 REINFORCEMENT PLATE 88 25.96 47.73 84 2 REINFORCEMENT PLATE 88 25.96 47.73 84 3 REINFORCEMENT PLATE 88 25.96 47.73 84

4 REINFORCEMENT PLATE 88 25.96 47.73 84 5 REINFORCEMENT PLATE 340 71.40 121.11 70 6 REINFORCEMENT PLATE 88 18.48 31.35 70 7 REINFORCEMENT PLATE 88 18.48 31.35 70 8 REINFORCEMENT PLATE 88 18.48 31.35 70 9 REINFORCEMENT PLATE 306 64.26 177.33 176 10 REINFORCEMENT PLATE 306 64.26 177.33 176 11 PLATE 54 10.80 15.39 43 12 PLATE 54 10.80 15.39 43       72

Case No.:18/24/80­ALC2/2008

Party Name:SUR HENNIG PVT. LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/00894/AM09/ RLA File :07/24/040/00273/AM09/ Lic.No/Date:0710059209 19.08.2008   DHI furnished written comments in this case vide their U.O. No.3(49)/08­TSW(B)/173 dated 06.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization in accordance with their written comments as under:­   1.      Quantity of brass items (Import item Nos. 1,7,8 & 20) may be allowed with 1% wastage.  2.      Quantity of other raw materials may be allowed with 2% wastage. 3.      Components may be allowed on net to net basis without any wastage with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     73

Case No.:7/24/80­ALC2/2008

Party Name:GEECY ENGINEERING PRIVATE LIMITED., 14.04.2009 Status:Case deferred HQ File :01/80/050/00883/AM09/ RLA File :03/94/040/00460/AM09/ Lic.No/Date:0310483079 19.08.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The representative of the DIPP informed the Committee that they had received the firm’s reply and case was under their study and they will finalize their  comments  shortly.  The  Committee,  therefore,  decided  to  defer  the  consideration  and  to  re­list  the  case  on 09.06.2009.     74

Case No.:8/24/80­ALC2/2008

Party Name:GEECY ENGINEERING PRIVATE LIMITED., 14.04.2009 Status:Case approved HQ File :01/80/050/00884/AM09/ RLA File :03/94/040/00443/AM09/ Lic.No/Date:0310483093 19.08.2008     1. Net empty weights of  10250 Kgs., 2600 Kgs., 2900Kgs. & 4050 Kgs. may be specified with the quantities of export product from S.Nos. 1 to 4 respectively. 2. Quantity of import item at S.No.1 may be allowed as 945 Kgs inclusive of 5% wastage. 3. Quantities of import items at S.No.2  & 5 may be allowed on net to net basis with accountability clause. 4. Total weight for import items at Sl Nos. 2 & 5 put together may be specified as 8013 Kgs 5. Quantity of import item at S.No.3 may be allowed as 1752 Meters (5167 Kgs .) on net to net basis as claimed by the firm. 6. Total quantity of Welding Consumables at S.No.5 may be allowed as 145 Kgs.  

Case No.:66/24/80­ALC2/2008

Party Name:WEATHERFORD Status:Case

75 DRILLING & PRODUCTION SERVICES(I)P.LTD 14.04.2009 deferred HQ File :01/80/050/00942/AM09/ RLA File :34/24/040/00090/AM09/ Lic.No/Date:3410022116 21.08.2008 Defer Date: 09.06.2009     1.  Justification for quantity of import items at  Sl.No. 4 to 7.     76

Case No.:73/24/80­ALC2/2008

Party Name:CICB CHEMICON PRIVATE LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/00949/AM09/ RLA File :07/24/040/00237/AM09/ Lic.No/Date:0710059270 21.08.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The Committee observed that no reply of the firm had been received by this office in response to this office letter calling for certain information. The Committee, therefore, decided to remind the firm for expediting the clarification as to why their export products are not covered under SCOMET list (Sl.No. 3D001) otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009.   77

Case No.:75/24/80­ALC2/2008

Party Name:PRECIHOLE MACHINE TOOLS PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00951/AM09/ RLA File :03/95/040/00468/AM09/ Lic.No/Date:0310483368 22.08.2008 Defer Date: 09.06.2009 informed the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The   78

Case No.:78/24/80­ALC2/2008

Party Name:ROCKWELL AUTOMATION INDIA PRIVATE LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00954/AM09/ RLA File :05/24/040/00351/AM09/ Lic.No/Date:0510226089 25.08.2008 Defer Date: 09.06.2009 comments  called  for  from  DIT  are  yet  to  be  received.    The  Committee,  therefore,  decided  to  remind  them  for expediting their comments. The case may be re­listed on 09.06.2009.     79

Case No.:85/24/80­ALC2/2008

Party Name:CRISTOPIA ENERGY SYSTEMS(I) PVT.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00961/AM09/ RLA File :11/24/040/00026/AM09/ Lic.No/Date:1110018228 25.08.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The DC(MSME) has desired some information vide their U.O. No. 30(324)2008­ME dt. 12.01.2009. The Committee has decided to ask the firm to furnish the following information/clarification desired by the technical authority otherwise their case would be rejected.   The case may be re­listed on 09.06.2009.   1.      Net weight of the export product. 2.      Process of manufacturing with process flow chart indicating use of all inputs. 3.      Drawing/design of export product.   80

Case No.:86/24/80­ALC2/2008

Party Name:RATNESH METAL INDUSTRIES PVT. LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/00962/AM09/ RLA File :08/24/040/00113/AM09/ Lic.No/Date:0810074246 26.08.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The MOS has desired some information vide their communication No. 2(13)/2006­TW(Vol.IV) dt. 23.03.2009. The Committee has decided to ask the firm to furnish the required information/clarification desired by the technical authority otherwise their case

ask the firm to furnish the required information/clarification desired by the technical authority otherwise their case would be rejected.   The case may be re­listed on 09.06.2009.   1.      Specific type of furnace and its capacity (induction/electric arc). 2.      Whether AOD/VOD converters are also installed in your firm.     81

Case No.:92/24/80­ALC2/2008

Party Name:SUR HENNIG PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/00968/AM09/ RLA File :07/24/040/00294/AM09/ Lic.No/Date:0710059332 27.08.2008 Defer Date: 09.06.2009 DHI furnished written comments in this case vide their U.O. No.3(49)/08­TSW(B)/172 dated 06.04.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization in accordance with their written comments as under:­   1.      Quantity of brass items (Import item Nos. 12,13,14,17 & 36) may be allowed with 1% wastage.  2.      Quantity of other raw materials may be allowed with 2% wastage. 3.      Components may be allowed on net to net basis without any wastage with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     82

Case No.:115/24/80­ALC2/2008

Party Name:JHAGADIA COPPER LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/00991/AM09/ RLA File :34/24/040/00105/AM09/ Lic.No/Date:3410022188 28.08.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of DC(MSME)  informed  the  Committee  that  they  have  not  received  reply  of  the  firm.  The  Committee  therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.     83

Case No.:95/24/80­ALC2/2008

Party Name:MINDA SILCA ENGINEERING LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/00971/AM09/ RLA File :05/24/040/00337/AM09/ Lic.No/Date:0510226413 28.08.2008 Defer Date: 09.06.2009 informed the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The   84

Case No.:129/24/80­ALC2/2008

Party Name:JAYDEEP INDUSTRIES 14.04.2009 Status:Case deferred HQ File :01/80/050/01005/AM09/ RLA File :52/24/040/00014/AM09/ Lic.No/Date:5210024198 29.08.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The  representative  of DC(MSME)  informed  the  Committee  that  they  have  not  received  firm’s  application.  The  Committee  therefore handed­over the case file to the technical authority for examination and submission of comments. The case may be   85

Case No.:131/24/80­ALC2/2008

LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01007/AM09/ RLA File :03/95/040/00496/AM09/ Lic.No/Date:0310484775 01.09.2008 Defer Date: 09.06.2009   1 Information in respect of Sl No 5 & 11 of the Standard Deficiency Format

1.      Information in respect of Sl.No.5 & 11 of the Standard Deficiency Format. 2.      The specification of material of cladding.     86

Case No.:133/24/80­ALC2/2008

Party Name:MIVEN MAYFRAN CONVEYORS PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01009/AM09/ RLA File :07/24/040/00256/AM09/ Lic.No/Date:0710059499 01.09.2008 Defer Date: 09.06.2009   Information in respect of Sl.No.4,5 & 11 of the Standard Deficiency Format.   87

