SEEPZ SPECIAL ECONOMIC ZONE ANDHERI (EAST), MUMBAI.

AGENDA FOR MEETING OF THE APPROVAL COMMITTEE FOR SECTOR SPECIFIC SPECIAL ECONOMIC ZONE FOR IT/ITES AT PUNE OF M/S. NALANDA SHELTER PRIVATE LTD.

DATE : 11.12.2024

TIME : 11:00 A.M.


MEETING OF THE APPROVAL COMMITTEE FOR SECTOR SPECIFIC SPECIAL ECONOMIC ZONE FOR IT/ITES AT PUNE, UNDER THE CHAIRMANSHIP OF DEVELOPMENT COMMISSIONER, SEEPZ-SEZ ON 11.12.2024 INDEX

Agenda Item No.

Subject

Agenda Item No. 01 :- Confirmation of the Minutes of the meeting held on 15.10.2024 Agenda Item No. 02 :- Action taken report for the Minutes of the meeting held on 15.10.2024 Agenda Item No. 03 :- Application for approval of Broad Banding of Additional Services with revision in projection. submitted by M/s. Hella India Automotive Pvt. Agenda Item No. 04 :- Monitoring of performance of M/s. Infovision Labs India Pvt. Ltd.


मेसस नालंदा शे टर ाइवेट लिमटेड -एसईजेड, पुणे,, के आईटी/आईटीईएस के लए से टर िव श िवशेष आ!थक #े$, का जोनल िवकास आयु' क( अ*य#ता म, , पुणे म, िदनांक 15.10.2024 को आयो-जत 44वी अनुमोदन सिम.त क( बैठक का कायवृ3। 1 एसईजेड का नाम मेसस नालंदा शे टर ाइवेट लिमटेड -एसईजेड, पुणे 2 से टर आईटी/आईटीईएस 3 बैठक सं4या 44व5
4 तारीख 15.10.2024

उप89थत सद9य :. नाम और पदनाम (एस/<ी.)
िवभाग 1 <ीमती िमतल िहरेमठ संयु' िवकास आयु' पुणे @9टर एसईजेड, पुणे 2 <ी संजय बांगर, उप िनदेशक उAोग, उAोग िवभाग पुणे #े$ महाराB सरकार से नािमत 3 <ीमती अचना परब सहायक आयु', आयकर िवभाग आयकर िवभाग से नािमत

4 <ीमती पुDपा गंगावणे, एफ़ टी डी ओ, पुणे डीजीएफटी िवभाग से नािमत 5 <ी धवल एस शकI , अधी#क सीमा शु क िवभाग पुणे से नािमत

िवशेष आमंि$त सद9य :. नाम और पदनाम (<ी.)
िवभाग 1 <ी सतबीर शमा िविनJद अ.धकारी सीKज़-एसईज़ेड, पुणे @9टर

एज,डा आइटम नंबर 01: िदनांक 16.08.2024 को आयो-जत 43व5 बैठक के कायवृ3 क( पुि

िवचार-िवमश के बाद, सिम.त ने 16.08.2024 को आयो-जत अनुमोदन सिम.त क( 43व5 बैठक के कायवृ3 क( पुि क(

एज,डा आइटम नंबर 02: िदनांक 16.08.2024 को आयो-जत 43व5 बैठक के संदभ मे क( गयी कायवाई क( Mरपोट ।

िवचार-िवमश के बाद, सिम.त ने 16.08.2024 को आयो-जत अनुमोदन सिम.त क( 43व5 बैठक के के संदभ मे क( गयी कायवाई क( Mरपोट को नोट िकया।

एज,डा आइटम नंबर 3: मेसस लेट,ट िNज ाइवेट लिमटेड Oारा 9तुत नई इकाई क( 9थापना के अनुमोदन के लए आवेदन:

िवचार-िवमश के बाद, सिम.त ने नालंदा शे टर ाइवेट लिमटेड -एसईजेड म, एक नई इकाई क( 9थापना के लए मेसस लेट,ट िNज ाइवेट लिमटेड के 9ताव को एसईजेड िनयम, 2006 के िनयम 17 और 18 के अनुसार मंजूरी दे दी। अनुमोिदत 9ताव का िववरण नीचे िदया गया है:

SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

(रा श Qपये म, (करोड़)) जगह 9थान यूिनट नंबर 11, 12, और 13 (26 सीट), Sाउंड Tोर, िबU डग - टॉवर ए, नालंदा शे टर ाइवेट लिमटेड, राजीव गांधी इWफोटेक पाक के पास, Xहजेवाड़ी, फेज I, पुणे 411 057। #े$ 418 वग मीटर िनJमत िकया जाने वाला उYपाद/दान क( जाने वाली सेवा . Sr. No. Services SAC/CPC Authorized Operations 1 Information Technology SAC-998314 CPC-842 Software Development, Application Development, Enhancement in Existing Application/Software, testing, Integration etc. 2 Information Technology Enabled Services in the nature of support services. SAC-998313 CPC-879 They provide Back supports like HR related services, Accounting, Software related support etc. 3 Research and Development Services. SAC-998313 CPC-851 They need R&D towards Intelligent Automation (IA), and Data Analytics services. वष-वार अनुमान, Kलांट एवं मशीनरी म, िनवेश/ पूंजीगत माल (Rs. In Cr.) 9वदेशी आया.तत कुल 0.66 0.12 0.78 सेवा 9वदेशी आया.तत कुल 7.29 0.76 8.05 रोज़गार कुल 26 (पुQष - 16, मिहला – 10)

थम Zलॉक अव.ध के लए अनुमान (Amount in Rs. Cr.)

1st 2nd 3rd 4th 5th Total FOB Value of Exports 1.90 2.50 3.25 3.60 4.00 15.25 FE outgo 0.17 0.13 0.16 0.22 0.20 0.88 NFE 1.73 2.37 3.09 3.38 3.80 14.37 SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

एज,डा मद सं4या 04: मेसस पीओ लाइXटग इं.डया ाइवेट लिमटेड तथा Kला89टक ओ8[नयम ऑटो ए सटीMरयस (इं.डया) ा. ल. आईटी अवसंरचना को साझा करने के संबंध म, अनुमोदन के लए आवेदन:

िवचार-िवमश के बाद, सिम.त ने आईटी अवसंरचना को साझा करने के संबंध म, (िन[नलखत Xबदु : 1,2,3 और 4 को छोड़कर) 9ताव को 2006 के एसईजेड िनयम के िनयम 27(5) के तहत 9वीकृ.त दी ।

  1. साझा क( जाने वाली आईटी अवसंरचना का िववरण नीचे िदया गया है:

Sr. No. Expenses Cost Sharing Ratio Created by Shared to 01 Internet Charges - Local 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 02 Internet Charges - Others 50:50% M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. M/s PO Lighting India Pvt. Ltd 03 FAS & WLD AMC Charges 55:45% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 04 Electricity charges 70:30% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd 05 IT Infrastructure (Cisco Switches, Cisco License Cost, Network Rack) 50:50% M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. M/s PO Lighting India Pvt. Ltd 06 IT Infrastructure (HPE server, Palo Alto Firewall, License cost, UPS) 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 07 IT Peripheral – Passive (Cables, Patch Panel, IOBOX, IO Connector, Patch cods) 50:45% M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. M/s PO Lighting India Pvt. Ltd 08 IT Peripheral – Passive (Cables, Patch Panel, IOBOX, IO Connector, Patch cods) 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 09 IT Peripheral – VC Device 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

10 IT Peripheral Dual Minotor Stand with dock station 100% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. यूिनट के बीच साझा िकया जाने वाला सामाWय कायालय #े$ Office reception – Area 55.70 Sq. Mtrs. M/s PO Lighting India Pvt. Ltd will have 25.00 Sq. Mtrs. M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. will have 30.70 Sq. Mtrs.

