07th October, 2025 Approval of Resolution Plan - Eagle Electronic (India) Private Limited [IA No. 63 of 2025 in CP(IB) No. 643 of 2023] (203.22 KB)
IN THE NATIONAL COMPANY LAW TRIBUNAL, MUMBAI BENCH- I
IA No. 63 of 2025 IN CP(IB) No. 643 of 2023 Under Section 30(6) read with Section 31(1) of the Insolvency and Bankruptcy Code, 2016
In the Application of
Kanak Jani
…Resolution Professional/Applicant
In the matter of
Profectus Capital Private Limited
…Financial Creditor
Versus
Eagle Electronic (India) Private Limited
…Corporate Debtor
Order Delivered On : 10.09.2025
Coram:
Hon'ble Member (Judicial) :
Sh. Sushil Mahadeorao Kochey
Hon'ble Member (Technical) :
Sh. Prabhat Kumar
Appearances: For the Applicant : Adv. Akshay Petkar, i/b Adv. Abhishek Salain, a/w Adv. Kinnari Raut
IN THE NATIONAL COMPANY LAW TRIBUNAL MUMBAI BENCH- I IA No. 63 of 2025 In CP(IB) No. 643 of 2023 Page 2 of 21
ORDER
Brief Background
-
The present Application is filed Ms. Kanak Jani, Resolution Professional (“Applicant/Resolution Professional”) of Eagle Electronic (India) Private Limited (“Corporate Debtor”) under Section 30(6) read with Section 31(1) of the Insolvency and Bankruptcy Code, 2016 (“Code”) and Regulation 39(4) of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 (“CIRP Regulations”) for seeking approval of the Revised Resolution Plan 08.10.2024 (as revised on 17.01.2025), submitted by Subhlaxmi Investment Advisory Private Limited (“Successful Resolution Applicant/SRA”) and for passing order/appropriate direction that this Tribunal may deem fit in the present matter. The Resolution Plan has been approved by 82.19% of the voting share of the members of the Committee of Creditors (“CoC”) at the 12th CoC meeting dated 05.05.2025.
-
The Corporate Debtor bearing CIN:U51505MH2011PTC218146 was incorporated on 01.06.2011 having its registered address at H No. 65, CTS No. 142-A-B Behind Chitramandir Talkies, Nashik, Maharashtra, India, 422001. Its authorized share capital is Rs. 4,00,00,000/- and its paid-up capital is Rs. 2,70,40,080/-.
-
The CIRP of the Corporate Debtor was initiated vide this Tribunal’s order dated 06.03.2024. This Tribunal appointed Mr. Kanak Jani as the Interim Resolution Professional (“IRP”) and he was subsequently confirmed as the Resolution Professional (“RP”) at the 1st CoC meeting held on 05.04.2024.
-
As per Regulation 6 of the CIRP Regulations, the Applicant made a public announcement vide Form-A on 08.03.2024 notifying the
MUMBAI BENCH- I IA No. 63 of 2025 Page 3 of 21
commencement of CIRP of the Corporate Debtor and inviting the claims of Creditors. Thereafter, the CoC was constituted.
-
At the 2nd CoC meeting, held on 03.05.2024, the CoC approved the appointment of Mr. Annam Srinivasa and Mr. Devarasetti Brahmaiah (“Registered Valuers”) for valuation the Corporate Debtor. The average fair value of the Corporate Debtor was determined as
Rs. 25,07,000/- (Rupees Twenty Five Lakhs and Seven Thousand Only). The average liquidation value of the Corporate Debtor was determined as Rs. 20,05,500/- (Rupees Twenty Lakhs, Five Thousand, and Five Hundred Only). -
The Resolution Professional published Form-G dated 05.05.2024 along with detailed Invitation of Expression of Interest (“EOI”).
-
At the 4th CoC meeting, held on 12.06.2024, the Evaluation Matrix and the Request for Resolution Plan (“RFRP”) were placed before the CoC and were unanimously approved pursuant to voting between 14.06.2024 to 17.06.2024.