Case No.:24/39/80­ALC2/2008

Party Name:SURAJ INDUSTRIES 14.04.2009 Status:Case deferred HQ File :01/80/050/01577/AM09/ RLA File :30/24/040/00005/AM09/ Lic.No/Date:3010057794 02.09.2008 Defer Date: 09.06.2009   Information in respect of Sl.No.3, 4,5 & 11 of the Standard Deficiency Format.     88

Case No.:7/39/80­ALC2/2008

Party Name:WEBB INDIA PVT. LTD 14.04.2009 Status:Case approved HQ File :01/80/050/01560/AM09/ RLA File :07/24/040/00353/AM09/ Lic.No/Date:0710060187 29.09.2008   representative of the DC(MSME) present in the meeting recommended the case. The Committee, after   1.      Quantity of import item no. 9 & 10 may be allowed with 1% wastage. 2.      Quantity of rest of the import items may be allowed on net to net basis with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,   89

Case No.:3/39/80­ALC2/2008

Party Name:PETRON ENGINEERING CONSTRUCTION LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01556/AM09/ RLA File :03/95/040/00394/AM09/ Lic.No/Date:0310488593 01.10.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The representative of the DIPP informed the Committee that they had received the firm’s reply and case was under their study and they will finalize their  comments  shortly.  The  Committee,  therefore,  decided  to  defer  the  consideration  and  to  re­list  the  case  on 09.06.2009.     90

Case No.:4/39/80­ALC2/2008

Party Name:TEKSONS LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01557/AM09/ RLA File :03/95/040/01217/AM08/ Lic.No/Date:0310488911 03.10.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.   On the recommendation of the

p p g, y g   Information in respect of Sl.No.3, 4,5 & 11 of the Standard Deficiency Format.   91

Case No.:1/32/80­ALC2/2008

Party Name:WEATHERFORD DRILLING & PRODUCTION SERVICES(I)P.LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01181/AM09/ RLA File :34/24/040/00134/AM09/ Lic.No/Date:3410022519 14.10.2008 Defer Date: 09.06.2009   Information in respect of Sl.No.3, 4 & 5   of the Standard Deficiency Format.     92

Case No.:6/32/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01186/AM09/ RLA File :03/95/040/00541/AM09/ Lic.No/Date:0310490271 14.10.2008     1.      Net empty export weights of 796.1 MT & 272.9 MT may be specified with the quantities of export products at S.Nos. 1 & 2 respectively (total net empty export weight 1069 MT). 2.      Weights of 742817 Kgs. and 108146 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 respectively and their quantities may be allowed on net to net basis. 3.           Weight  of  5035  Kgs  &  3252  Kgs.  may  be  specified  with  the  quantities  of  import  items  at  S.No.  2  &  4 4.      Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5.           Quantities of import items at Sl.No.5 & 6 may be allowed as applied for i.e. 22129 Kgs. & 62915 Kgs. respectively inclusive of   3 % wastage. 6.      Quantity of import item at S.No.7 may be allowed as 1040 mtrs. (7222 Kgs.) inclusive of 2% wastage. 7.      Weights of 75.738 MT, 2.2 MT, 1.5 MT, 2 MT, 2.6 MT, 6 MT & 1.5 MT may be added with the quantities of import items at S.Nos. 8, 9, 10, 11, 12, 18 & 20 respectively and their quantities may be allowed on net to net basis. 8.      Quantities of import items from S.Nos. 13 to 17 may be allowed as applied for. 9.      Import item at S.No.19 may be allowed as per Packing Policy. 10.  Import item at S.No.20 to be supplied alongwith export product. 11.  Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     93

Case No.:12/32/80­ALC2/2008

Party Name:OHSUNG ELECTRONICS INDIA PRIVATE LIMTIED 14.04.2009 Status:Case deferred HQ File :01/80/050/01192/AM09/ RLA File :31/24/040/00182/AM09/ Lic.No/Date:3110035794 15.10.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.  

Case No.:4/32/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ Fil 01/80/050/01184/AM09/ RLA Fil 07/24/040/00319/AM09/ Li N /D 0710060422 D f D

94 HQ File :01/80/050/01184/AM09/ RLA File :07/24/040/00319/AM09/ Lic.No/Date:0710060422 15.10.2008 Defer Date: 09.06.2009   1.      Information in respect of Sl.No.5 & 11 of the Standard Deficiency Format. 2.      Specific quantity of each export product and their weight separately. 3.      Input weight of each casting/ forging and corresponding finished weight. 4.      Use of each component proposed for import in the manufacture of export product. 5.      Weight of steel tubes proposed for import (for example items No. 71 to 73)     95

Case No.:5/32/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01185/AM09/ RLA File :07/24/040/00321/AM09/ Lic.No/Date:0710060423 15.10.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.   On the recommendation of the   1.      Information in respect of Sl.No.5 & 11 of the Standard Deficiency Format. 2.      Specific quantity of each export product and their weight separately. 3.      Input weight of each casting/ forging and corresponding finished weight. 4.      Use of each component proposed for import in the manufacture of export product. 5.      Weight of steel tubes proposed for import (for example items No. 71 to 73)   96

Case No.:11/32/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01191/AM09/ RLA File :09/24/040/00280/AM09/ Lic.No/Date:0910035658 16.10.2008 Defer Date: 09.06.2009   1.      Information in respect of Sl.No.5 & 11 of the Standard Deficiency Format. 2.      Specific quantity of each export product and their weight separately. 3.      Input weight of each casting/ forging and corresponding finished weight. 4.      Use of each component proposed for import in the manufacture of export product. 5.      Weight of steel tubes proposed for import (for example items No. 71 to 73)     97

Case No.:8/32/80­ALC2/2008

Party Name:GUMMI METALL TECHNIK (INDIA)PVT.LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01188/AM09/ RLA File :07/24/040/00395/AM09/ Lic.No/Date:0710060465 16.10.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.The representative of the DHI informed the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The   98

Case No.:9/32/80­ALC2/2008

Party Name:G.B. ENGINEERING ENTERPRISES PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01189/AM09/ RLA File :04/24/040/00172/AM09/ Lic.No/Date:0410099219 16.10.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.

99

Case No.:15/32/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01195/AM09/ RLA File :03/95/040/00555/AM09/ Lic.No/Date:0310490893 17.10.2008     1.      Net empty export weights of 796.1 MT & 272.9 MT may be specified with the quantities of export products at S.Nos. 1 & 2 respectively (total net empty export weight 1069 MT). 2.      Weights of 742817 Kgs. and 108146 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 3.           Weight  of  5035  Kgs  &  3252  Kgs.  may  be  specified  with  the  quantities  of  import  items  at  S.No.  2  &  4 4.      Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5.           Quantities of import items at Sl.No.5 & 6 may be allowed as applied for i.e. 22129 Kgs. & 62915 Kgs. respectively inclusive of   3 % wastage. 6.      Quantity of import item at S.No.7 may be allowed as 1040 mtrs. (7222 Kgs.) inclusive of 2% wastage. 7.      Weights of 75.738 MT, 2.2 MT, 1.5 MT, 2 MT, 2.6 MT, 6 MT & 1.5 MT may be added with the quantities of import items at S.Nos. 8, 9, 10, 11, 12, 18 & 20 respectively and their quantities may be allowed on net to net basis. 8.      Quantities of import items from S.Nos. 13 to 17 may be allowed as applied for. 9.      Import item at S.No.19 may be allowed as per Packing Policy. 10.  Import item at S.No.20 to be supplied alongwith export product. 11.  Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     100

Case No.:16/32/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01196/AM09/ RLA File :03/95/040/00556/AM09/ Lic.No/Date:0310490899 17.10.2008     1.      Net empty export weight of 1087 MT may be specified with the quantity of export product. 2.      Weights of 827950 Kgs. and 65734 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 3.           Weight of 3000 Kgs  &  2253  Kgs.  may  be  specified  with  the  quantities  of  import  items  at  S.No.  2  &  4 4.      Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5.           Quantities of import items at Sl.No.5 & 6 may be allowed as applied for i.e. 19858 Kgs. & 60070 Kgs. respectively inclusive of   3 % wastage. 6.      Quantity of import item at S.No.7 may be allowed as 1129 mtrs. (5993 Kgs.) inclusive of 2% wastage. 7.      Weights of 58.484 MT, 1 MT, 1 MT, 2 MT, 1.5 MT, 12.18 MT, & 0.75 MT may be added with the quantities of import items at S.Nos. 8, 9, 10, 11, 12, 18 & 20 respectively and their quantities may be allowed on net to net basis. 8.      Quantities of import items from S.Nos. 13 to 15 & 17 may be allowed as applied for. 9.      Quantity of import item at S.No.16 may be allowed as 22319 Kgs. 10.  Import item at S.No.19 may be allowed as per Packing Policy. 11.  Import item at S.No.20 to be supplied alongwith export product. 12.  Quantity of import item at S.No.21 may be allowed on net to net basis.    13.  Import of components may be allowed with accountability clause   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,

p ( g p y) p g p     101

Case No.:18/32/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01198/AM09/ RLA File :03/94/040/00698/AM09/ Lic.No/Date:0310491045 20.10.2008 Defer Date: 09.06.2009   102