Minutes of the 44th Meeting of the Approval Committee held under the Chairmanship of Zonal Development Commissioner SEEPZ-SEZ, Mumbai for Sector Specific Special Economic Zone for IT/ITES of M/s. Nalanda Shelter Pvt Ltd -SEZ, PUNE held on 15.10.2024. 1 Name of the SEZ M/s Nalanda Shelter Pvt Ltd – SEZ, PUNE 2 Sector IT/ITES 3 Meeting No. 44th 4 Date 15.10.2024

Members present

Sr. No. Name and Designation (S/Shri.) Department 1 Smt. Mital Hiremath Joint Development Commissioner Pune Cluster SEZ, Pune 2 Shri. Sanjay Bangar Deputy Director of Industries, Pune Region Nominee of Govt. of Maharashtra 3 Smt. Archana Parab, Asst. Commissioner, IT Nominee of Income Tax, Pune 4 Smt. Pushpa Gangawane FTDO Nominee of DGFT, Pune 5 Shri Dhaval S Shirke, Superintendent Nominee of Customs, Pune

Special Invitee SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

Sr. No. Name and Designation Department 1 Shri Satbir Sharma Specified Officer SEEPZ-SEZ, Pune Cluster

Agenda Item No.01: Confirmation of the Minutes of the 43rd meeting held on 16.08.2024

After deliberation, the Committee confirmed the minutes of the 43rd meeting of Approval Committee held on 16.08.2024.

Agenda Item No. 02 : Action taken report for the Minutes of the meeting held on 16.08.2024

      After deliberation, the Committee has taken a note of the Action taken

report for the Minutes of the meeting held on 16.08.2024.

Agenda Item No. 3 : Application for approval of Setting up of New Unit submitted by M/s Latent Bridge Private Limited :

After deliberation, Committee approved the proposal of M/s. Latent Bridge Private Limited for setting up of a new unit in MIDC – SEZ in terms of Rule 17 & 18 of SEZ Rules, 2006. The details of the approved proposal as detailed below :

Location Unit No. 11, 12, & 13 (26 Seats), Ground Floor, Building – Tower A, Nalanda Shelter Private Limited, Near Rajiv Gandhi Infotech Park, Hinjewadi, Phase I, Pune 411 057. Area 418 Sq. Meters Product to be manufactured /Service to be rendered. Service Provider Plant & Machinery Indigenous Imported TOTAL 0.66 0.12 0.78 Services Indigenous Imported TOTAL 7.29 0.76 8.05 Employment Total 26 (Male - 16, Female – 10)

Approved Projections for 1st Block Period (Rs. In Crores)

1st 2nd 3rd 4th 5th Total FOB Value of Exports 1.90 2.50 3.25 3.60 4.00 15.25 FE SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

outgo 0.17 0.13 0.16 0.22 0.20 0.88 NFE 1.73 2.37 3.09 3.38 3.80 14.37

Agenda No. 4 : Application of M/s PO Lighting India Pvt. Ltd & M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. for approval of share of IT infrastructure:

After deliberation, the committee approved the proposal (except a 1 to 4 services )to share IT infrastructure facilities with their other SEZ unit, as per Rule 27(5) of the SEZ Rules, 2006

a. Details of infrastructure facilities to be shared are as detailed below:

Sr. No. Expenses Cost Sharing Ratio Created by Shared to 01 Internet Charges - Local 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 02 Internet Charges - Others 50:50% M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. M/s PO Lighting India Pvt. Ltd 03 FAS & WLD AMC Charges 55:45% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 04 Electricity charges 70:30% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd 05 IT Infrastructure (Cisco Switches, Cisco License Cost, Network Rack) 50:50% M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. M/s PO Lighting India Pvt. Ltd 06 IT Infrastructure (HPE server, Palo Alto Firewall, License cost, UPS) 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 07 IT Peripheral – Passive (Cables, Patch Panel, IOBOX, IO Connector, Patch cods) 50:45% M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. M/s PO Lighting India Pvt. Ltd 08 IT Peripheral – Passive (Cables, Patch Panel, IOBOX, IO Connector, Patch cods) 50:50% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. 09 IT Peripheral – VC 50:50% M/s PO Lighting M/s Plastic Omnium SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

Device India Pvt. Ltd Auto Exteriors (India) Pvt Ltd. 10 IT Peripheral Dual Minotor Stand with dock station 100% M/s PO Lighting India Pvt. Ltd M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. Common Office area to be shared between the parties Office reception – Area 55.70 Sq. Mtrs. M/s PO Lighting India Pvt. Ltd will have 25.00 Sq. Mtrs. M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. will have 30.70 Sq. Mtrs.

बैठक अ*य# को धWयवाद के साथ समा_ हुई। Meeting ended with a vote of thanks to the Chair.