-
The Provisional List of Prospective Resolution Applicants (“PRA”) was published on 30.05.2024 and the Final List of PRA(s) was published on 14.06.2024. The PRA(s) were provided the Information Memorandum on 19.06.2024 and the last date for the submission of Resolution Plans was 19.07.2024.
-
At the 6th CoC meeting, held on 24.07.2024, the CoC approved the issuance of a fresh Form-G as no Resolution Plan had been received in response to the first round of EOI. Subsequently, the RP published a fresh Form-G on 25.07.2024, as per which the last date to submit EOI was 09.08.2024 and the last date for submission of Resolution Plans was 08.10.2024. The RP also filed an application, IA No. 5434/2024, seeking an extension of 90 days of the CIRP period, which was allowed
MUMBAI BENCH- I IA No. 63 of 2025 Page 4 of 21
by this Tribunal vide order dated 28.11.2024. In response to the fresh Form-G, the RP received 3 EOIs. On 19.08.2024, the RP published the Provisional List of PRA(s) and on the 03.09.2024, the Final List of PRA(s) was published.
-
At the 8th CoC meeting held on 11.10.2024, the CoC approved the extension for the submission of Resolution Plans from 08.10.2024 to 29.10.2024, pursuant to the request of PRA(s).
-
At the 9th CoC meeting, held on 06.11.2024, the 2 Resolution Plans received were opened in the presence of the Resolution Applicants and they were directed to take corrective correction to comply with the minimum upfront payment of EMD as laid down in the RFRP before further consideration of the Resolution Plans.
-
At the 10th CoC meeting, held on 26.11.2024, the Resolution Plans were analysed and were found to be non-compliant with certain provisions of the Code. Since further time was required for consideration of the Resolution Plans and the response of the Resolution Applicants regarding the non-compliance, pursuant to the CoC’s approval, the RP filed an application, IA No. 292/2025, seeking an extension of 60 days of the CIRP period beyond 270 days, which was allowed by this Tribunal vide order dated 21.02.2025. At the 11th CoC meeting, held on 17.12.2024, the responses received from the Resolution Applicants were discussed and negotiations ensued.
-
At the 12th CoC meeting, held on 20.01.2025, the 2 compliant Resolution Plans, one submitted by Subhlaxmi Investment Advisory Private and the other by Raj Enterprises along with Mrs. Meenu Yogendra Chaudhary were placed before the CoC for their approval.
-
The 2 Resolution Plans were put to vote through e-voting between 22.01.2025 which concluded on 05.05.2025 and the Resolution Plan
MUMBAI BENCH- I IA No. 63 of 2025 Page 5 of 21
dated 08.10.2024 (as revised on 17.01.2025) submitted by Subhlaxmi Investment Advisory Private Limited was approved by the CoC with 82.19% votes through the e-voting conducted between 31.01.2024 and 03.02.2024. Consequently, Subhlaxmi Investment Advisory Private Limited was declared the Successful Resolution Applicant (“SRA”) and a Letter of Intent (“LOI”) was issued to them on 06.05.2025, which they accepted unconditionally.
-
As per Regulation 36B(4A) of the CIRP Regulations, read with the RFRP, the SRA has deposited an amount of Rs. 2,87,500/- (5% of the NPV of the Resolution Plan), credited to the Corporate Debtor’s CIRP Bank Account on 12.05.2025 towards performance security.
-
Since the voting on the Resolution Plans ended on 05.05.2025, which is beyond the CIRP Period, the CoC approved the filing of an Application seeking further extension. Consequently, an Application, IA No.3486/2025 was filed, seeking extension of further 30 days beyond 330 days, i.e. till 28.02.2025, which came to be allowed by this Tribunal vide order dated 11-08-2025. A further extension of 85 days, from 01.03.2025 to 24.05.2025 was sought vide IA No. 2786/2025, which was allowed by this Tribunal on 11.08.2025.