Case No.:21/32/80­ALC2/2008

Party Name:STARION INDIA P.LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01201/AM09/ RLA File :31/24/040/00190/AM09/ Lic.No/Date:3110035836 20.10.2008 Defer Date: 09.06.2009 representative  of  DIPP  present  in  the  meeting,  it  was  decided  by  the  Committee  to  call  for  the  following   Information in respect of Sl.No.3,5 & 11 of the Standard Deficiency Format export product wise.     103

Case No.:30/32/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01210/AM09/ RLA File :07/24/040/00379/AM09/ Lic.No/Date:0710060602 22.10.2008   DHI furnished written comments in this case vide their U.O. No.3(19)/09­TSW(B)/148 dated 24.03.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization in accordance with their written comments as under:­   1.        Import items at Sl.No. 112, 115, 116, 117 and 126 are not component of export product and may be deleted. 2.        Import of spares may be allowed as per policy for mandatory spares. 3.        All other items may be allowed on net­to­net basis with accountability clause.   Note: The import of components shall be permitted on net­to­net basis with accountability clause and  the  type, technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.     104

Case No.:31/32/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01211/AM09/ RLA File :07/24/040/00378/AM09/ Lic.No/Date:0710060603 22.10.2008   considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.   The  DHI  furnished  written  comments  in  this  case  vide  their  U.O.  No.3(19)/09­TSW(B)/149  dated 24.03.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization in accordance with their written comments as under:­   1.        Import items at Sl.No. 112, 115, 116, 117 and 126 are not component of export product and may be deleted. 2.        Import of spares may be allowed as per policy for mandatory spares. 3.        All other items may be allowed on net­to­net basis.  

105

Case No.:34/32/80­ALC2/2008

Party Name:SUR HENNIG PVT. LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/01214/AM09/ RLA File :07/24/040/00410/AM09/ Lic.No/Date:0710060607 22.10.2008   Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization with following modifications:­   1.      Quantity of Import item Nos. 3, 16 to 21 & 33 may be allowed with 1% wastage.  2.      Import items no. 15, 31, 36 & 37 may be allowed with 2% wastage. 3.      Other import items may be allowed on net to net basis without any wastage with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     106

Case No.:41/32/80­ALC2/2008

Party Name:TEMA INDIA LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01221/AM09/ RLA File :03/95/040/00655/AM09/ Lic.No/Date:0310491632 23.10.2008 Defer Date: 09.06.2009 hardcopy  of  firm’s  application  along  with  clarification  has  not  been  received  so  far  from  concerned  Regional Authority in spite of reminder.  The Committee, therefore, decided to remind RA with a copy to firm to forward 4 set of application along with clarification at the earliest and on receipt forward the same to DIPP for examination and submission of comments. The case may be re­listed on 09.06.2009.     107

Case No.:42/32/80­ALC2/2008

Party Name:MICRON INSTRUMENTS PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/01222/AM09/ RLA File :05/24/040/00474/AM09/ Lic.No/Date:0510229880 23.10.2008     1.  Total net weight of export products may be specified as 231.75 Kgs. 2.  Quantity of import item may be allowed as 1367.3 Kgs. inclusive of  490% wastage after taking 1/3rd recovery   108

Case No.:43/32/80­ALC2/2008

Party Name:MICRON INSTRUMENTS PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/01223/AM09/ RLA File :05/24/040/00475/AM09/ Lic.No/Date:0510229883 23.10.2008     1. Total net weight of export products may be specified as 725.8 Kgs. 2. Quantity of import item may be allowed as 2467.7 Kgs. inclusive of 240% wastage after taking 1/3rd recovery.    

Case No.:44/32/80­ALC2/2008

Party Name:THE SARASWATI INDUSTRIAL SYNDICATE LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01224/AM09/ RLA File :05/24/040/00339/AM09/ Lic No/Date:0510229888 Defer Date:

109 HQ File :01/80/050/01224/AM09/ RLA File :05/24/040/00339/AM09/ Lic.No/Date:0510229888 23.10.2008 Defer Date: 09.06.2009 firm has furnished incomplete reply in response to this office letter calling for certain information. The Committee, therefore, decided to advise the firm to appear before the NC to explain their case in person along with full facts. The case may be re­listed on 09.06.2009.   110

Case No.:45/32/80­ALC2/2008

Party Name:BGR ENERGY SYSTEMS LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/01225/AM09/ RLA File :04/24/040/00170/AM09/ Lic.No/Date:0410099440 23.10.2008 Defer Date: 09.06.2009 Committee observed that the firm has furnished incomplete reply in response to this office letter calling for certain  information.  The  Committee,  therefore,  decided  to  direct  the  firm  to  furnish  the  following information complete in all respects otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009:­     1.    Information in respect of Sl.No.5 & 11 of the Standard    Deficiency Format  export product wise.     2.   Size / Specification of import items at Sl. Nos. 1 to 4 including length of tubes.   111

Case No.:46/32/80­ALC2/2008

Party Name:SUR HENNIG PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01226/AM09/ RLA File :07/24/040/00420/AM09/ Lic.No/Date:0710060659 23.10.2008 Defer Date: 09.06.2009 informed  the  Committee  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The     112

Case No.:49/32/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/01229/AM09/ RLA File :03/94/040/00676/AM09/ Lic.No/Date:0310491730 24.10.2008   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The representative of the DIPP present in the meeting recommended the case. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization with following modifications:­   1. Net empty weights of 42.4 MT,  1.56 MT,  4.4 MT,   8.95 MT,   8.95 MT,   8.95 MT,  18.2  MT,   5.44 MT,   5.44 MT,   5.44 MT,    5.44 MT,  4.4  MT,  5.59  MT,  5.59  MT,  10.85  MT,  10.85  MT,  10.85 MT,  10.85 MT,  7.138 MT,   34.92 MT,   17.352 MT,  18.064  MT,   17.404 MT,    17.523 MT,   6.75 MT,   29.2 MT & 9.25 MT  may be added with the quantities of export products at S.Nos. 1 to 27 respectively. 2. Word “relevant” may be prefixed with the description of import items from S.No. 1 to 4, 12, 18 to 21 & 23. 3. Quantities of import items at S.No.1, 2, 3 & 4 may be allowed as 36682 Kgs., 13136  Kgs., 55299 Kgs. & 9653 Kgs. respectively inclusive of 10% wastage. 4. Weights of 9989 Kgs., 5486 Kgs., 22918 Kgs., 9646 Kgs, 14859 Kgs., 7861 Kgs.,& 2996 Kgs. may be added with the quantities of import items from S.Nos. 5 to 11 respectively and their quantities may be allowed on net to net basis. 5. Quantity of import item at S.No.12 may be allowed as 14 mtrs (1594 Kgs.) inclusive of 2% wastage. 6. Weights of 613 Kgs & 655 Kgs. may be added with the quantities of import items at S.Nos. 13 & 22 respectively and their quantities may be allowed on net to net basis. 7. Quantities of import items at S.Nos. 14, 15 & 16  may be allowed as  2303 Kgs.each. 8. Import item at S.No. 17 may be deleted. 9. Quantity of import item at S.No. 18 may be allowed as 38903 mtrs. (9380 Kgs.) inclusive of 2% wastage. 10. Quantity of import item at S.No. 19 may be allowed as 35087 mtrs. (28005 Kgs.) inclusive of 2% wastage. 11. Quantity of import item at S.No. 20 may be allowed as 461 mtrs. (288 Kgs.) inclusive of 2% wastage 12. Quantity of import item at S.No. 21 may be allowed as 41348 mtrs. (46182  Kgs.) inclusive of 2% wastage. 13. Quantity of import item at S.No. 23 may be allowed as 55 mtrs. (699 Kgs.) inclusive of 2% wastage 14. Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,  technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.   C 0/32/80 A C2/2008 GO & O C G / 2/80 A C2/2009 S C