(`ानेaर भा पाटील, आईएएस) (Dnyaneshwar B. Patil, IAS) अ*य# एवं िवकास आयु' Chairman-cum- Development Commissioner

SEEPZM-SSEZ0MINF(NSPL)/1/2024-O/o JDCP-SEEPZ SEZ I/72008/2024

ACTION TAKEN REPORT FOR THE APPROVAL COMMITTEE MEETING HELD ON 15.10.2024 IN RESPECT OF NALANDA SHELTER PVT. LTD., - SEZ, Hinjawadi, Phase I, Pune. APPROVED ON 16.10.2024

Name of the unit

Subject Action Taken M/s Latent Bridge Private Limited : Application for approval of Setting up of New Unit LOA issued on 18.10.2024 M/s PO Lighting India Pvt. Ltd & M/s Plastic Omnium Auto Exteriors (India) Pvt Ltd. Application for approval of
sharing of IT infrastructure.

Approval letter issued to the unit on 25.10.2024

OFFICE OF THE DEVELOPMENT COMMISSIONER, SEEPZ SPECIAL ECONOMIC ZONE, GOVT. OF INDIA, ANDHERI (EAST), MUMBAI


AGENDA NOTE FOR CONSIDERATION OF APPROVAL COMMITTEE


a. Proposal : Proposal dated 12.11.2024 received on 22.11.2024 submitted by M/s. Hella India Automotive Pvt. Ltd., an IT/ITES unit located at Nalanda Shelters Pvt Ltd - SEZ, for approval of Broad Banding of Additional Services with revision in projection. b. Specific Issue on which decision of AC is required: -
Approval of Committee for Broad Banding of Additional Services with revision in projection in terms of 19(2) of SEZ Rules, 2006 c. Relevant provisions of SEZ Act, 2005 & Rules, 2006/Instruction/
Notification :- As per 1st proviso to Rule No. 19(2) of SEZ Rules, 2006 [“Provided that the Approval Committee may also approve proposals for broad banding, diversification, enhancement of capacity of production, change in the items of manufacturing or service capacity, if it meets the requirements of rule 18”]. d. Other Information: - Broad banding of additional of service in the existing LOA as authorized operations as detailed below: Existing Approved Operations Proposed additional of Operations (Services)

  1. Information Technology in the Nature of Software Development, Application Development, Enhancement in Existing Application/Software, Integration, Testing and Maintenance.

Information Technology Enabled Services such as Engineering and Design services. 3. Other Business services 4. Support Centers.

  1. Information Technology in the Nature of Software Development, Application Development, Enhancement in Existing Application/Software, Integration, Testing and Maintenance.

Information Technology Enabled Services such as Engineering and Design services. 3. Other Business services 4. Support Centres 5. Prototype Development & Testing (SAC – 99833 & CPC – 8672) (Test Bench – HSN – 90312000 Wire Harness – HSN 85443000) Approved & Proposed Projections of Investment and Employment: (Rs. In Crores) Sr. No Item Existing Projection Total Revised Projection 1. Capital Goods

i. Indigenous 115.40 115.72 ii. Imported 47.66 47.88

Total 163.06 163.60 2. Raw Material

i. Indigenous 0.00 0.00 ii. Imported 0.00 0.00

Total 0.00 0.00 3. Input of Services

i. Indigenous Services 149.28 149.72 ii. Imported Services 18.48 18.59

Total 167.76 168.31 4. Employment 957(Men-603, Women- 354) 966 (Men – 609, Women – 357) Approved Projection: (Rs. In Crores)

2024-25 2025-26 2026-27 2027-28 2028-29 Total FOB value of Exports

86.73

169.77

194.68

220.58

252.19

923.94 FE Outgo 43.52 3.92 5.51 6.19 7.00 66.14 NFE Earnings 43.21 165.85 189.16 214.38 245.19 857.80 Proposed Revision of Projection : (Rs. In Crores)