Salient Features of the Resolution Plan 17. The key features and summary of the Resolution Plan submitted by the Resolution Applicant and as approved by the CoC are as under:
17.1. The SRA is a private limited company with expertise in providing financial services, advisory and consultancy services on shares, stocks, etc. and to purchase, sell, acquire, hold, dispose off shares, stocks, securities, bonds, etc. Mr. Anand Prakash and Mr. Hardev are the 2 shareholders holding 50% shares each of the SRA.
MUMBAI BENCH- I IA No. 63 of 2025 Page 6 of 21
17.2. Treatment of Stakeholders:
Stakeholder Type
Amount Admitted
Proposed pay- out
Percentage of realizable amount CIRP Cost 31,00,000 31,00,000 100% Secured Financial Creditors 28,56,23,985.60 16,31,964
Unsecured Financial Creditors 2,42,85,236.60 1,00,000
Operational Creditors
(i) Government 5 ,46, 14,400 95,768
(ii) Workmen & Employees 522,268 522,268 100% (iii) Other Operational Creditors 65,49,094 50,000 0.76% (iv) Contingencies
2,50,000
Shareholders
NA
NA
NA
Total
399,463,763.85
57,50,000/-
1.44%
This Tribunal, on 14.08.2025, had sought clarification from the Applicant as to how the Financial proposals laid out in the plan meets the provision under Section 30(2)(a) in relation to payment of CIRP cost in priority to the payment of other debts of the Corporate Debtor as the CIRP cost is stated to be funded over a period of 6 months, whereas, the plan contemplates initial infusion of 7,50,000/-, which is for the purpose of settling the claim of other creditor including PF department. Pursuant to order dated 14.08.2025, the Applicant submitted an Additional Affidavit dated 20.08.2025, wherein the SRA has affirmed that – “3. That we further undertake that the CIRP costs of Rs 31,00,000/- and any further amount as may be communicated under
MUMBAI BENCH- I IA No. 63 of 2025 Page 7 of 21
the head of CIRP Cost, will be paid in full, in priority upfront and immediately without any delay, in compliance with the applicable rules, regulations, and directions of the Hon'ble National Company Law Tribunal (NCLT) and/or upon approval of the Plan by the Hon'ble NCTL.”
17.3. Source of Funds: The SRA has submitted that its certified net worth is Rs. 22.39 Crores with leveraging capabilities to the extent of Rs. 40 Crores. The financial resources of the Resolution Applicant and its proprietor are more than sufficient to provide funds required to meet the payments proposed for the implementing the Resolution Plan. The SRA has liquidity of owned funds. The source of funds for funding the, Resolution Plan shall be owned funds and the loans given are in liquidation form, i.e., recoverable on demand along with investments by the SRA.
17.4. Term of the Plan and its Implementation Schedule: The term of the Plan shall be 6 months from the date on which NCLT approves the Plan and is extendable, if required as the case may be, if any, if delay is not on the part of the SRA.
17.5. Supervision of the Plan, Mechanism regarding management and control of the affairs of the Corporate Debtor: Immediately upon the Tribunal approval date, the Monitoring Committee shall be constituted and the Insolvency Professional shall convene meeting of the Monitoring Committee on receipt of the order of this Tribunal. The Monitoring Committee shall comprise the Insolvency Professional as Chairman, One Representative on behalf of the Resolution Applicant and one representative to be nominated by all the financial creditors. The Monitoring Committee shall be dissolved immediately on the implementation of the Resolution Plan. On approval of the Resolution Plan by this Tribunal, the management of the Corporate Debtor will get transferred from the Applicant to the Monitoring Committee. The payments of the amounts committed
MUMBAI BENCH- I IA No. 63 of 2025 Page 8 of 21
under the Plan will be made in the bank account of Corporate Debtor which will remain under the control of the Monitoring Committee. The said amount will be distributed by Monitoring Committee to various stakeholders under the Plan.
17.6. Approvals for implementation of the Resolution Plan : As per the Resolution Plan, the Resolution Applicant shall obtain all necessary approvals within a period of one year from the date of the approval of the Resolution Plan the time prescribed under Applicable Law.