113

Case No.:50/32/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/01230/AM09/ RLA File :03/94/040/00717/AM09/ Lic.No/Date:0310492142 27.10.2008     1. Net empty weights of 211 MT, 211 MT, 153.5 MT & 153.5 MT may be added with the quantities of export products at S.No.1, 2, 3, & 4  respectively (combined net export weight 729MT). 2. Weights of 25442 Kgs., 42442 Kgs., 388 Kgs. & 6192 Kgs. may be specified with the quantities of import items at S.Nos. 1, 2, 3 & 4 respectively and their quantities may be allowed on net to net basis. 3. Import items at S.Nos. 5, 6, 13 & 14 may be allowed on net to net basis. 4. Word “relevant” may be prefixed with the description of import items at S.Nos. 7 to 12. 5. Quantity of import item at S.No.7 may be allowed as 13 mtrs. (377 Kgs.) inclusive of 2% wastage. 6. Quantity of import item at S.No.8 may be allowed as 188 mtrs. (5284 Kgs.) inclusive of 2% wastage. 7. Quantity of import item at S.No.9 may be allowed as 204 Kgs. inclusive of  2% wastage as applied for by the firm. 8. Quantities  of  import  items  at  S.No.10  &  11  may  be  allowed  as  37045  Kgs.  &  37909  Kgs.  respectively inclusive of 2.3% wastage as applied for by the firm. 9. Quantity of import item at S.No.12 may be allowed as 533392 Kgs. inclusive of 6.7% wastage after 1/3rd recovery. 10. Quantities of import items at S.Nos.  15, 16 & 17 may be allowed as  13526 Kgs.each. 11. Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     114

Case No.:51/32/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case approved HQ File :01/80/050/01231/AM09/ RLA File :03/94/040/00714/AM09/ Lic.No/Date:0310492145 27.10.2008     1. Net empty weights of 182.48 MT & 194 MT may be added with the quantities of export products at S.No.1 & 2 respectively (combined net export weight 376.48 MT). 2. Weights of 11727 Kgs., 13214 Kgs. & 2602 Kgs. may be specified with the quantities of import items at S.Nos. 1,  3 & 4 respectively and their quantities may be allowed on net to net basis. 3. Import items at S.Nos. 2, 5, 6, 12 & 13 may be allowed on net to net basis. 4. Word “relevant” may be prefixed with the description of import items at S.Nos. 7 to 11. 5. Quantity of import item at S.No.7 may be allowed as 178 mtrs. (3045 Kgs.) inclusive of 2% wastage. 6. Quantity  of  import  item  at  S.No.8  may  be  allowed  as  146576  Kgs.  inclusive  of  7.1%  wastage  after  1/3rd recovery. 7. Quantities  of  import  items  at  S.No.9  &  10  may  be  allowed  as  24709    Kgs.  &  25319  Kgs.  respectively inclusive of 2.3% wastage as applied for by the firm. 8. Quantity of import item at S.No.11 may be allowed as 121742 Kgs. inclusive of 7.6% wastage after 1/3rd recovery. 9. Quantities of import items at S.Nos. 14, 15 & 16 may be allowed as  6938  Kgs.each. 10. Weight of 14855 Kgs. may be specified with the quantity of import item at S.Nos. 17 and its quantity may be allowed on net to net basis. 11. Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,

115

Case No.:57/32/80­ALC2/2008

Party Name:VINDHYA TELELINKS LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01237/AM09/ RLA File :11/24/040/00035/AM09/ Lic.No/Date:1110018800 27.10.2008 Defer Date: 09.06.2009 comments  called  for  from  DOT  are  yet  to  be  received.    The  Committee,  therefore,  decided  to  remind  them for expediting their comments. The case may be re­listed on 09.06.2009.   116

Case No.:58/32/80­ALC2/2008

Party Name:VINDHYA TELELINKS LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01238/AM09/ RLA File :11/24/040/00047/AM09/ Lic.No/Date:1110018802 27.10.2008 Defer Date: 09.06.2009 comments  called  for  from  DOT  are  yet  to  be  received.    The  Committee,  therefore,  decided  to  remind  them for expediting their comments. The case may be re­listed on 09.06.2009.   117

Case No.:60/32/80­ALC2/2008

Party Name:KAMAL RUBPLAST INDUSTRIES (P) LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01240/AM09/ RLA File :05/24/040/00477/AM09/ Lic.No/Date:0510230022 27.10.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  the DC(MSME) informed the Committee that they had received the firm’s reply and case was under their study and they will finalize their comments shortly. The Committee, therefore, decided to defer the consideration and to re­list the case on 09.06.2009.     118

Case No.:12/39/80­ALC2/2008

Party Name:NOV SARA INDIA PRIVATE LIMITED 14.04.2009 Status:Case closed HQ File :01/80/050/01565/AM09/ RLA File :61/24/040/00062/AM09/ Lic.No/Date:6110000257 12.12.2008   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that RA vide their letter No. 61/24/040/00062/AM09 dt. 30.03.2009 informed that the subject advance authorization has been issued as per GN – 4 for the engineering products hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.   119

Case No.:26/39/80­ALC2/2008

Party Name:BIRLA ERICSSON OPTICAL LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01579/AM09/ RLA File :11/24/040/00062/AM09/ Lic.No/Date:1110019185 12.12.2008 Defer Date: 09.06.2009 comments called for from DIT/DOT are yet to be received.  The Committee, therefore, decided to remind them for expediting their comments. The case may be re­listed on 09.06.2009.   120

Case No.:14/39/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01567/AM09/ RLA File :04/24/040/00183/AM09/ Lic.No/Date:0410100820 15.12.2008 Defer Date: 09.06.2009   1.      Information in respect of Sl.No.5 & 11 of the Standard Deficiency Format. 2.      Specific quantity of each export product and their weight separately. 3.      Input weight of each casting / forging and corresponding finished weight. 4.      Use of each component proposed for import in the manufacture of export product. 5.      Weight of steel tubes proposed for import.     C N 15/39/80 ALC2/2008 P t N THE SARASWATI M t N /D t 2/80 ALC2/2009 St t C

121

Case No.:15/39/80­ALC2/2008

Party Name:THE SARASWATI INDUSTRIAL SYNDICATE LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01568/AM09/ RLA File :05/24/040/00586/AM09/ Lic.No/Date:0510232526 15.12.2008 Defer Date: 09.06.2009 firm has furnished incomplete reply in response to this office letter calling for certain information. The Committee, therefore, decided to advise the firm to appear before the NC to explain their case in person along with full facts. The case may be re­listed on 09.06.2009.   122

Case No.:16/39/80­ALC2/2008

Party Name:TITAN INDUSTRIES LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/01569/AM09/ RLA File :07/24/040/00512/AM09/ Lic.No/Date:0710061691 15.12.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The representative  of  DIPP informed the Committee that they have not received reply of the firm. The Committee therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.     123

Case No.:17/39/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01570/AM09/ RLA File :03/95/040/00641/AM09/ Lic.No/Date:0310497867 15.12.2008     1. Net empty export weight of 796.1 MT may be specified with the quantity of export product. 2. Weights of 564860 Kgs. and 65734 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 3. Weight  of  4000  Kgs  &  2253  Kgs.  may  be  specified  with  the  quantities  of  import  items  at  S.No.  2  &  4 4. Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5. Quantities  of  import  items  at  Sl.No.5  &  6  may  be  allowed  as  applied  for  i.e.  15053  Kgs.  &  53169  Kgs. respectively inclusive of   3 % wastage. 6. Quantity of import item at S.No.7 may be allowed as 990 mtrs. (6528 Kgs.) inclusive of 2% wastage. 7. Weights of 55.246 MT, 1 MT, 1.5 MT, 1 MT, 1.4 MT, 6 MT & 0.75 MT may be added with the quantities of import items at S.Nos. 8, 9, 10, 11, 12, 18 & 20 respectively and their quantities may be allowed on net to net basis. 8. Quantities of import items from S.Nos.13to17 may be allowed as applied for. 9. Import item at S.No.19 may be allowed as per Packing Policy. 10. Import item at S.No.20 to be supplied alongwith export product. 11. Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,     124

Case No.:18/39/80­ALC2/2008

Party Name:ZINSER TEXTILE SYSTEMS PVT. LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01571/AM09/ RLA File :03/95/040/00549/AM09/ Lic.No/Date:0310497874 15.12.2008 Defer Date: 09.06.2009 comments  called  for  from  Textile  Commissioner  are  yet  to  be  received.    The  Committee,  therefore,  decided  to remind them for expediting their comments. The case may be re­listed on 09.06.2009.  