2024-25 2025-26 2026-27 2027-28 2028-29 Total FOB value of Exports

88.07

171.24

196.29

222.35

254.15

932.11 FE Outgo 43.57 3.97 5.58 6.26 7.08 66.47 NFE Earnings 44.50 167.27 190.71 216.09 247.07 865.64

Other Information: - M/s. Hella India Automotive Pvt. Ltd., granted LOA NO. SEEPZ-SEZ/NSPL-SEZ/HIAPL/16/2023- 24/649 dated 24.08.2023 (Original LOA), located at Ground Floor, 4th and 5th floor, Tower A, Nalanda Shelters Pvt Ltd – SEZ, RGIP, Hinjewadi, Phase – I, Pune 411057. DCP: 03.06.2024 LOA Validity up to: 02.06.2029 Reason for Broad-banding with Revision in Projection: The unit has submitted that, they are engaged into Engineering & Design Services and Development of new products therefore their customers want them to export this prototype as well. As a result, they will source materials, integrate them, and test them on their premises and after that they will export the product as a prototype. In this regard, they would like to propose for broad banding of they approved authorized operations.

The unit has enclosed following documents along with their application: Copy of Form F3 filed through SEZ Online system. Copy of LOA List of Imported & Indigenous Capital goods. List of Imported and Indigenous Services. Copy of Form F. e. ADC’s Recommendation: Approval Committee may like to consider the proposal of the unit for Broad Banding of Additional Services with revision in projection, in terms of Rule 19(2) of SEZ Rules, 2006.


OFFICE OF THE DEVELOPMENT COMMISSIONER, SEEPZ SPECIAL ECONOMIC ZONE, GOVT. OF INDIA, ANDHERI (EAST), MUMBAI


AGENDA NOTE FOR CONSIDERATION OF APPROVAL COMMITTEE

a. Proposal : Monitoring of the performance of M/s. Infovision Labs India Private Ltd. an IT/ITES unit located in Nalanda Shelter Pvt. Ltd., - SEZ, for 5 years i.e., FY 2019-20 to FY 2024-25 (upto August, 2024) of 1st Block period. b. Specific Issue on which decision of AC is required: - Monitoring of the performance of the unit for 5 years i.e., FY 2019-20 to FY 2024-25 (upto August, 2024) of 1st Block period, in terms of Rule 54 of SEZ Rules, 2006. c. Relevant provisions of SEZ Act, 2005 & Rules, 2006/Instruction/ Notification :- As per Rule 54 of SEZ Rules, 2006 “Performance of the Unit shall be monitored by the Approval Committee as per the guidelines given in Annexure appended to these rules”. d. Other Information: - Approved Projections: (1st block Period) (Rs. In Crores) 2019-20 2020-21 2021-22 2022-23 2023-24 TOTAL FOB Value of Exports 1.51 28.43 42.49 63.81 95.71 231.95 FE Outgo 0.30 0.30 3.70 0.75 0.97 6.02 NFE 1.21 28.13 38.79 63.05 94.74 225.93 Performance as compared to projections: FY 2020-21 to FY 2024-25 (Rs. In Crores) Year Export F.E. OUTGO Projected Actual Raw Material (Goods/Services) C.G. import Other outflow Projected Actual Projected Actual Actual

2019-20 1.51 0.92 0.00 0.00 6.02 0 0 2020-21 28.43 1.83 2021-22 42.49 10.41 0 0 2022-23 63.81 8.41 0 0 2023-24 95.71 7.89 0 0 2024-25 (upto Aug., 2024 0 1.00 0 0 Total 231.95 30.46 0.00 0.00 6.02 0 0 Reasons for less export as compared to Projection: The Unit vide their mail dated 14.11.2024 clarified that they were expecting more business as their Unit was operational in the month of March, 2020, that time pandemic hampered their business globally and hence no contract got materialized, therefore there were no exports in this unit. The Management decided to exit from SEZ scheme. Cumulative NFE achieved: FY 2019-20 to FY 2024-25 (upto August, 2024) (Rs. In Crores) Year Cumulative NFE Achieved Cumulative % NFE Achieved 2019-20 0.0092 100 % 2020-21 1.84 100% 2021-22 12.26 100 % 2022-23 20.67 100 % 2023-24 28.60 100 % 2024-25 (upto August, 2024) 29.60 100 % Employment Achievement : FY 2019-20 to 2024-25 (upto August, 2024) Approved Existing (Upto August, 2024) Proposed