17.7. Legal Costs : All definite legal expenses incurred in the process of recovering dues shall be borne by the SRA. In the event, the dues are successfully recovered within three years, 30% of the recovered amount shall be distributed to both secured and unsecured financial creditors, pari-passu.
17.8. Avoidance Transactions: The application for avoidance of the PUFE transactions has been filed by Resolution Professional. Accordingly, the SRA, provides that such application will be pursued by the CoC after approval of the Plan and all the resultant financial or non-financial benefits of such application(s) on order of this Tribunal shall be available for the benefits of the stakeholders in proportion to their claims admitted. All the cost of pursuing such application shall be paid by the CoC.
Statutory Compliance: 18. In compliance of Section 30(2) of IBC, 2016, the Resolution Professional has examined the Resolution plan of the Successful Resolution Applicant and confirms that this Resolution Plan: a) Provides for payment of Insolvency Resolution Process cost in a manner specified by the Board in the priority to the payment of other debts of the corporate debtor;
MUMBAI BENCH- I IA No. 63 of 2025 Page 9 of 21
b) Provides for payment of debts of Operational Creditor in such
manner as may be specified by the board which shall not be less
than
(i) the amount to be paid to such creditors in the event of
liquidation of the Corporate Debtor under Section 53; or
(ii) the amount that would have been paid to such creditors, if
the amount to be distributed under the Resolution Plan
had been distributed in accordance with sub-section (1) of
Section 53 in the event of liquidation of the corporate
debtor.
c) Provides for management of the affairs of the Corporate Debtor
after approval of Resolution Plan;
d) The implementation and supervision of Resolution Plan;
e) Does not prima facie contravene any of the provisions of the law
for time being in force,
f) Confirms to such other requirements as may be specified by the
Board.
g) As per the Affidavit, the Resolution Applicant is not covered
under Section 29A.
- In compliance of Regulation 38 of CIRP Regulations, the Resolution Professional confirms that the Resolution plan provides that: a) The amount due to the Operational Creditors under Resolution Plan shall be given priority in payment over Financial Creditors. b) It has dealt with the interest of all Stakeholders including Financial Creditors and Operational Creditors of the Corporate Debtor. c) A statement that neither the Resolution Applicants nor any related parties have failed to implement nor have contributed to the failure of implementation of any other Resolution Plan approved by the Adjudicating Authority in the past. d) The terms of the plan and its implementation schedule.
MUMBAI BENCH- I IA No. 63 of 2025 Page 10 of 21
e) The management and control of the business of the Corporate
Debtor during its term.
f) Adequate means of Supervising its implementation.
g) The Resolution Plan Demonstrates that it addresses
i. The cause of the Default
ii. It is feasible and viable
iii. Provision for effective implementation
iv. Provisions for approvals required and the time lines for the
same.
v. Capability to Implement the Resolution Plan
- The Resolution Professional has submitted Form-H under Regulation 39(4) of the CIRP Regulations to certify that the Resolution Plan as approved by the CoC meets all the requirements of the Code and its Regulations, the relevant parts of which are reproduced below:
FORM H (Revised as on 20.08.2025)
COMPLIANCE CERTIFICATE
Under Regulation 39(4) of the Insolvency and Bankruptcy Board of India
(Insolvency Resolution Process for Corporate Persons) Regulations, 2016
I, Kanak Jani, registered as Insolvency Professional (IP) having registration number
IBBI/IPA-001/IP-PO 1757/2019 -2020/12685, an Insolvency Professional enrolled
with the Indian Institute of Insolvency Professionals of ICAI and registered with the
Board, the Resolution Professional for the Corporate Insolvency Resolution Process
(CIRP) of Eagle Electronics India Private Limited.
1A. The details of the CIRP are as under:
Sl. .No.
Particulars
Description
1.
Name of the CD
Eagle Electronics India Private Limited (In
CIRP)
MUMBAI BENCH- I IA No. 63 of 2025 Page 11 of 21
Date of Initiation of CIRP
06-03-2024
3.