Case No.:20/39/80­ALC2/2008

Party Name:WEATHERFORD DRILLING & PRODUCTION SERVICES(I)P.LTD 14.04.2009 Status:Case deferred

125 HQ File :01/80/050/01573/AM09/ RLA File :34/24/040/00169/AM09/ Lic.No/Date:3410022901 15.12.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The   126

Case No.:21/39/80­ALC2/2008

Party Name:SGL CARBON INDIA PVT.LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01574/AM09/ RLA File :31/24/040/00230/AM09/ Lic.No/Date:3110036420 15.12.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The     127

Case No.:18/40/80­ALC2/2008

Party Name:TERUMO PENPOL LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01622/AM09/ RLA File :53/24/040/00008/AM09/ Lic.No/Date:5310007118 16.12.2008 Defer Date: 09.06.2009 comments called for from C&PC are yet to be received.  The Committee, therefore, decided to remind them for expediting their comments. The case may be re­listed on 09.06.2009.   128

Case No.:27/39/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01580/AM09/ RLA File :09/24/040/00351/AM09/ Lic.No/Date:0910036322 16.12.2008 Defer Date: 09.06.2009 informed the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The     129

Case No.:29/39/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01582/AM09/ RLA File :03/95/040/00609/AM09/ Lic.No/Date:0310498137 16.12.2008     1.      Net empty export weight of 1087 MT may be specified with the quantity of export product. 2.      Weights of 827950 Kgs. and 65734 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 3.           Weight of 3000 Kgs  &  2253  Kgs.  may  be  specified  with  the  quantities  of  import  items  at  S.No.  2  &  4 4.      Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5.           Quantities of import items at Sl.No.5 & 6 may be allowed as applied for i.e. 19858 Kgs. & 60070 Kgs. respectively inclusive of   3 % wastage. 6.      Quantity of import item at S.No.7 may be allowed as 1129 mtrs. (5993 Kgs.) inclusive of 2% wastage. 7.      Weights of 58.484 MT, 1 MT, 1 MT, 2 MT, 1.5 MT, 12.18 MT, & 0.75 MT may be added with the quantities of import items at S.Nos. 8, 9, 10, 11, 12, 18 & 20 respectively and their quantities may be allowed on net to net basis. 8.      Quantities of import items from S.Nos. 13 to 15 & 17 may be allowed as applied for. 9.      Quantity of import item at S.No.16 may be allowed as 22319 Kgs. 10.  Import item at S.No.19 may be allowed as per Packing Policy. 11.  Import item at S.No.20 to be supplied alongwith export product. 12.  Quantity of import item at S.No.21 may be allowed on net to net basis.    13.  Import of components may be allowed with accountability clause   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,

p p p y yp ,     130

Case No.:30/39/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01583/AM09/ RLA File :03/95/040/00603/AM09/ Lic.No/Date:0310498147 16.12.2008     1.      Net empty export weight of 1178.8 MT may be specified with the quantity of export product. 2.      Weights of 409446 Kgs. and 82638 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 3.           Weight  of  3000  Kgs  &  1500  Kgs.  may  be  specified  with  the  quantities  of  import  items  at  S.No.  2  &  4 4.      Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5.           Quantities of import items at Sl.No.5 & 6 may be allowed as applied for i.e. 30659 Kgs. & 75420 Kgs. respectively inclusive of   3 % wastage. 6.      Quantity of import item at S.No.7 may be allowed as 495 mtrs. (2392 Kgs.) inclusive of 2% wastage. 7.      Weights of 81.427 MT, 2 MT, 2.5 MT, 4 MT, 10.6 MT & 0.75 MT may be added with the quantities of import items at S.Nos. 8, 9, 11, 12, 18 & 21 respectively and their quantities may be allowed on net to net basis. 8.      Import item at S.No. 10 may be deleted. 9.       Quantities of import items from S.Nos. 13 to 15 may be allowed as applied for. 10.  Quantities of import item at S.No  16 & 17 may be allowed as 22991 Kgs. & 60040 Kgs. respectively. 11.  Import item at S.No.19 may be allowed as per Packing Policy. 12.  Quantity of import item at S.No 20 may be allowed as 5 Nos. on net to net basis. However, duty free weight may be restricted to 655980 Kgs. inclusive of 47% wastage after 20% recovery. 13.  Import item at S.No.21 to be supplied alongwith export product. 14.  Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,  technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.   131

Case No.:31/39/80­ALC2/2008

LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01584/AM09/ RLA File :03/95/040/00665/AM09/ Lic.No/Date:0310498153 16.12.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   132

Case No.:34/39/80­ALC2/2008

Party Name:GUHRING INDIA PRIVATE LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01587/AM09/ RLA File :07/24/040/00493/AM09/ Lic.No/Date:0710061716 16.12.2008 Defer Date: 09.06.2009 and on receipt forward the same to DHI for examination and submission of comments. The case may be re­listed on 09.06.2009.  

Case No.:36/39/80­ALC2/2008

Party Name:INTERNATIONAL COIL LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/01589/AM09/ RLA File :05/24/040/00604/AM09/ Lic.No/Date:0510232759 Defer Date:

133 16.12.2008 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  DIPP informed the Committee that they have not received reply of the firm. The Committee therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.     134

Case No.:37/39/80­ALC2/2008

Party Name:BOYSEN INDIA LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01590/AM09/ RLA File :05/24/040/00612/AM09/ Lic.No/Date:0510232794 17.12.2008 Defer Date: 09.06.2009 Committee observed that RA has forwarded incomplete application. The Committee, therefore, decided to remind RA to furnish the 4 set of complete application for examination by the NC.   The case may be re­ listed on 09.06.2009:­   135

Case No.:38/39/80­ALC2/2008

Party Name:GKB RX LENS PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/01591/AM09/ RLA File :02/24/040/00231/AM09/ Lic.No/Date:0210121273 18.12.2008   C&PC  furnished  written  comments  in  a  similar  case  of  the  applicant  firm  vide  their  O.M.  No.46011/42/2007­PC.II dated 23.03.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization on the basis of  earlier  decision  in  the similar case as under:­   1.      Quantity of import item No. 1 viz. Spectacle Lenses Semi Finished Raw Material may be allowed with 2% wastage. 2.      Quantity of other import items may be allowed as recommended by C&PC in their O.M. referred to above.     136

Case No.:42/39/80­ALC2/2008

Party Name:DUCTMASTER INDIA PVT.LTD, 14.04.2009 Status:Case deferred HQ File :01/80/050/01595/AM09/ RLA File :07/24/040/00462/AM09/ Lic.No/Date:0710061800 18.12.2008 Defer Date: 09.06.2009 hardcopy of firm’s application has not been received so far from concerned Regional Authority.  The Committee, therefore, decided to remind RA to forward the firm’s application at the earliest and on receipt forward the same to technical  authority  i.e  DIPP  for  examination  and  submission  of  comments.      The  case  may  be  re­listed  on 09.06.2009.   137

Case No.:43/39/80­ALC2/2008

Party Name:RAJ HAMSA ULTRALIGHTS PVT LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01596/AM09/ RLA File :07/24/040/00519/AM09/ Lic.No/Date:0710061805 18.12.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   138

Case No.:44/39/80­ALC2/2008

Party Name:POLY MEDICURE LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01597/AM09/ RLA File :05/24/040/00609/AM09/ Lic.No/Date:0510232951 18.12.2008 Defer Date: 09.06.2009 comments called for from C&PC are yet to be received.  The Committee, therefore, decided to remind them for expediting their comments. The case may be re­listed on 09.06.2009.