Men 506 17 The Unit vide letter dated 21.08.2024 is exiting from SEZ Scheme, proposed employment is not given. Women 127 06 Total 633 23 Other Information: LOA No. & Date LOA No. SEEPZ-SEZ/NSPL- SEZ/ILIPL/01/2019-20 dt. 09.03.2020 Location of Unit Ist Office Floor, Unit No. 1& 2, Tower A & Incubation Space at Ground floor, Nalanda Shelter Pvt. Ltd – SEZ, Blue Ridge, Rajiv Gandhi Gandhi Infotech Park, Hinjewadi, Phase I, Pune 411 057 Validity of LOA 26.03.2025 Item(s) of manufacture/ Services IT/ITES Date of commencement of production 27.03.2020 Execution of BLUT 16.36 Crores Outstanding Rent dues NA Labour Dues NA Validity of Lease Agreement NA Pending CRA Objection, if any NA Pending Show Cause Notice/ Eviction Order/Recovery Notice/ Recovery Order issued, if any NA a. No. of employees as on 31.08.2024 Man – 17 women – 06 Total : 23 Area allotted (in sq.ft.) 56,608 Sq. Ft. Area available for each employee per sq.ft. basis (area / no. of employees) 89.43 Sq. Ft. Investment till date Building NA Plant & Machinery 14.60 Crores Quantity and value of goods exported under Rule 34 (unutilized goods) NA Value Addition during the monitoring period NA Whether all the APRs being considered now has been filed well within the time limit, or otherwise. If no, details of the Year along with no of days delayed to be given. Yes

The Specified Officer vide letter dated 22.10.2024 has submitted report as detailed below: a. Details of year-wise export as per the prescribed format: From the year 2020-2021 to 2024-2025 (In Crores) Year/ Period Figures reported in APR (FOB Value) Figures as per Softex / Customs Records Difference, if any Reason for Difference / Remarks 2019-20 0.01 0.01 0.00 NA 2020-2021 1.83 1.83 0.00 NA 2021-2022 10.41 10.43 (-0.02) Dierence is due to Exchange Rate Variation 2022-2023 8.41 8.86 (-0.45) During the Year, raised the Credit Note of Rs. (-0.41) Crore) Balance dierence if (-0.04) Crore is due to Exchange Rate Variation. 2023-2024 7.89 8.66 (-0.77) During the Year, raised the Credit Note of Rs. (-0.75) Crore) Balance dierence if (-0.02) Crore is due to Exchange Rate Variation. 2024-2025 1.00 1.00 0.00 NA b. Import i. (Capital Goods including procurement done on IUT (from SEZ, EOU, STPI, EHTP) basis: From the year 2019-2020 to 2023-2024 (In Crores) Year/ Period Figures as per Revised APR Figures as per SEZ Online / Customs Records Difference, if any Reason for Difference / Remarks 2020-21 0.00 0.00 0.00 NA 2021-22 0.00 0.00 0.00 2022-23 0.00 0.00 0.00 2023-24 0.00 0.00 0.00 2024-25 0.00 0.00 0.00 ii. Raw Material From the year 2019-20 to 2023-24

Year/ Period Figures as per APR Figures as per SEZ Online / Customs Records Difference, if any Reason for Difference / Remarks 2019-2020 0.00 0.00 Nil NA 2020-2021 0.00 0.00 Nil NA 2021-2022 0.00 0.00 Nil NA 2022-2023 0.00 0.00 Nil NA 2023-2024 0.00 0.00 Nil NA (c ) BLUT 1 Value of BLUT Executed (Duty foregone) (including for CG / Raw Material / Services) Value of Additional BLUT executed Year: Date of acceptance BLUT amount: TOTAL value of BLUT Executed F. No. SEEPZ-SEZ/NSPL- SEZ//ILIPL/01/2019-20/ dt. 21.05.2020. BLUT Amount 16.36 Cr. TOTAL BLUT 16.36 Cr. 2 Total Duty Foregone on goods & services procured (Category-wise BLUT value utilized separately for imported and indigenous goods and services) This should be based on BLUT worksheet which provides for estimated value and duty foregone separately for each category of procurement. Value In Crore FY Goods (Imp. & Indi.) Services (Imp. & Indi.) 2020-21 0.09 0.00 2021-22 0.04 0.14 2022-23 0.00 0.00 2023-24 0.00 0.00 2024-25 0.00 0.00 Total 0.13 0.14 3 Has the Unit procured goods and or Services without having sufficient balance in their BLUT. If yes, Month & Year when the BLUT was exhausted. Details of the consignments and Total value of Goods procured without having sufficient or NIL balance in BLUT. No