Date of Appointment of IRP
06-03-2024
4.
Date of Publication of Public
Announcement
08-03-2024
5.
Date of Constitution of CoC
29-03-2024
6.
Date of First Meeting of CoC
05-04-2024
7.
Date of Appointment of RP
15-04-2024
8.
Date of Appointment of Registered
Valuers
22-04-2024
9.
Date of Issue of Invitation for EoI
05-05-2024 (Original)
25-07-2024 (Extended)
10.
Date of Final List of Eligible Prospective
Resolution Applicants
14-06-2024 (Original)
03-09-2024 (Extended)
11.
Date of Invitation of Resolution Plan
19-06-2024 (Original)
08-09-2024 (Extended)
12.
Last Date of Submission of Resolution
Plan
19-07-2024 (Original)
08-10-2024 (Extended)
13.
Date of submission of Resolution Plan to
the RP
Original Resolution Plan on 08-10-2024
and Revised Resolution Plan on 17-01-2025
14.
Date of placing the Resolution Plan
before the CoC
20-01-2025
15.
Date of Approval of Resolution Plan by
CoC
Approved in 12th CoC meeting held on 20-01-
2025 and e-voting completed on 05-05-2025
MUMBAI BENCH- I IA No. 63 of 2025 Page 12 of 21
Date of Filing of Resolution Plan with
Adjudicating Authority
21.05.2025
17.
Date of Expiry of 180 days of CIRP
02.09.2024
18.
Date of each order extending/excluding
the period of CIRP on request filed by
RP
The RP filed the following Applications
under Section 12(2) of IBC, 2016 seeking
extension from time to time:
i.
Extension of 90 days from 03.09.2025
till 01.12.2025, i.e., for 270 days- IA
No. 5434/MB/2024 which was allowed
on 28-11-2024.
ii.
Extension 60 days from 02.12.2025 till
01.02.2025, i.e., 330 days-
IA(I.B.C)/292/MB/2025 which was
allowed on 21-01-2025.
iii.
Extension beyond 330 days, for a further
period of 30 days, i.e., till 28.02.2025 -
I.A. 3486 of 2025 which was allowed on
11-08-2025.
iv.
Extension of 85 days from 01.03.2025 to
was allowed on 11-08-2025 in I.A. 2786
of 2025 was allowed on 11-08-2025.
19.
Date of Expiry of Extended Period of
CIRP
24.05.2025
20.
Fair Value (Plant and Machinery)
Rs. 25,07,000.00/-
21.
Liquidation Value (Plant and
Machinery)
Rs. 20,05,500.00/-
22.
Number of Meetings of CoC held
13 (Thirteen) plus one resolution passed vide
confirmation on email.
MUMBAI BENCH- I IA No. 63 of 2025 Page 13 of 21
- I hereby certify that - (i) The said Resolution Plan complies with all the provisions of the Insolvency and Bankruptcy Code 2016 (IBC/Code), the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 (CIRP Regulations) and does not contravene any of the provisions of the law for the time being in force. (ii) the Resolution Applicant (Subhlaxmi Investment Advisory Private Limited) has submitted an affidavit pursuant to section 30(1) of the Code confirming its eligibility under section 29A of the Code to submit resolution plan. The contents of the said affidavit are in order. (iii) the said Resolution Plan has been approved by the CoC in accordance with the provisions of the Code and the CIRP Regulations made thereunder. The Resolution Plan has been approved by 82.19 % of voting share of financial creditors after considering its feasibility and viability and other requirements specified by the CIRP Regulations. (iv) The voting was held in the meeting of the CoC on 20.01.2025 where all the members of the CoC were present. or I sought vote of members of the CoC by electronic voting system which was kept open at least for 24 hours as per regulation 26.