139

Case No.:50/39/80­ALC2/2008

Party Name:NICOMET INDUSTRIES LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01603/AM09/ RLA File :03/95/040/00793/AM09/ Lic.No/Date:0310498704 18.12.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.     140

Case No.:48/39/80­ALC2/2008

Party Name:PAHARPUR COOLING TOWERS LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/01601/AM09/ RLA File :02/24/040/00218/AM09/ Lic.No/Date:0210121313 19.12.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  DIPP informed the Committee that they have not received reply of the firm. The Committee therefore handed­over the firm’s reply to the technical authority for examination and submission of comments. The case may be re­listed on 09.06.2009.   141

Case No.:49/39/80­ALC2/2008

Party Name:GKB RX LENS PVT LTD 14.04.2009 Status:Case approved HQ File :01/80/050/01602/AM09/ RLA File :02/24/040/00233/AM09/ Lic.No/Date:0210121346 19.12.2008   considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.    The  C&PC  furnished  written  comments  in  a  similar  case  of  the  applicant  firm  vide  their  O.M.  No.46011/42/2007­PC.II dated 23.03.2009. The Committee, after deliberating upon the case, decided to ratify the norms in respect of the subject advance authorization on the basis of  earlier  decision  in  the similar case as under:­   1.           Quantity  of  import  item  No.  15  i.e.  Spectacle  Lenses  Semi  Finished  may  be  allowed  with  2  % wastage. 2.      Quantity of other import items may be allowed as recommended by C&PC in their O.M. referred to above.accord       142

Case No.:9/40/80­ALC2/2008

LIMITED 14.04.2009 Status:Case approved HQ File :01/80/050/01613/AM09/ RLA File :03/95/040/00526/AM09/ Lic.No/Date:0310498998 19.12.2008     1.      Net empty export weight of 1488.3 MT may be specified with the quantity of export product. 2.      Weights of 588740 Kgs. and 84394 Kgs. may be specified with the quantities of import items at S.No. 1 & 3 3.           Weights of 4000 Kgs & 2331 Kgs. may be specified with the quantities of import items at S.No. 2 & 4 4.      Word “Relevant” may be prefixed with the descriptions of import items at S.Nos. 5, 6 & 7. 5.           Quantities of import items at Sl.No.5 & 6 may be allowed as applied for i.e. 44323 Kgs. & 85596  Kgs. respectively inclusive of   3 % wastage. 6.      Quantity of import item at S.No.7 may be allowed as 495 mtrs. (7344 Kgs.) inclusive of 2% wastage. 7.      Weights of 86.642 MT, 2.5 MT, 2.5 MT, 2.5 MT, 9.4 MT & 0.75 MT may be added with the quantities of import items at S.Nos. 8, 9, 11, 12, 18 & 21 respectively and their quantities may be allowed on net to net basis. 8.      Import item at S.No. 10 may be deleted. 9.      Quantities of import items from S.Nos. 13 to 15, 17 & 22 may be allowed as applied for. 10.  Quantity of import item at S.No  16  may be allowed as 27811 Kgs. 11 I t it t S N 19 b ll d P ki P li

11.  Import item at S.No.19 may be allowed as per Packing Policy. 12.  Quantity of import item at S.No 20 may be allowed as 6 Nos. on net to net basis. However, duty free weight may be restricted to 782776 Kgs. inclusive of 45.2% wastage after 20% recovery. 13.  Import item at S.No.21 to be supplied alongwith export product. 14.  Import of components may be allowed with accountability clause.   Note:  The  import  of  components  shall  be  permitted  on  net­to­net  basis  with  accountability  clause  and  the  type,  technical specifications (including part No. if any) etc. of the Components sought for import should conform to those utilized in the manufacture of the resultant product.   143

Case No.:1/40/80­ALC2/2008

Party Name:CIM TOOLS PVT.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01605/AM09/ RLA File :07/24/040/00511/AM09/ Lic.No/Date:0710061857 22.12.2008 Defer Date: 09.06.2009 reply of the firm had been received by this office in response to this office letter calling for certain information. The 09.06.2009.   144

Case No.:6/40/80­ALC2/2008

Party Name:OHSUNG ELECTRONICS INDIA PRIVATE LIMTIED 14.04.2009 Status:Case deferred HQ File :01/80/050/01610/AM09/ RLA File :31/24/040/00251/AM09/ Lic.No/Date:3110036564 22.12.2008 Defer Date: 09.06.2009 representative  of  DIPP  present  in  the  meeting,  it  was  decided  by  the  Committee  to  call  for  the  following   Information in respect of Sl.No.5,11 & 11a of the Standard Deficiency Format export product wise.   145

Case No.:7/40/80­ALC2/2008

Party Name:SANDVIK ASIA LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01611/AM09/ RLA File :31/24/040/00236/AM09/ Lic.No/Date:3110036574 22.12.2008 Defer Date: 09.06.2009 and on receipt forward the same to DIPP for examination and submission of comments. The case may be re­listed on 09.06.2009.     146

Case No.:10/40/80­ALC2/2008

Party Name:MINDA SILCA ENGINEERING LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01614/AM09/ RLA File :05/24/040/00565/AM09/ Lic.No/Date:0510233251 23.12.2008 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The Committee  noted  that and on receipt forward the same to DHI for examination and submission of comments. The case may be re­listed on 09.06.2009.   147

Case No.:8/40/80­ALC2/2008

Party Name:VA TECH ESCHER WYSS FLOVELPVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01612/AM09/ RLA File :05/24/040/00631/AM09/ Lic.No/Date:0510233247 23.12.2008 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The  

Case No :20/40/80­ALC2/2008

Party Name:MADRAS HYDRAULIC Meet No/Date:2/80­ALC2/2009 Status:Case

148

Case No.:20/40/80­ALC2/2008

Party Name:MADRAS HYDRAULIC HOSE PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01624/AM09/ RLA File :04/24/040/00224/AM09/ Lic.No/Date:0410101209 24.12.2008 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The committee noted that DGFT has  referred  the  case  to  DHI  whereas  the  case  pertains  to  DIPP.    The  committee  accordingly,  advised  the representative of DHI to transfer the case to DIPP for examination and submission of comments. The case may be     149

Case No.:3/48/80­ALC2/2008

Party Name:MINDA SILCA ENGINEERING LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01764/AM09/ RLA File :05/24/040/00706/AM09/ Lic.No/Date:0510235844 05.02.2009 Defer Date: 09.06.2009 Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The DC(MSME) has desired some information vide their U.O. No. 30(356)2008­ME dt. 25.03.2009. The Committee has decided to ask the firm to furnish the following information/clarification desired by the technical authority otherwise their case would be rejected.   The case may be re­listed on 09.06.2009:­   1.      Weight of each export product (all the three) separately for each pice and total number of pieces. 2.      Sheet layout diagram of the material indicating the wastage during the operation of blanking. 3.      Details of calculation, as how the quantity of raw material has been arrived with complete wastage justification. 4.      Process of manufacturing and stepwise wastage therein.   150

Case No.:4/48/80­ALC2/2008

Party Name:ECOCAT INDIA PVT.LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01765/AM09/ RLA File :05/24/040/00707/AM09/ Lic.No/Date:0510235848 05.02.2009 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The Committee  noted  that and on receipt forward the same to DHI/DC(MSME) for examination and submission of comments. The case may be re­listed on 09.06.2009.     151

Case No.:7/48/80­ALC2/2008

Party Name:PYRO ELECTRIC INSTRUMENTS GOA PVT.LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01768/AM09/ RLA File :17/24/040/00101/AM09/ Lic.No/Date:1710002402 05.02.2009 Defer Date: 09.06.2009 representative  of  DIPP  present  in  the  meeting,  it  was  decided  by  the  Committee  to  call  for  the  following   Information in respect of Sl.No.11 of the Standard Deficiency Format for import item at Sl.No. 2.   152

Case No.:10/48/80­ALC2/2008

Party Name:KINETIC ENGINEERING LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01771/AM09/ RLA File :31/24/040/00304/AM09/ Lic.No/Date:3110037278 06.02.2009 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.  The  representative  of  DHI informed the Committee that they have not received application of the firm. The Committee therefore handed­over the firm’s application to the technical authority for examination and submission of comments. The case may be re­ listed on 09.06.2009.   153

Case No.:11/48/80­ALC2/2008

Party Name:RANGSONS ELECTRONICS PVT LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01772/AM09/ RLA File :07/24/040/00553/AM09/ Lic.No/Date:0710062859 06.02.2009 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The Committee  noted  that h d f fi ’ li ti h t b i d f f d R i l A th it i it f i d

and on receipt forward the same to DIT for examination and submission of comments. The case may be re­listed on 09.06.2009.     154

Case No.:12/48/80­ALC2/2008

CO. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01773/AM09/ RLA File :03/94/040/00953/AM09/ Lic.No/Date:0310506016 06.02.2009 Defer Date: 09.06.2009   1.        Value of individual items proposed for import. 2.        Appendix 11A of the application does not match with total requirement in the application. 3.        Gross weight and net weight of item no. 4 to 7 of import. 4.        Weight of tube (item No. 8 of import) 5.        Weight and specification of item no. 9 of import. 6.        Information in respect of Sl.No.3,4,5 & 11 of the Standard Deficiency Format.   155

Case No.:13/48/80­ALC2/2008

Party Name:ZINSER TEXTILE SYSTEMS PVT. LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01774/AM09/ RLA File :03/95/040/00716/AM09/ Lic.No/Date:0310506022 06.02.2009 Defer Date: 09.06.2009 comments  called  for  from  Textile  Commissioner  are  yet  to  be  received.    The  Committee,  therefore,  decided  to remind them for expediting their comments. The case may be re­listed on 09.06.2009.   156

Case No.:29/48/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01790/AM09/ RLA File :61/24/040/00069/AM09/ Lic.No/Date:6110000286 06.02.2009 Defer Date: 09.06.2009 and on receipt forward the same to DHI for examination and submission of comments. The case may be re­listed on 09.06.2009.   157

Case No.:6/48/80­ALC2/2008

Party Name:TIMKEN INDIA LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01767/AM09/ RLA File :02/24/040/00259/AM09/ Lic.No/Date:0210122985 06.02.2009 Defer Date: 09.06.2009 representative  of  DIPP  present  in  the  meeting,  it  was  decided  by  the  Committee  to  call  for  the  following   Information in respect of Sl.No.3,4 & 11 of the Standard Deficiency Format export product wise.   158

Case No.:8/48/80­ALC2/2008

Party Name:RATHI TRANSPOWER PVT.LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01769/AM09/ RLA File :31/21/040/00369/AM09/ Lic.No/Date:3110037268 06.02.2009 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The Committee  noted  that and on receipt forward the same to DHI for examination and submission of comments. The case may be re­listed on 09.06.2009.  