(d) Employment made as on date (as on end of block period / year up to which monitoring is being done) Projected employment as per Form F – Man : 506, Women : 127, Total : 633 As on 31st August, 2024: Man: 17 Woman: 06 Total: 23 (e) Details of pending Foreign Remittance beyond Permissible period, if any (as on 31.03.2022) To cross-check the same and verify whether necessary permission from AD Bank / RBI has been obtained. No Foreign Remittance is pending beyond the permissible period is pending for realization, except for two Invoices. (f) Whether all softex has been led for the said period. If no, details thereof. SO to also check whether unit has obtained Softex condonation from DC office / RBI and if approved, whether they have filed such pending Softex. Yes. All Softex Forms has beenled for the monitoring period. (g) Whether all Softex has been certied, if so till which month has the same been certied. If not, provide details of the Softex and reasons for pendency. Yes, All the Softex Forms till August, 2024 has been certified. (h) Whether unit has led any request for Cancellation of Softex No. (i) Whether any Services provided in DTA / SEZ/EOU/STPI etc. against payment in INR in r/o IT/ITES Unit during the period. If yes, details thereof (year wise details to be provided) No. They have not provided any services in DTA / SEZ / EOU / STPI etc. against payment in INR during the reporting period. (j) SO to verify and certify whether the unit has updated the BLUT ledger Module in SEZ Online. NA (k) Has the unit cleared any Capital Goods procured duty free in DTA against payment of Duty, or otherwise? Full details to be provided along with value of assets and duty discharged. No

(l) Is the unit sharing any of their infrastructure with other units or are utilizing infrastructure of another unit in the same or other SEZ? If so, details thereof, including the details of the unit with whom the sharing is being made, and the payment terms If approval for sharing of common infrastructure has been obtained from UAC / DC office, the date of UAC / Approval letter to be indicated No (m) Whether all DSPF for services procured during the said monitoring period under consideration has been led by the unit and whether the same has been processed for approval by the SO Office. No. (n) Whether unit has led all DTA procurement w.r.t. the goods procured by them during the monitoring period for the relevant period. If no, details thereof Yes. They have led all the DTA Procurement w.r.t. the goods procured by them during the monitoring period for the relevant period. (o) Details of the request IDs pending for OOC in respect of DTA procurement on the date of submission of monitoring report No. Request ID is pending for OOC. (p) Has the unit set up any cafeteria / canteen / food court in unit premises? If yes, whether permission from UAC / DC office has been issued, or otherwise office has been issued, or otherwise Whether unit has availed any `duty paid goods / services for setting up such facility? If yes, whether unit has discharged such duty / tax benet availed? details to be given including amount of duty / tax recovered or yet to be recovered They have set up only dry pantry with no cooking facility. Also, all the capital goods lying at the dry pantry area was procured by them without availing any duty benefit. (q) Whether any violation of any of the provisions of law has been noticed / observed by the Specied Officer during the period under monitoring No e. ADC’s Recommendation: The Unit has achieved export revenue of Rs. 30.46Crores as against projected export of Rs. 231.95 Crores i.e. 13.13% for FY 2019-20 to 2024-25 (Upto August, 2024) in 05 years of 1st Block period (i.e. 2019-20 to 2024-25 (Upto August, 2024) The Unit was called for the reason why the Export was less than the approved projection. The Unit vide their mail dated 14.11.2024 clarified that they were expecting more business as their Unit was

operational in the month of March, 2020, that time, pandemic hampered their business globally and hence no contract got materialized therefore there were no exports in this unit, hence the Management decided to exit from SEZ scheme. The unit has achieved positive NFE of Rs. 29.60Crore in the fifth year of 2024-25 (upto August, 2024) on cumulative basis. i.e. 100 % As per SO’s report, the unit has 23 employees (Man – 17, Women – 06 = 23) as on 31.08.2024 i.e. FY 2024-25, as compared to the projected employment i.e. Total employment – 633 (Men – 506, Women – 127) Approval Committee may like toMonitor the performance of the unit for 5 years i.e. FY 2019-20 to 2024-25 (Upto August, 2024) of 1st Block period, in terms of Rule 54 of SEZ Rules, 2006.