7A. Realisable Amount: SI. No. Particulars Description
- Total Realisable amount under the plan Rs. 57,50,000/-
- Fair Value (Securities or Financial Assets) Rs. 25,07,000/-
- Liquidation Value (Securities or Financial Assets) Rs. 20,05,500/-
- Percentage (%) of realisable amount to Fair Value 229.36%
- Percentage (%) of realisable amount to Liquidation Value 286.71 %
- Percentage (%) of realisable amount to Principal amount 1.65%
MUMBAI BENCH- I IA No. 63 of 2025 Page 14 of 21
- Percentage (%) of realisable amount to Total admitted claims 1.44%
- Percentage (%) of realisable amount to Other than
admitted
Corporate Guarantee claims NA
7B. Details of Realisable amount: (Amount in Rupees) Stakeholder Type Amounts Payment Schedule Amount Claimed Amount Admitted Realisable amount under the plan Amount Realizable Plan to amount claimed (%) Secured Financial Creditors Creditors not having a right to vote under sub- section (2) of section 21
- Dissenting
-Assenting
NA
NA
295,006,597.60
NA
Abstained 55,195,480.04
230,437,505.56 285,632,985.60
NA
NA
16,31,964/-
NA
NA
0.571 %
6 months
MUMBAI BENCH- I IA No. 63 of 2025 Page 15 of 21
Unsecured Financial Creditors (a) Creditors not having a right to vote under sub- section (2) of section 21
NA
NA
NA
NA 6 months -Dissenting
-Assenting NA
24,285,236.60 NA
24,285,236.60 NA
1,00,000/- NA
0.41% Operational Creditors (i) Government
83,064,966.00
82,428,411.65
50,000/-
0.061%
6 months
(ii) Workman
-PF Dues
-Other Dues
NA
NA
NA
NA
NA
(iii) Employees
-PF Dues
-Other Dues
(Gratuity)
45,768.00 522,268.00
45,768.00 522,268.00
45,768.00 522,268/-
100% 100%
30 days (iv) Other Operational Creditor
7,989,895.00
6,549,094.00
50,000/-
0.76%
6 months Other debts and dues NA NA 2,50,000/- Contingencies NA NA Shareholders NA NA NA NA NA Total 410,868,963.20 399,463,763.85 57,50,000/- 1.44% As above
- On perusal of the Resolution Plan, we find that the Resolution Plan provides for the following:
MUMBAI BENCH- I IA No. 63 of 2025 Page 16 of 21
a) Payment of CIRP Cost as specified u/s 30(2)(a) of the Code. b) Repayment of Debts of Operational Creditors as specified u/s 30(2)(b) of the Code. c) For management of the affairs of the Corporate Debtor, after the approval of Resolution Plan, as specified U/s 30(2)(c) of the Code. d) The implementation and supervision of Resolution Plan by the RP and the CoC as specified u/s 30(2)(d) of the Code.
-
The RP has complied with the requirement of the Code in terms of Section 30(2)(a) to 30(2)(f) and Regulations 38(1), 38(1)(a), 38(2)(a), 38(2)(b), 38(2)(c) & 38(3) of the CIRP Regulations.
-
The RP has filed Compliance Certificate in Form-H along with the Resolution Plan. On perusal, the same is found to be in order. The Resolution Plan has been approved by the CoC by majority of 82.19%.
-
In Clause 10.1 of the Resolution Plan, the SRA has prayed for transfer of all assets to the Resolution Applicant on approval of the Resolution Plan by NCLT, which in our considered view stands transferred to the Resolution Applicant in terms of and subject to compliance of the conditions stated in the Resolution Plan. As regards the effect and consequences arising from the Resolution Plan described in the Resolution Plan at various places, such stated effect of the Resolution Plan shall be operative and binding in accordance with the principle laid down by Hon’ble Supreme Court in case of Ghanshyam Mishra and Sons Private Limited v/s. Edelweiss Asset Reconstruction Company Limited{(2021) 13 S.C.R 737}. Further, it is clarified and ordered that -
a. Any increase in the authorized capital shall be subject to payment of prescribed fee, if any applicable, and filing of prescribed forms with the Registrar of Companies.