Case No.:5/48/80­ALC2/2008

Party Name:RANGSONS ELECTRONICS PVT LTD 14.04.2009 Status:Case deferred

159 HQ File :01/80/050/01766/AM09/ RLA File :07/24/040/00559/AM09/ Lic.No/Date:0710062891 09.02.2009 Defer Date: 09.06.2009 and on receipt forward the same to DIT for examination and submission of comments. The case may be re­listed on 09.06.2009.     160

Case No.:15/48/80­ALC2/2008

Party Name:ABB LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01776/AM09/ RLA File :07/24/040/00610/AM09/ Lic.No/Date:0710062941 10.02.2009 Defer Date: 09.06.2009 and on receipt forward the same to DHI / DIT for examination and submission of comments. The case may be re­ listed on 09.06.2009.   161

Case No.:17/48/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01778/AM09/ RLA File :11/24/040/00073/AM09/ Lic.No/Date:1110019583 10.02.2009 Defer Date: 09.06.2009 informed  the  Committee  that  they  received  the  firm’s  reply  and  case  was  under  their  study.  The  Committee, therefore, decided to defer the consideration and to relist the case on 09.06.2009.   162

Case No.:18/48/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01779/AM09/ RLA File :11/24/040/00076/AM09/ Lic.No/Date:1110019584 10.02.2009 Defer Date: 09.06.2009   1. Specific quantity of each export product with details of the accessories and their weight separately. 2. Input Weight of each casting / forging and corresponding finished weight. 3. Use of each component proposed for import in the manufacture of export product. 4. Information in respect of Sl.No.5 & 11 of the Standard Deficiency Format.     163

Case No.:19/48/80­ALC2/2008

Party Name:KIRLOSKAR PNEUMATIC CO LTD 14.04.2009 Status:Case deferred HQ File :01/80/050/01780/AM09/ RLA File :31/24/040/00303/AM09/ Lic.No/Date:3110037315 10.02.2009 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The Committee  noted  that and on receipt forward the same to DIPP for examination and submission of comments. The case may be re­listed on 09.06.2009.   164

Case No.:20/48/80­ALC2/2008

Party Name:EMERSON PROCESS MANAGEMENT (INDIA) PVT.LTD. 14.04.2009 Status:Case closed HQ File :01/80/050/01781/AM09/ RLA File :03/94/040/01018/AM09/ Lic.No/Date:0310506584 11.02.2009   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that RA vide their letter dt. 11.02.2009 informed that the subject advance authorization has been issued as per GN – 4 for the engineering products hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.

165

Case No.:21/48/80­ALC2/2008

Party Name:ALSTOM PROJECTS INDIA LIMITED, 14.04.2009 Status:Case approved HQ File :01/80/050/01782/AM09/ RLA File :32/21/040/00166/AM09/ Lic.No/Date:3210039716 11.02.2009   Decision : The case regarding ratification of norms in respect of above advance authorization was considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The representative of the DHI present in the meeting recommended the case. The Committee, after deliberating  upon  the  case,  decided  to  ratify  the  norms  in  respect  of  the subject advance authorization as per General Note No.4 for Engineering Product.     166

Case No.:22/48/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01783/AM09/ RLA File :09/24/040/00401/AM09/ Lic.No/Date:0910037049 12.02.2009 Defer Date: 09.06.2009 and on receipt forward the same to DHI for examination and submission of comments. The case may be re­listed on 09.06.2009.   167

Case No.:23/48/80­ALC2/2008

ELECTRICALS LIMITED 14.04.2009 Status:Case deferred HQ File :01/80/050/01784/AM09/ RLA File :09/24/040/00408/AM09/ Lic.No/Date:0910037050 12.02.2009 Defer Date: 09.06.2009 Norms  Committee  (NC­I)  in  its  M.No.02/10  held  on  16.04.2009  as  per  the  agenda.    The Committee  noted  that and on receipt forward the same to DHI for examination and submission of comments. The case may be re­listed on 09.06.2009.   168

Case No.:24/48/80­ALC2/2008

Party Name:PRECIHOLE MACHINE TOOLS PVT. LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01785/AM09/ RLA File :03/95/040/00936/AM09/ Lic.No/Date:0310506902 12.02.2009 Defer Date: 09.06.2009 informed the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The     169

Case No.:26/48/80­ALC2/2008

Party Name:ZINSER TEXTILE SYSTEMS PVT. LTD. 14.04.2009 Status:Case deferred HQ File :01/80/050/01787/AM09/ RLA File :03/95/040/00876/AM09/ Lic.No/Date:0310507257 16.02.2009 Defer Date: 09.06.2009 comments  called  for  from  Textile  Commissioner  are  yet  to  be  received.    The  Committee,  therefore,  decided  to remind them for expediting their comments. The case may be re­listed on 09.06.2009.   170

Case No.:27/48/80­ALC2/2008

Party Name:TELCO CONSTRUCTION EQUIPMENT CO. LTD., 14.04.2009 Status:Case closed HQ File :01/80/050/01788/AM09/ RLA File :03/95/040/00371/AM09/ Lic.No/Date:0310507433 16.02.2009   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that RA vide their letter dt. 17.02.2009 informed that the subject advance authorization has been issued as per GN – 4 for the engineering products hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.

171

Case No.:28/48/80­ALC2/2008

Party Name:ICEM ENGINEERING COMPANY LIMITED, 14.04.2009 Status:Case deferred HQ File :01/80/050/01789/AM09/ RLA File :03/94/040/01013/AM09/ Lic.No/Date:0310507440 16.02.2009 Defer Date: 09.06.2009 representative  of  DIPP  present  in  the  meeting,  it  was  decided  by  the  Committee  to  call  for  the  following   1.      Separate quantities of Carbon Steel Roll Shell and Dished Ends in numbers and weights. 2.  Information in respect of items at S.Nos. 3, 5 & 11 of Standard Deficiency Format     172

Case No.:30/48/80­ALC2/2008

Party Name:TELCO CONSTRUCTION EQUIPMENT CO. LTD., 14.04.2009 Status:Case closed HQ File :01/80/050/01791/AM09/ RLA File :03/95/040/00282/AM09/ Lic.No/Date:0310507456 16.02.2009   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that RA vide their letter dt. 17.02.2009 informed that the subject advance authorization has been issued as per GN – 4 for the engineering products hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.   173

Case No.:31/48/80­ALC2/2008

Party Name:TELCO CONSTRUCTION EQUIPMENT CO. LTD., 14.04.2009 Status:Case closed HQ File :01/80/050/01792/AM09/ RLA File :03/95/040/00370/AM09/ Lic.No/Date:0310507465 16.02.2009   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee noted that RA vide their letter dt. 17.02.2009 informed that the subject advance authorization has been issued as per GN – 4 for the engineering products hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.   174

Case No.:32/48/80­ALC2/2008

Party Name:TELCO CONSTRUCTION EQUIPMENT CO. LTD., 14.04.2009 Status:Case closed HQ File :01/80/050/01793/AM09/ RLA File :03/95/040/01195/AM08/ Lic.No/Date:0310507467 16.02.2009   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The Committee noted that RA vide their letter dt. 17.02.2009 informed that the subject advance authorization has been issued as per GN – 4 for the engineering products hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.     175