b. The Applicant shall file necessary forms and pay prescribed fees, if any, in terms of provisions of the Companies Act, 2013 in
MUMBAI BENCH- I IA No. 63 of 2025 Page 17 of 21
relation to reduction in capital and issuance of fresh capital,
however, the Registrar of Companies shall waive the additional
fees, if any, payable on such filing.
c. The
SRA
may
approach
prescribed
authorities
for
waiver/reduction in fees, charges, stamp duty, and registration
fees, if any arising from actions contemplated under the
Resolution Plan and such request shall be subject to the relevant
law/statute and adherence to the procedure prescribed thereunder.
d. The SRA may file appropriate application, if required, for renewal
of all Business Permits, rights, entitlements, benefits, subsidies and
privileges whether under applicable Law, contract, lease or license
granted in favour of the Corporate Applicant or to which the
Corporate Applicant is entitled to or accustomed to, which have
expired on the Effective Date, and follow the due procedure
prescribed for the purpose upon payment of prescribed fees. The
contract with third parties shall be subject to consent of such
parties. It is clarified that continuance of approvals shall not be
refused on account of extinguishment of any dues under Code and
extension or renewal thereof shall not be denied on account of past
insolvency of the Corporate Applicant. No action shall lie against
the Corporate Applicant for any non-compliances arising prior to
the date of approval of Resolution Plan, however, such non-
compliances shall be cured, if necessitated to keep the approval in
force, after acquisition by the Corporate Applicant within period
stipulated in the Resolution Plan.
e. No orders levying any tax, demand of penalty from the Corporate
Applicant in relation to period up to approval of the Resolution
Plan shall be passed by any authority and such demand, if created,
shall not enforceable as having extinguished in terms of approved
Resolution Plan.
f. The carry forward of losses and unabsorbed depreciation shall be
available in accordance with the provisions of Income Tax Act,
and the Income Tax Department shall be at liberty to examine the
MUMBAI BENCH- I IA No. 63 of 2025 Page 18 of 21
same.
g. An application for compounding/condoning shall be filed in
accordance with the procedure specified in respective law or
concerned authority, however, no fine or penalty shall be imposed
for non-compliances till the date of approval of this Plan or such
further period as is permitted in terms of this Order.
h. ROC shall update the records and reflect the Corporate Applicant
as ‘Active’ upon filing of pending returns/forms after payment of
normal fees (not additional fee). In case such filing is not
permitted by the e-filing portal, the ROC shall accept such
forms/returns in physical format and manage to upload the same
by back-end. The Corporate Applicant shall be exempted from
using the words “and reduced”.
i. The Compliances under the applicable law for all the statutory
appointments by the Corporate Applicant shall be completed
within 12 months, whereafter, the necessary consequence under
respective law shall follow.
j. The Successful Resolution Applicant, the Corporate Debtor and
the assets of the Corporate Debtor forming part of Resolution plan
shall have immunity, privileges and protection as is available in
the form and manner stated in Section 32A of the Code.
k. It is clarified that any relief, concession or waiver prayed in the
Resolution Plan but not specifically dealt with in Para 19(a) to (j)
above, save as otherwise permissible in terms of Ghanshyam
Mishra and Sons Private Limited (supra) or specific provisions of
the Code read with the Regulations, shall be deemed to be denied
or rejected.
- In K Sashidhar v. Indian Overseas Bank & Others (in Civil Appeal No.10673/2018 decided on 05.02.2019) the Hon’ble Apex Court held that if the CoC had approved the Resolution Plan by requisite percent of voting share, then as per Section 30(6) of the Code, it is imperative for the Resolution Professional to submit the same to the Adjudicating
MUMBAI BENCH- I IA No. 63 of 2025 Page 19 of 21
Authority (NCLT). On receipt of such a proposal, the Adjudicating Authority is required to satisfy itself that the Resolution Plan as approved by CoC meets the requirements specified in Section 30(2) of the Code. The Hon’ble Apex Court further observed that the role of the NCLT is ‘no more and no less’. The Hon’ble Apex Court further held that the discretion of the Adjudicating Authority is circumscribed by Section 31 of the Code and is limited to scrutiny of the Resolution Plan “as approved” by the requisite percent of voting share of financial creditors. Even in that enquiry, the grounds on which the Adjudicating Authority can reject the Resolution Plan is in reference to matters specified in Section 30(2) of the Code when the Resolution Plan does not conform to the stated requirements.