Case No.:37/48/80­ALC2/2008

Party Name:METSO PAPER INDIA PVT.LTD. 14.04.2009 Status:Case closed HQ File :01/80/050/01798/AM09/ RLA File :05/24/040/00722/AM09/ Lic.No/Date:0510236514 16.02.2009   Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The Committee noted that RA vide their letter dt. 17.02.2009 informed that the subject advance authorization has been issued as per Public Notice No. 20 hence hard copy of the firm’s application not forwarded to NC. The Committee accordingly decided to close the case on the part of NC without any examination.   176

Case No.:33/48/80­ALC2/2008

Party Name:THERMAL SYSTEMS (HYDERABAD) P.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01794/AM09/ RLA File :09/24/040/00419/AM09/ Lic.No/Date:0910037105 17.02.2009 Defer Date: 09.06.2009 informed the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The   C N 34/48/80 ALC2/2008 P N THERMAL SYSTEMS M N /D 2/80 ALC2/2009 S C

177

Case No.:34/48/80­ALC2/2008

Party Name:THERMAL SYSTEMS (HYDERABAD) P.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01795/AM09/ RLA File :09/24/040/00418/AM09/ Lic.No/Date:0910037106 17.02.2009 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The     178

Case No.:35/48/80­ALC2/2008

Party Name:THERMAL SYSTEMS (HYDERABAD) P.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01796/AM09/ RLA File :09/24/040/00414/AM09/ Lic.No/Date:0910037107 17.02.2009 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The   179

Case No.:36/48/80­ALC2/2008

Party Name:THERMAL SYSTEMS (HYDERABAD) P.LTD., 14.04.2009 Status:Case deferred HQ File :01/80/050/01797/AM09/ RLA File :09/24/040/00420/AM09/ Lic.No/Date:0910037108 17.02.2009 Defer Date: 09.06.2009 informed  the  Committee  that  the  case  was  under  their  study  and  they  will  finalize  their  comments  shortly.  The       S.No. 01

Case No.  A­09

M/s. Trumac Engg. Co. P. Ltd;  Ahmedaad HQ F.No.01/80/162/880/AM.09/DES.I Lic.No. & Date Meeting No.02/10 RA F.No.03/95/40/39/2/AM09 0310488667 dt.01.10.2009 Date: 14.04.2009 Ratification of norms The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee observed that the comments called  for  from  Textile  Commissioner  are  yet  to  be  received.    The  Committee,  therefore,  decided  to  remind  them  for expediting their comments. The case may be re­listed on 09.06.2009.     S.No.01

Case No.  A/R­59

M/s.  Navkar  Transcore P.   Ltd;  Ahmedaad HQ F.No.01/80/50/1322/AM07/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.08/24/40/308/AM07 0810062841 dt.9.2.2007 Date: 14.04.2009 Revision of norms The case regarding revision of norms in respect of above advance authorization was considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The committee decided to restore the description as applied for by the firm with the flexibility that width of export product may be allowed as 50 mm to 460 mm as requested by the firm in their letter dt. 05.05.2008.     S.No.02

Case No.  A/R­60

M/s.  Alstom Projects  India Ltd;, Vadodara HQ F.No.01/80/50/1180/AM07/DES.I HQ F.No.01/80/50/00844/AM07/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.03/94/40/01100/AM07 RA F.No.03/94/40/00850/AM07 0310414907 dt. 08.01.2007 0310406397 dt. 02.11.2206 Date: 14.04.2009 Revision of norms The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  DGFT’s files were sent to DHI but these files are not available in DHI and therefore it was decided to reconstruct these files calling for available papers from the firm & RA.  The case will be re­listed on 09.06.2009.     S.No.03

Case No.  A/R­63

M/s.  Godrej  &  Boyce Mfg. Co. Ltd. Mumbai HQ F.No.01/80/50/00961/AM08/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.03/94/040/587/AM08 0310442080 dt.06.9.2007 Date: 14.04.2009 Revision of norms The  case  regarding  revision  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The representative of the DIPP informed the Committee that the case was under their study and they will finalize their comments shortly. The Committee, therefore, decided to defer the consideration and to re­list the case on 09.06.2009.

S.No.04

Case No.  A/R­64

M/s. Micron Instruments  P.   Ltd;  New Delhi HQ F.No.01/80/50/307/AM08/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.05/24/40/300/AM08 0510206450 dt.18.07.2007 Date: Revision of norms The  case  regarding  revision  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The Committee observed that no reply of the firm had been received by this office in response to this office letter calling for certain information. The Committee, therefore, decided to remind the firm for expediting the said information otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009.     S.No.05

Case No.  A/R­65

M/s. Micron Instruments  P.   Ltd;  New Delhi HQ F.No.01/80/162/711/AM08/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.05/24/40/306/AM08 510206559 dt.20.07.2007 Date: 14.04.2009 Revision of norms The  case  regarding  revision  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee observed that no reply of the firm had been received by this office in response to this office letter calling for certain information. The Committee, therefore, decided to remind the firm for expediting the said information otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009.     S.No.06

Case No.  A/R­67

M/s.  Navkar  Transcore P.   Ltd;  Ahmedaad HQ F.No.01/80/162/95/AM08/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.08/24/40/344/AM07 0810063837 dt.23.03.2007 Date: Revision of norms The case regarding revision of norms in respect of above advance authorization was considered by the Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The Committee reviewed the agend and observed that request for variation in westage cannot be considered as it is time barred. The committee further observed that NC had not suggested any amendment in the description of import items and export items as pointed out by the firm.   The committee accordingly decided to forward the earlier NC decision to the firm for their information.  The case may be closed from NC.               S.No.07

Case No.  A/R­68

M/s. MPP Technologies P. Ltd; Banglore HQ F.No.01/80/162/921/AM07/DES.I Lic.No. & Date Meeting 02/10 RA F.No.34/21/40/915/AM07 0710048373 dt.13.11.2006 Date: 14.04.2009 Revision of norms The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The committee noted that the case file is readily not available in the DGFT.  The committee accordingly decided to ask the firm to forward 4 set of application, licence and AWS standards at the earliest to take a view on the firm’s request. The case may be re­listed on 09.06.2009.     S.No.08

Case No.  A/R­73

M/s.Magppie  International Ltd; New Delhi HQ F.No.01/80/50/695/AM07/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.05/24/40/538/AM07 0510191655 dt.25.09.2006 Date: 14.04.2009 Revision of norms The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The representative of the firm Shri Sachin Jain  accompanied  by  two  executives  appeared  before  the  Committee  for  personal  hearing.  They  explained  the manufacturing process to the Committee.  The  Committee,  advised  them  to  furnish  the  amended  description  of  their export and import items reflecting clear difference between the products. They promised to furnish the same as per advice. After receipt of the proper reply from the firm, norms may be ratified under GN­4.  The case may be re­listed on 09.06.2009 if any need arise.     S.No.09

Case No.  A/R­76

M/s. Windsor Machine Ltd; Mumbai HQ F.No.01/81/50/742/AM01/DES.II/I Lic.No. & Date Meeting No. 02/10 RA F.No.03/010/770/AM01/ZALC 0310056052 dt. 06.10.2000 Date: 14.04.2009 Revision of norms The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda.  The representative of the DHI informed the Committee that the case was under their study and they will finalize their comments shortly. The Committee, therefore, decided to defer the consideration and to re­list the case on 09.06.2009.   S.No.10

Case No.  A/R­85

  M/s.  Voltas  Ltd., Mumbai HQ F.No.01/81/50/340/AM08/DES.II/DES.I Lic.No. & Date Meeting No. 02/10 RA F.No.3/95/040/603/AM08 0310444434 Dt. 27.09.2007 Date: 14.04.2009 Ratification of Norms The  case  regarding  ratification  of  norms  in  respect  of  above  advance  authorization  was  considered  by  the  Norms Committee (NC­I) in its M.No.02/10 held on 16.04.2009 as per the agenda. The Committee observed that no reply of the firm  had  been  received  by  this  office  in  response  to  this  office  letter  calling  for  certain  information.  The  Committee, h f d id d i d h fi f di i h id i f i h i h i ill b j d i h

therefore, decided to remind the firm for expediting the said information otherwise their case will be rejected without any further chance and no further representation will be entertained.   The case may be re­listed on 09.06.2009.   (B. C. Nayak D.O., DHI)  Member      (S.K. Jain, D.O., DIPP)      Member               (B.D. Ghosh, Jt. IA, MOS) Member       (K.K. Funda, Asstt. Director)       Member           (A.K. Mishra, AIA, MOS) Member        (Krishan Kumar, Dy. DGFT)       Convener           (A. Komu) Chairman