-
In view of the discussions and the law thus settled, the instant Resolution Plan meets the requirements of Section 30(2) of the Code and Regulations 37, 38, 38(1A) and 39(4) of the CIRP Regulations. The Resolution Plan is not in contravention of any of the provisions of Section 29A of the Code and is in accordance with law. The same needs to be approved. Hence, ordered.
-
The Resolution Plan is hereby approved. It shall become effective from this date and shall form part of this order with the following directions: i. It shall be binding on the Corporate Applicant, its employees, members, creditors, including the Central Government, any State Government or any local authority to whom a debt in respect of the payment of dues arising under any law for the time being in force is due, guarantors and other stakeholders involved in the Resolution Plan.
ii. The approval of the Resolution Plan shall not be construed as waiver of any statutory obligations/liabilities of the Corporate Applicant and shall be dealt by the appropriate Authorities in accordance with law. Any waiver sought in the Resolution Plan,
MUMBAI BENCH- I IA No. 63 of 2025 Page 20 of 21
shall be subject to approval by the Authorities concerned in light of the Judgment of the Hon’ble Supreme Court in Ghanshyam Mishra and Sons Private Limited v/s. Edelweiss Asset Reconstruction Company Limited, the relevant paragraphs of which are extracted herein below:
“95. (i) Once a resolution plan is duly approved by the
adjudicating authority under sub-section (1) of Section 31, the
claims as provided in the resolution plan shall stand frozen and
will be binding on the corporate debtor and its employees,
members, creditors, including the Central Government, any
State Government or any local authority, guarantors and other
stakeholders. On the date of approval of resolution plan by the
adjudicating authority, all such claims, which are not a part of
the resolution plan shall stand extinguished and no person will
be entitled to initiate or continue any proceedings in respect to a
claim, which is not part of the resolution plan;
(ii) 2019 Amendment to Section 31 of the I&B Code is
clarificatory and declaratory in nature and therefore will be
effective from the date on which the Code has come into effect;
(iii) consequently, all the dues including the statutory dues
owed to the Central Government, any State Government or any
local authority, if not part of the resolution plan, shall stand
extinguished and no proceedings in respect of such dues for the
period prior to the date on which the adjudicating authority
grants its approval under Section 31 could be continued.”
iii. The Memorandum of Association (“MoA”) and Articles of Association (“AoA”) shall accordingly be amended and filed with the Registrar of Companies (“RoC”), Mumbai, Maharashtra for information and record.
MUMBAI BENCH- I IA No. 63 of 2025 Page 21 of 21
iv. The Successful Resolution Applicant, for effective implementation of the Resolution Plan, shall obtain all necessary approvals, under any law for the time being in force, within such period as may be prescribed. It is clarified that the authorities shall not withhold the approval/consent/extension for the reason of insolvency of the Corporate Applicant or extinguishment of their dues upto approval of Resolution plan in terms of the approved plan. Any relief or concession as sought on the plan shall be subject to the provisions of the relevant Act.
v. The moratorium under Section 14 of the Code shall cease to have effect from this date.
vi. The Applicant shall supervise the implementation of the Resolution Plan and file status of its implementation before this Authority from time to time, preferably every quarter.
vii. The Applicant shall forward all records relating to the conduct of the CIRP and the Resolution Plan to the IBBI along with copy of this Order for information.
viii. The Applicant shall forthwith send a certified copy of this Order to the CoC and the Resolution Applicant, respectively for necessary compliance.
Sd/- Sd/-
Prabhat Kumar
Sushil Mahadeorao Kochey
Member (Technical)
Member (Judicial)
/SP/
Verbatim extracted text (OCR/PDF). Older scans and tables may show extraction artifacts — verify against the original for anything you act on.